Item 4.b.
Algi CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: FEBRUARY9, 2021
SUBJECT: REVIEW DRAFT POSITION PAPER TO RECEIVE AN UPDATE AND
ANNOUNCE THE ADVERTISEMENT FOR BIDDING OF THE SOLIDS
HANDLING FACILITY IMPROVEMENTS, DISTRICT PROJECT 7348; AND
AUTHORIZE THE GENERAL MANAGER TO AMEND TWO EXISTING
PROFESSIONAL ENGINEERING SERVICES AGREEMENTS TO INCLUDE
AS-NEEDED SUPPORT SERVICES WITH:
1. MW H CONSTRUCTORS, I NC. I N AN AMOUNT NOT TO EXCEED
$150,000, INCREASING THE AGREEMENT COST CEILING TO $1.1
MILLION; AND
2. ARCSI NE ENGINEERING IN AN AMOUNT NOT TO EXCEED $250,000,
INCREASING THE AGREEMENT COST CEILING TO $975,000
SUBMITTED BY: INITIATING DEPARTMENT:
NATHAN HODGES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECT DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
Due to the significance and costs of this project, staff will provide a status update to the Board of Directors
(Board) and be available for questions or comments before advertising the project for bidding. Board
authorization is also required for the General Manager to execute an amendment to a professional
engineering services agreement for amounts greater than $200,000.
BACKGROUND
The Solids Handling Facility Improvements, District Project 7348 (Solids Project) began in 2017 when
staff recommended to combine five separate capital projects from the Fiscal Year(FY) 2016-17 Capital
Improvement Budget (CI B) and brought forward three additional projects in the same year's budget due
to the interdependency and complexity for each of the solids processes. The Solids Project represents
one of the largest and most challenging construction projects since the treatment plant (plant), as it is
known, was expanded in the 1970s.
The Solids Project is listed as the highest priority project in the C I B and is needed to meet safe, reliable,
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 10 of 25
Page 2 of 14
and regulatory operations for the solids processing at Central San and includes the following major
elements:
• Sludge blending and storage— new optimized and energy efficient mixing systems;
• Sludge dewatering — centrifuge and cake pump equipment replacement and upgrades;
• Incinerator modifications— burner upgrades, new center shaft drives and combustion air blowers;
• New air pollution control equipment— replacing the wet scrubbers with up-to-date equipment that was
proven under pilot testing conditions;
• Solids Conditioning Building (SCB) and incinerator seismic modifications;
• Ash Handling Facility— new enclosed facility adjacent to the Emergency Sludge Loadout Facility
(ESLF), and removal of the deficient existing system within the SCB;
• ESLF upgrades — completed under a separate project for sludge loading and hauling;
• Emergency stairway—for the safety of the SCB occupants and construction is already in progress
under a separate project;
• Major electrical, instrumentation and controls (E I C) coordination and replacement with the new
systems, including a newARC flash resistant electrical room; and
• Construction sequence and constraints for all the impacted systems and operations, including
allowing a 12-month period to shut down the incinerators and off-haul sludge.
Clean Water State Revolving Fund(SRF) Funding:
The Clean Water SRF program is a federal-state partnership that provides communities low-cost
financing for a wide range of water quality infrastructure projects. Staff has been coordinating and working
with the State for SRF funding for this project for over a year. Central San received approval for additional
funding to satisfy all estimated construction expenses which totals $173 million. The agreement to secure
SRF funding consists of an initial agreement that sets the funding ceiling and is executed in advance of
project award. In December 2020, staff submitted updated project documents in support of receiving the
initial agreement prior to advertising the project, and recently received notice that the initial agreement is
expected to be ready for Central San's execution in April 2021. Upon successful bidding and award of the
project, the final construction budget will be established, and a final SRF agreement will be executed.
Contractor Pre-qualification:
On September 3, 2020, pre-qualification documents were posted for general contractors (GCs) and
electrical subcontractors (ECs). Staff received responses from seven GCs and eight ECs. After a
thorough evaluation of the submitted qualifications, all GCs and ECs were informed they qualified for
bidding the project.
An informational update meeting was held via Microsoft Teams for all pre-qualified contractors on January
20, 2021. Staff presented the updated bid schedule, available items such as the model, construction
estimate, and other pertinent information for the project.A brief video of the 4-Dimensional (4D) sequence
and schedule model was shared to demonstrate the elements and complexity of the construction
proposed under the contract.
Other contractor pre-qualifications were considered, such as seismic or furnace subcontractors. However,
staff elected to include the qualifications as part of the experience requirements listed under the bid
requirements.
Project Bid Schedule:
The project is scheduled to be advertised on February 22 and March 1, 2021. The bid opening is
scheduled at the end of April 2021 but may be extended into May, depending on questions or input from
bidders, to allow all bidders ample time to prepare a bid for the project. Staff plans to present the project
for award in July or August of 2021.
The bid schedule anticipates a two-month bid evaluation including SRF review. The project documents,
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 11 of 25
Page 3 of 14
bid forms, and security shall include a 120-calendar day period in which bids cannot be withdrawn to
accommodate the SRF review, which is common practice for these types of large SRF funded projects.
