HomeMy WebLinkAbout04.a. Review draft Position Paper to approve a contingency project in the amount of $450,000 for the El Toyonal Sewer Replacement Project; authorize the General Manager to execute a construction contract change order in the amount of $338,000 with Pacifi Page 1 of 6
Item 4.a.
Algi CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: FEBRUARY9, 2021
SUBJECT: REVIEW DRAFT POSITION PAPER TO APPROVE A CONTINGENCY
PROJECT IN THE AMOUNT OF $450,000 FOR THE EL TOYONAL SEWER
REPLACEMENT PROJECT; AUTHORIZE THE GENERAL MANAGER TO
EXECUTE A CONSTRUCTION CONTRACT CHANGE ORDER IN THE
AMOUNT OF $338,000 WITH PACIFIC TRENCHLESS, INC.; AND FIND
THAT THE PROJECT IS EXEMPT FROM THE CALIFORNIA
ENVIRONMENTAL QUALITYACT (CEQA)
SUBMITTED BY: INITIATING DEPARTMENT:
JASON FITCH, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
Authorization from the Board of Directors (Board) is required to include a contingency project in the
Capital Improvement Program or execute a construction contract change order for an amount greater than
$200,000.
BACKGROUND
The existing sewer located within the public right-of-way along EI Toyonal in the City of Orinda (City)
requires replacement (location shown in Attachment 1). This sewer, originally installed in 1950, is
approximately 1,400 lineal feet, 6-inch diameter clay pipe, and was identified for replacement under a
future North Orinda sewer renovation project and phase within the next two years.
The Collection System Operations Department (CSOD) and Capital Projects Division were recently
informed that East Bay Municipal Utility District (EBMUD) hired a contractor, Teichert Construction
(Teichert), to install two water mains on EI Toyonal and construction is ongoing. EBMUD's project also
includes plans to repave portions of EI Toyonal this April.
Staff routinely coordinates projects within the service area with EBMUD. Historically, EBMUD uses their
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 4 of 25
Page 2 of 6
in-house staff to construct water mains similar to the project Teichert is performing. I n this case, staff was
unaware of the project since it was work being coordinated by a contractor rather than EBMUD staff that
normally notifies the District. Staff will contact EBMUD to discuss the planning and coordination of future
third-party construction projects to avoid this from happening again.
As Teichert's construction progressed, CSOD was able to inspect several sections of Central San's
sewer that were exposed during Teichert's work. The condition of the sewer was found to be deficient in
many areas and, therefore, it is highly recommended to address this sewer sooner than planned and prior
to EBMUD's completion of the final paving of the roadway.
The Capital Projects Division confirmed that the sewer requires full replacement and, due to the urgency
of the work, provided a design to obtain change order bids from available Central San sewer contractors.
Replacement of the sewer will consist of a combination of pipe-bursting and open-trench methods to
install a new 8-inch sanitary sewer and manholes.
The engineer's estimate for the sewer replacement is $385,000; two bids were received. The lowest cost
was $338,000 from Pacific Trenchless, Inc., which is the general contractor working on the Martinez
Sewer Renovations - Phase 6, District Project 8458. The second bid was approximately$354,600. The
work is expected to begin as soon as possible and will be completed by April 1, 2021, prior to EBMUD
repaving the road.
CEQA
Staff has concluded that this project is exempt from CEQA under Central San CEQA Guidelines Section
15302 because it involves replacement of existing facilities at substantially the same locations and with the
same purpose and level of activity as the facilities being replaced.Any capacity increases are for non-
growth inducing, wet weather purposes. The project also is exempt under Central San CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that the activity in
question may have a significant effect on the environment. This certainty is based on Central San's
experience with numerous sewer construction projects of this nature, the relatively short distance involved,
and Central San's mitigating construction specifications. These specifications are standardized general
and special conditions that are made part of the project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with applicable federal,
state, county, district, municipal and local laws, ordinances, orders, and regulations. Approval of this project
will establish the Board's independent finding that this project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
The Board could consider the following alternatives or provide other direction:
Alternative 1 — Do not approve a contingency project or construction contract change order to perform the
work under the EBMUD scheduled timeline or perform the work later under another sewer renovation
project and bid. This is not recommended for several reasons, which includes additional traffic and
residential impacts to the EI Toyonal neighborhood, and a project cost increase for paving restoration due
to the City's paving moratorium after EBMUD's project. Central San also does not currently have any
bidding contracts that can perform the work by April.
