Item 9.c.
CENTRALSAN
jdf A- hom
CENTRAL CONTRA COSTA SANITARY DISTRICT
March 4, 2021
TO: HONORABLE BOARD OF DIRECTORS
FROM: CLINT SHIMA, SENIOR ENGINEER
REVIEWED BY: NEIL MEYER, PLANT MAINTENANCE DIVISION MANAGER
STEVE MCDONALD, DIRECTOR OF OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE SUMMARY OF 2020 ENERGY USAGE
Senior Engineer Clint Shima will present a summary of Central San's 2020 energy usage. The
presentation will include the following:
• Treatment Plant Usage - 2019 versus 2020
• MCE Impact
• Monthly Usage Statistics
• General Energy Information
• Solar Panels
Strategic Plan re-In
GOAL TWO: Environmental Stewardship
Strategy 4- Reduce reliance on non-renewable energy
GOAL SIX: Innovation and Optimization
Strategy 2—Improve and modernize operations through technology and efficiency measures
ATTACHMENTS:
1. December 2020 Energy Usage
2. Presentation
March 4, 2021 Regular Board Meeting Agenda Packet- Page 108 of 131
CCCSD December 2020 Energy Usage
HHWCF(Solar) Treatment Plant Monthly Total Energy Cost: $306,546
HHWCF(Gas and $269 86%of Total$
Electricity)$206 0% 0% $294 /MG Treated
POD Reserv.&Serv.
Charges(PG&E) POD Demand Charge
Misc(Gas and $25,035 10%
Electricity) $2,122 (MCE)$- 0% 1,966 kWh/MG Treated
1% POD Electricity
Import(MCE) CSO Facility
$9,679 4%
PG&E Charges csosolar, 2%of Total$
trans.+dist.+etc. $2,261,40% CSO Gas,
mus Reserv.& $2,242,39%
Serv.Charges)
$15,428 CSO Electricity,
6% $39,1% 7:ave 2 of 7
CSO Vehicle icle
Bay Electricity, Bay Gas,$448
$680,12% ,8%
POD Natural Gas POD Landfill Gas
$114,487 43% $34,537 Pump Stations
13% San Ramon,$9,519, 12%of Total$
25% Moraga,$8,272,
22%
12 Other Pump Stations,
O $1,629,4%
Transmission
Concord Industrial,
$1,027,3% Orinda Crossroads,
$7,278,19%
Fairview Lift Station,
$1,585,4%
Lower Orinda,
$4,213,11%
Maltby, $1,666,4% Martinez,$2,854,8%
Operating Cost of CCCSD by Month TP Electricity Source in kWh TP MMBTU of Gas Consumed
$400,000 2,500 50
$350,000 $334,137 $339,291 45
671 $306,544 2,000 40
$300,000
3 m 35
$250,000 v 1,500 30
$200,000 n 25
o
r 1,000 s 20
$150,000
15
$100,000 500 10
$50,000 5
$0 0 0
Sep-20 Oct-20 Nov-20 Dec-20 Sep-20 Oct-20 Nov-20 Dec-20 Sep-20 Oct-20 Nov-20 Dec-20
■PG&E Charges ■POD Reserv.&Serv.Charges
■POD Demand Charge ■Other Energy Charges ■Cogen ■Standby Power ■PG&E ■Natural Gas ■Landfill Gas
■POD Landfill Gas ■Natural Gas Delivery
■POD Natural Gas
TP Electricity by Source in kWh TP MMBTU of Gas Consumed TP Energy by Source in kWh
30 600 100 2 05
6.93
90 4.72
25 Soo 80
70
20 400
s 60
t 3
3 15 0 300 m 50
c
c c 0_ 40 — — —
o N
10 200
0 30 26.36—29.27—29.58—29.10— —
F 28.26
20 — — — — —
5 100
10
0 0 0
2016 2017 2018 2019 2020 2016 2017 2018 2019 2020 2016 2017 2018 2019 2020
Year Year
Year
■Cogen ■Standby Power ■PG&E ■Natural Gas ■Landfill Gas ■Aux Boilers WHB Steam ■Cogen Steam
■Cogen Electrical ■Standby Power ■PG&E
This month CCCSD produced and purchased electricity at an average rate of $0.1030 /kWh(including maintenance)
Anthropogenic GHG
Emissions Renewable Energy Landfill Gas Compared to $0,1448 /kWh if exclusively from PG&E
MTCO2e Profile 7,624 MMBtu
zs000 15%
Generation breaks even with PG&E at $7•90 /MMBTU
Recovered Waste Heat
20000 5,464 MMBtu
15000
10% Solar Natural gas was purchased $3.10 /MMBTU
39 MMBtu eq. at a rate of
N
0.08%
0 10000 Total Non-Renewable
~ 37,792MMBtu MCE Renewables Natural gas transmission
5000 74% 350 MMBtu eq. cost 1.66 /MMBTU
0.68%
0 CCCSD produces steam at
an average rate of $0.0028 /Ib steam
March 4, 2021 Regular Board Meeting Agenda Packet- Page 109 of 131
Page 3 of 7
r• -
SUMMARY OF CENTRAL SAN'S
2020 ENERGY USAGE
Board of Directors Meeting
March 4, 2021
Clint Shima, P.E.