M WH Constructors, Inc. (M WH)Agreement Revision:
MW H was hired in January 2020 to provide construction management services for the project. The scope
of services includes constructability review, assist with pre-bid services, and construction management for
the Solids Project. MW H has reviewed various design submittals, conducted constructability reviews,
performed schedule analysis, and provided cost estimates and alternative shutdown scenarios for the
project. MW H has been an active participant in workshops, project meetings, and other critical efforts to
assist Central San to prepare and understand the construction impacts of this major endeavor.
MW H's input and work has been critical in confirming the construction cost estimate and providing
comments to improve the construction documents for contractor bidding and constructability. MW H and
Central San estimated the construction cost to be $125 million.
Additional authorization is needed for MW H to continue their pre-bid support services. The identified
services needed at this time include:
1. Review of final submittal used for bidding;
2. Additional constructability input needed during bidding;
3. Support for contractor questions related to the estimate, schedule model analysis, and project
sequencing for potential shutdowns and electrical work;
4. Assist with front-end contract document changes, if needed; and
5. Provide supplemental services to assist staff during bidding with site inspections, tracking bid
questions and designer changes.
MW H is already on-site at the plant assisting with construction management of the Filter Pant and
Clearwell I mprovements — Phase 1 A Project and assisting with the Solids Project bid will be an efficient
use of time and will be done on an as-needed basis.
Aresine Engineering (ArcSine)Agreement Revision:
ArcSine's agreement to provide as-needed electrical engineering support was executed in February 2019
and they are under agreement through 2023. Their work supports all capital projects, especially pump
station projects, the Steam Project, and the Solids Project. ArcSine provides important supplemental
electrical and control system engineering support since Capital Projects has a single electrical engineer
supporting all projects in design and construction, as well as Operations on many occasions. The plant's
control systems group is equally occupied with maintaining the existing plant control system infrastructure
and making improvements.
This as-needed agreement has been used to support the Solids Project and additional services are
anticipated to support staff's efforts to bid or provide supplemental information needed for bidders.
This revision will provide the budget to continue support for the Solids Project and other Central San
needs for the remainder of the agreement duration.
Black& Veatch Corporation (B&10 Agreement:
B&V, along with HDR, I nc. and Degenkolb Engineers, are the project's Design Engineers. On August 20,
2020, the Board authorized an increase of $350,000 to the existing agreement for bidding services; no
additional fees are being requested under the designer agreement.
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 12 of 25
Page 4 of 14
ALT ERNAT IVESiCONSIDERAT IONS
The Board could consider the following alternatives or provide other direction.
Agreement Revisions
The Board could elect to not authorize the revisions to the MWH and ArcSine agreements. Staff would
have to find alternative solutions which is not recommended since the Capital Projects Division does not
have the staff to reassign during the bid schedule, nor the software expertise for the project scheduling
and modeling being done by MWH.Also, there is only one Central San electrical engineer with the
experience sufficient for this project.ArcSine understands Central San's electrical standards and has the
staff with the necessary experience to provide supplemental services needed for this project.
FINANCIAL IMPACTS
On August 6, 2020, the Board authorized staff to submit an updated SRF Loan Application to the State
Water Resources Control Board for the full project costs of $173.1 million. The total estimated project
costs include planning, $1 million pilot testing of the new air pollution control equipment, pre-design,
detailed design, consultant costs, construction estimate ($125 million), construction management, and
contingency. To date, Central San has spent approximately$16 million to construct the early release
projects and for the work leading to the final design and bid package.
Once, the bids are received and Central San has determined the final contract price from the lowest and
responsible bidder, the total project estimate will be adjusted.
M WH
The current cost ceiling is $950,000. The proposed revision of $150,000 will bring the cost ceiling to $1.1
million.A subsequent revision will be brought to the Board at time of project award for other construction
management services.
ArcSine
The current cost ceiling is $725,000. The proposed revision of $250,000 will bring the cost ceiling to
$975,000. A subsequent revision will be brought to the Board at time of project award for supplemental
services to support Central San staff.
COMMITTEE RECOMMENDATION
The Engineering & Operations Committee reviewed this item at its February 9, 2021 meeting and
recommended
RECOMMENDED BOARD ACTION
Authorize the General Manager to amend two existing professional engineering services agreements
under the Solids Handling Facility Improvements, District Project 7348 to include as-needed support
services, as follows:
1. MWH Constructors, I nc. in an amount not to exceed $150,000, increasing the agreement cost
ceiling to $1.1 million; and
2. ArcSine Engineering in an amount not to exceed $250,000, increasing the agreement cost ceiling to
$975,000.
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 13 of 25
Page 5 of 14
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 2—Maintain a positive reputation
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations, Strategy 2—Anticipate and prepare for potential regulatory
changes
GOAL THREE: Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
GOAL FIVE:Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life, Strategy 2—Execute long-term capital renewal and
replacement program
GOAL SIX: Innovation and Optimization
Strategy 2—Improve and modernize operations through technology and efficiency measures
ATTACHMENTS:
1. Presentation
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 14 of 25
Page 6 of 14
SOLIDS HANDLING FACILITY IMPROVEMENTS
" DISTRICT PROJECT 7348
ADVERTISING FOR BID
Engineering &Operations Committee
February 9, 2021
Jean-Marc Petit, P.E.
