HomeMy WebLinkAbout04.c. (Handout) Updated Presentation Item 4.c.
(Handout)
Updated Presentation
FISCAL YEAR (FY) 2020-2021
CAPITAL IMPROVEMENT
BUDGET UPDATE
Engineering & Operations Committee
v January 19, 2021
Edgar J. Lopez, P.E.
b
Capital Projects Division Manager
FY 2020-21 CAPITAL IMPROVEMENT BUDGET (CIB)
WITH CURRENT EXPENDITURES AS OF 12/31/20
Budget Actual Expenditures %Actual
Program to Date as of 12/31/20* Budget Spent
to Date
Collection System (CS) $49,686,784 $15,624,908 31%
Treatment Plant(TP) $39,194,584 $8,601,835 22%
General Improvements $6,108,365 $3,446,341 56%
Recycled Water $11,506,037 $671,178 6%
CIB Contingency $2,100,000 NA NA
Totals: $108,595,770 $28,344,262 26%
*Draft current fiscal year expenditures as of December 31,2020
z
1
COLLECTION SYSTEM -
SEWER RENOVATION PROJECTS
In Construction:
• Danville, Phase 3 — 6,400 feet of sewer mains (100% complete)
• Martinez, Phase 6 — 9,000 feet of sewers (85% complete)
• Walnut Creek, Phase 14 —9,814 feet of sewers (65% complete)
• Lafayette, Phase 14 — 12,585 feet of sewers (55% complete)
In Design:
• South Orinda, Phase 8 bidding in January and awarding in March,
includes 5,100 feet of sewers
• Bid projects from Collection System Sewer Renovation — Phase 1,
include next phases of Danville, Martinez, North Orinda,
South Orinda, and Walnut Creek
MARTINEZ, PHASE 6
2
WALNUT CREEK, PHASE 14
New Manhole Base ,y Final Paving
r
Cured-in-Place Pipe
I $
een�e is
�on�o�d
Pump Station
P,ea.an. (PS) Upgrades
• wa na —
6e,keley O Phase 1 Pump Stations
O IV nan e Phase 2 Pump Stations
O
Oaki—d
77
o no�
� • ;a��MP�a��.a,d�,1v����,a�Fa�,�„ m P
c conec��o�ci, a
�.. EESD Pumolno smtlons
_
`xw�neawa iar,_�,e�o vE=ni_ - cnee'W - an
iiaz o`�eswe���a co��om am ciano� n=V, o,an =
P.mping SWti— -
f\ 6
3
PUMP STATION UPGRADES -
PHASE 1 , DISTRICT PROJECT (DP) 8436
• Total Project Budget: $35 million (M)
• Contractor: Mountain Cascade, Inc. ! '-
• Contract Price: approx. $25.6 M e(
• Estimate completion by Dec. 2021 W
Major electrical and mechanical
renovation at Moraga, Orinda
Crossroads, and Flush Kleen Pump _
Stations
iIV. .�
PUMP STATION UPGRADES -
MAJOR ITEMS IN PROGRESS
i
f
,
New Generator and Electrical Equipment
Y^ at Flush Kleen PS
Removed Suspended
Ceilings at Moraga and New Pumps
Orinda Crossroads at Flush Kleen PS
Pump Stations
s
4
OTHER CS PROJECTS AND ITEMS TO COME
Protects in Process
• Bid new Cured-in-Place Pipe Contract this fiscal year;
current contract is closed
• Continue Pump Station Upgrades — Phase 2 design, which
includes renovation of three Martinez pump stations
• Planning phase work for Large Diameter Pipeline Inspection
Program
Items to Come
• Solicit Requests for Proposal for various as-needed services
19
SOLIDS HANDLING FACILITY IMPROVEMENTS
(SOLIDS PROJECT), DP 7348
1 2 2 3 4 5 6 7 8
06
-
44
EXISTING SLUDGE MULTIPLE AIR POLLUTION ASH HANDLING EMERGENCY CENTRIFUGE
SCB SEISMIC
DIGESTER BLENDING/ HEARTH CONTROL AND LOADOUT SLUDGE DEWATERING RETROFIT
DEMOLITION STORAGE FURNACES
LOADOUT SYSTEM
I10
5
SOLIDS PROJECT SCHEDULE
• State Revolving Fund (SRF):
• Increased SRF funding request
• Met with SRF legal team on October 22, 2020
• Awaiting SRF initial funding; draft Agreement
expected soon a--
• Final Agreement will be executed after bid 1 j
opening and award of project
• Design:
• Advertisement depends on acceptance
of 100% Final Design and review
• SRF information to be fully addressed in
bid documents
• Bid Period: February 2021 —April 2021
• Anticipated Award: July—August 2021
• Notice to Proceed: estimated October 2021
• Construction Complete: estimated October
2025
• Construction Period: 1,400 days -1
' 11
OTHER RELATED ACTIVITIES TAKING PLACE
Staging Area Improvements:
• Design in progress to improve:
• Contractor staging area
• Security and access to the treatment plant
• Bid early 2021
• Construct spring/summer 2021
Abandoned Digester Demolition:
• Staff evaluating bids received
• Uniform Public Construction Cost Accounting Act(UPCCAA)
Informal Project or Change Order
Treatment Plant Safety Enhancements - Phase 5:
• Install emergency stairway from the Solids Control Building Control
Room
• Construction is underway
12
6
MECHANICAL AND CONCRETE RENOVATIONS,
DP 7351
Construction completed
• Minor warranty work to complete
Installed new gates at the influent
and nearby structures
Rehabilitated Primary
Sedimentation Tanks (PSTs) 3
and 4, concrete and adjacent
structures
• Replaced and installed new gates
in the PSTs
• Also completed:
Fo
• Odor control scrubber
rehabilitation
�. PSTs 3 and 4 flight rail
loom system replacement
':13
OUTFALL IMPROVEMENTS - PHASE 7, DP 7353
, T
Contractor: Power Engineering Construction
Company
Contract: $4.5 M
7
OUTFALL IMPROVEMENTS - PHASE 7 (CONTD.)
15
OTHER TP PROJECTS AND ITEMS TO COME
Design for the Electric Blower Improvements, DP 7377,
60% complete
Completed condition assessments under Steam and Aeration
Blower Systems Renovation, DP 7349
Started construction of the Influent Pump Electrical
Improvements, DP 7328
Completed construction of the Plant Control System Input/Output
Replacement - Phase 1, DP 7339
• Started or completed several UPCCAA informal projects
16
8
FILTER PLANT AND CLEARWELL IMPROVEMENTS —
PHASE 1A, DP 7361
New electrical substation and
motor control center(MCC)
48
Replace backwash pumps _
(480V)
• Two new steel storage tanks-
3,000,000 gallons each
• Clearwell(CW):
• East Clearwell
decommissioned
• West Clearwell in
service
• Rehab 1 Filter&Mechanical
• Upgrade chemical systems for
coagulation and disinfection
Replace Substation 40-2400V
with 480V
Project Scope
' 17
FILTER PLANT AND CLEARWELL IMPROVEMENTS —
PHASE 1A, DP 7361
Contractor: C. Overaa & Company
Contract Price: $26,584,000
Total Estimated Project Budget: $38,589,000
Notice to Proceed: October 13, 2020
Completion Date: October 30, 2022
Work Completed:
• Executed Contract
• Submittal Reviews - Ongoing
• Permits Obtained
• Earthwork Underway - Clearwell demo and using
soils to raise Levee C
' 18
9
CONSTRUCTION PHOTOS
Levee of Basin C
East Cell of
--
Clearwell
19
Fm
iLQUESTIONS?
I 20
W6L
10