Senior Engineer
Plant Maintenance Division
a Slide 1
OVERVIEW
Central San's Energy Usage
Tracked Monthly
Board Updated Quarterly
Treatment Plant 2019 versus 2020
Monthly Usage Statistics
MCE Impact
General Energy Information u
�rY 1
New Time-of-Use Rates 49Ri
Solar Panels
:.. `. Slide 2 '
CENTRALSAN
March 4, 2021 Regular Board Meeting Agenda Packet- Page 110 of 131
Page 4 of 7
TREATMENT PLANT 2019 VERSUS 2020
2019 2020
Natural Gas 411,000 MMBtu $2.0 M 426,000 MMBtu $2.0 M
(NG):
Landfill Gas 92,000 MMBtu $419 k 85,000 MMBtu $377 k
(LFG):
Total: 503,000 MMBtu $2.4 M 511,000 MMBtu $2.4 M
Electricity
(PG&E&MCE): 2,882,000 kWh $1,094 k 1,690,000 kWh $738 k
Cogeneration: 21,986,000 kWh 22,952,000 kWh
Total: 24,868,000 kWh 24,642,000 kWh
Slide 3
�eCENTRALSAN
MONTHLY USAGE STATISTICS
• Total Costs (NG, LFG, and Electricity)
o Range: $271,756 to $383,615
o Average: $312,000
• Average Cost/ MG: $291.25
• Average kWh / MG: 1,894
• Area Cost Breakdown
o Treatment Plant: 80% — 87%
o Pumping Stations: 11% — 17%
o Collection System Operations Facility: < 3%
Slide 4 r'
sCENTRALSAN
March 4, 2021 Regular Board Meeting Agenda Packet- Page 111 of 131
Page 5 of 7
MCE IMPACT
Savings: Approximately $80,000 compared to
Pacific Gas and Electric (PG&E) rates
MCE: Light Green is 60% renewable
Total PG&E and MCE 2020 Cost: $738,000
MCE 2020 Cost: $174,000
Slide 5
GENERAL ENERGY INFORMATION
• Cogeneration engine exchanged in November
• NG 2017 Average: $3.50 / MMBtu
• NG 2018 Average: $3.24 / MMBtu
• NG 2019 Average: $3.04 / MMBtu
• NG 2020 Average: $3.01 / MMBtu
• NG 2021 Average: $3.25 / MMBtu
2020 Greenhouse Gas: Below 25,000 CO2e MT
Renewable Energy: —27%
Slide 6 I'
CENTRALSAN
March 4, 2021 Regular Board Meeting Agenda Packet- Page 112 of 131
Page 6 of 7
GENERAL ENERGY INFORMATION
• PG&E
o On July 1, 2020, PG&E emerged from Chapter 11
Bankruptcy Protection
o Continued Public Safety Power Shutoff outages —
Portable Generators
• Energy Optimization
o Strategic Energy Management
o On-Bill Financing (OBF) Program
•a
Slide 7
CENTRALSAN
NEW TIME-OF-USE RATES
•Time-of-Use Rate Plan change from E20 to B20 in
March (originally November)
• Minimal affect on operations expected
W..1..—A.,l thr I W-M H
fthvafrmberif WIMer xmmMerftMrAMI30 of Mm Se mher30 Mm 1+ m
Before:Energy Time-Of-Use Cost(E-20) After:Energy Time-0f-Use Cost JB-20)
Mende lflday day-Mday a nerydaYl]pdr,sl
xpO
ldaW (WIMer) [Summer) [vmYdaylMerl March,Apnl,or May Every day(Summer)
Mer(Summ
um AM uwAM OFF PEAK
f2 AM.9AM
00:00 AM OO:OOAM
a9:m AM PARTIAL PEAK 09`00°311 OFFPEAK
s� 'm-1z PM 10 pp°A� OFFPEAK SUPE 1z Am
11:00 AM OFFPEAK 11 wm 12 -AImA PEAK
—I'm f2A0PM 9AM.2PM
01:OOPMeaiz Gay M:00 PM
P.Wd—GAY PARTIAL PEAK DFP PEAK
03:00 PM Memorial NY 03:WPM 2PM-4PM 1PMh1a PMa
..PM aurtM1 al ruly 9304M-9:30 PM 00:00 PM
eWr O,
vxernm Gayng GaPEAK PEAK PEAK
"in -
Gaup vM shy 0000 vM
O I'm PARTIAL PEAK oa..PM
—Z fiPM-9,30PM pg;pp pA,
ww PM OFFPEAK OFF PEAK 1a.op PM OFF PEAK OFF PARI4YPFAK
11:00 PM 11:00 PM 9PM-UPIA
1L00 AM - - 12;�A,r, 9PM-f}1UY1 9PM-SZ
Slide 8 41411CENTRALSAN'
yr —
March 4, 2021 Regular Board Meeting Agenda Packet- Page 113 of 131
Page 7 of 7
SOLAR PANELS
INSTALLED AT HOUSEHOLD HAZARDOUS WASTE FACILITY AND
COLLECTION SYSTEMS OPERATIONS FACILITY
2019 Produced: 283 MWh
2020 Produced: 271 MWh
4` -
Slide 9
CENTRALSAN
•
Slide 10 411111111w,CENTRALSAN'