Director of Engineering and Technical Services
s,
Edgar J. Lopez, P.E.
Capital Projects Division Manager
SOLIDS HANDLING FACILITY
IMPROVEMENTS (SOLIDS PROJECT
1 2 2 3 4 5 6 7 8
06
EXISTING SLUDGE MULTIPLE AIR POLLUTION ASH HANDLING EMERGENCY CENTRIFUGE
SOLIDS
DIGESTER BLENDING/ HEARTH CONTROL AND LOADOUT SLUDGE DEWATERING CONDITIONING
DEMOLITION STORAGE FURNACES
LOADOUT SYSTEM BUILDING
SEISMIC
RETROFIT
2
1
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 15 of 25
Page 7 of 14
OTHER RELATED ACTIVITIES TAKING PLACE
Staging Area Improvements:
• Design completed
• Improve contractor staging area
• Additive bid item for RV Dumping
Station
• Bidding soon
• Construction Summer 2021
Abandoned Digester Demolition:
• Design completed
• Uniform Public Construction Cost Treatment Plant Safety Enhancements
Accounting Act project _Phase 5:
• Contract being executed for Install emergency stairway from the
$193,000 Solids Control Building Control
Room
• Construction is underway
CENTRALSAN
` 3
SOLIDS PROJECT STATUS
• Total State Revolving Fund (SRF) Funding Estimate -
$173 Million (M)
❖ $125 M District construction estimate
• Construction duration = 1,400 calendar days
• Informational meeting held with pre-qualified contractors
on January 22, 2021:
-*.-Presented bid timeline, 4-Dimensional schedule
model, and other information that contractors will be
able to receive
• Notification to the Board on February 18, 2021, staff will
be available for questions or comments
�l
II 4
CENTRALSAN
2
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 16 of 25
Page 8 of 14
PRE-QUALIFIED GENERAL CONTRACTORS AND
ELECTRICAL SUBCONTRACTORS
General Contractors: Electrical Subcontractors:
• Balfour Beatty • Blocka Construction, Inc.
• Flatiron West, Inc. • Con J. Franke Electric, Inc.
• Kiewit Infrastructure West Co. • Contra Costa Electric
• C. Overaa&Co. • Helix Electric
• Shimmick Construction Company, • Mass. Electric Construction
Inc. Company
• Walsh Construction • San Joaquin Electric, Inc.
• W. M. Lyles Co. • Shimmick Construction Company,
Inc.
• Sprig Electric
s
CENTRALSAN
PROJECT BIDDING SCHEDULE
Bid opening through award dates are subject to change:
Milestone
Advertise February 22 and March 1, 2021
Site Visits March 1 —April 23, 2021
Bid Opening April 28, 2021
Bid Evaluation including April 29 —July 5, 2021
SRF
Engineering & Operations July 13, 2021
Committee Review
Board Award August 5, 2021
CENTRALSAN
3
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 17 of 25
Page 9 of 14
PROJECT SUPPORT NEEDED
MWH Constructors, Inc.:
Sequence and schedule support for model.
Assist in front-end documents.
Assist staff during bidding with site visits and tracking
correspondence and changes and other services.
ArcSine Engineering:
Assist Capital Projects (CP) with review of electrical
and controls items and questions.
Supplement staff since CP has one person with skills
needed for this project.
Provide other services as needed.
RECOMMENDED BOARD ACTION
Authorize the General Manager to amend two existing
professional engineering services agreements for as-
needed services as follows:
1. MWH Constructors, Inc. in an amount not to exceed
$150,000; and
2. ArcSine Engineering in an amount not to exceed
$250,000.
CENTRALSAN
4
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 18 of 25
Page 10 of 14
QUESTIONS?
�J
CENTRAL SAN
SUPPLEMENTAL INFORMATION
r 10
5
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 19 of 25
Page 11 of 14
CRITICAL SYSTEMS - BOILER, COGEN AND
FUEL LINES
Critical Pipeline
dao ���sm
■r�
■Pai ai vive���
11
i
STRUCTURAL SEISMIC SCOPE
Irk.-'
i`
CENTRAL SAN
12
6
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 20 of 25
Page 12 of 14
POLY DOSING SYSTEM AND CENTRIFUGE
a
41
13
ELECTRICAL CABLE TRAY
DEMOLITION FRONT VIEW
T � ,
F 7-
T
7w"
I'14
CENTRALSAN
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 21 of 25
.
■ 4
ilt
CENTRALSAN
NEW WET SCRUBBERS
16
5
CENTRALSAN
Page 14 of 14
NEW ASH LOADOUT BUILDING
� I
11�
OVERALL CONSTRUCTION MODEL
GMWH
CONSTRUCTORS
CENTRAL SAN
11$
9
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 23 of 25