Alternative 2 — Discuss postponing the paving with EBMUD so that Central San can conduct a traditional
design, public bid, and award process. This is not recommended since any postponement would impact
the City and its residents with longer construction activities or temporary paving conditions.
Therefore, staff recommends a contingency project for the EI Toyonal sewer work and authorizing a
contract change order since the pricing received is very competitive and below Central San's estimate for
the work.
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 5 of 25
Page 3 of 6
FINANCIAL IMPACTS
The total estimated cost for this contingency project is $450,000, which includes design, contractor
construction costs, permits, construction management, and contingency as shown in Attachment 2. There
is $2.1 million allocated in the Fiscal Year 2020-21 Capital I mprovement Budget (CI B) contingency
account; therefore, adequate funding is available for this project. Upon Board approval, the required
$450,000 will be transferred to the new project, resulting in a remaining balance of$1.65 million.
COMMUNITY OUTREACH
Staff has been in communication with the City during design and to coordinate the proposed construction
work. Since there is currently construction in the area, and this work will be done prior to completion of
EBMUD's project, the residents are aware of construction activities in the roadway. Staff will provide
additional construction signs and notify the nearby residents or property owners of Central San's
construction work to provide awareness and the opportunity to receive feedback or answer questions, as
typically done under all sewer renovation projects.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the February 9, 2021 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the project is exempt from CEQA:
2. Approve a contingency project in the amount of$450,000 for the EI Toyonal Sewer Replacement
Project;
3. Authorize the General Manager to execute a construction contract change order with Pacific
Trenchless, I nc. in the amount of $338,000; and
4. Authorize a transfer of $450,000 from the Fiscal Year 2020-21 C I B Contingency to fund the project.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service, Strategy 2—Maintain a positive reputation
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
GOAL FIVE:Infrastructure Reliability
Strategy 2—Execute long-term capital renewal and replacement program, Strategy 3—Protect personnel and assets
from threats and emergencies
GOAL SEVEN:Agility and A daptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 6 of 25
Page 4 of 6
ATTACHMENTS:
1. Location Map
2. Post-Bid/P reconstruction Estimate
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 7 of 25
Page 5 of 6
EI Toyonal Sewer Replacement
Map Date: 1/26/2021
C,1-0
°rij� Stantonq,e- Walnut Creek
Oil"
y �0, Detail
Area
�
o COrin d a r� CaT'no•p Lafayette
ab/°.
GCeS°er�V / Moraga
Ardilla Rd
Canon-Dr
Valles/to�h
Las Mesas /
Path Path)
Gler��\\o`N
EI ToyOna/ n
3.
G t' o
L-aV F o
OO~
L• 'Poo
4bD o 00 °d+
G o
N G°N• �
EI-TOYona/
Carnino•del-Cieto O�eQ� ear
va-Madrora�
� MaN°
C South Trl--_
Mains to be Replaced
Note: 0 500 Map Displayed in North American Datum of 1983 Attachment
Central San data as of January,2021. Feet California State Plane,Zone III RIPS 0403,US Feet 1
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 8 of 25
Page 6 of 6
ATTACHMENT 2
EL TOYONAL SEWER REPLACEMENT
POST-BID/PRECONSTRUCTION ESTIMATE
% of
Item Description Amounts Construction
No. Cost
1. CONSTRUCTION
a. Construction Contract Change Order $338,000
b. 15% Contingency $50,000
c. Permits $5,000
SUBTOTAL - CONSTRUCTION COST $393,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $10,000
- Public Relations/Right-of-Way $4,000
- Operations (CSO) $4,000
b. Consultants
- Inspection $25,000
- Material Testing/Arborist/Others $4,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $47,000 12%
3. PREBID EXPENDITURES
a. Engineering (Design, Survey, Right-of-Way, Drafting) $10,000
SUBTOTAL - PREBID EXPENDITURES $10,000 3%
4. TOTAL ESTIMATED PROJECT COST $450,000
February 9, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 9 of 25