HomeMy WebLinkAbout04.c. Receive update on FY 2020-21 Mid-Year Capital Improvement Budget Page 1 of 17
Item 4.c.
CENTRAL SAN
January 19, 2021
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE UPDATE ON FISCAL YEAR 2020-21 MID-YEAR CAPITAL
IMPROVEMENT BUDGET
Attached is a presentation on the Fiscal Year 2020-21 Mid-Year Capital Improvement Budget Update.
Strategic Plan Tie-In
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations, Strategy 2—Anticipate and prepare for potential regulatory
changes
GOAL THREE: Fiscal Responsibility
Strategy 2—Ensure integrity and transparency in financial management
GOAL FOUR: Workforce Development
Strategy 3—Inspire employee engagement
GOAL FIVE:Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life, Strategy 2—Execute long-term capital renewal and
replacement program, Strategy 3—Protect personnel and assets from threats and emergencies
GOAL SIX: Innovation and Optimization
Strategy 1—Implement the Central San Smart Initiative
ATTACHMENTS:
1. Presentation
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 28 of 66
Page 2 of 17
FISCAL YEAR (FY) 2020-2021
CAPITAL IMPROVEMENT
BUDGET UPDATE
Engineering & Operations Committee
January 19, 2021
Edgar J. Lopez, P.E.
Ilk
Capital Projects Division Manager
1
FY 2020-21 CAPITAL IMPROVEMENT BUDGET (CIB)
WITH CURRENT EXPENDITURES AS OF 12/31/20
Budget Actual Expenditures %Actual
Program to Date as of 12/31/20* Budget Spent
to Date
Collection System $49,686,784 $15,624,908 31%
Treatment Plant $39,194,584 $8,601,835 22%
General Improvements $6,108,365 $3,446,341 560/(
Recycled Water $11,506,037 $671,178 6%
CIB Contingency $2,100,000 NA NA
Totals: $108,595,770 $28,344,262 26%
*Draft current fiscal year expenditures as of December 31,2020 '
z
2
1
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 29 of 66
Page 3 of 17
COLLECTION SYSTEM (CS) PROGRAM
HIGHLIGHTS
3
COLLECTION SYSTEM -
SEWER RENOVATION PROJECTS
In Construction:
• Danville, Phase 3 — 6,400 feet of sewer mains (100% complete)
• Martinez, Phase 6 — 9,000 feet of sewers (85% complete)
• Walnut Creek, Phase 14 — 9,814 feet of sewers (65% complete)
• Lafayette, Phase 14 — 12,585 feet of sewers (55% complete)
In Design:
• South Orinda, Phase 8 bidding in January and awarding in March,
includes 5,100 feet of sewers
• Bid projects from Collection System Sewer Renovation — Phase 1,
include next phases of Danville, Martinez, North Orinda,
South Orinda, and Walnut Creek
I 4
4
2
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 30 of 66
Page 4 of 17
DANVILLE, PHASE 3
Pipe Pullback for HDD Lateral Pit-Launched HDD Drill Rig
Abandon Existing Sewers Sewer Main Open Cut
t,
HDD=Horizontal Directional Drilling e
5
MARTINEZ, PHASE 6
6
6
3
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 31 of 66
Page 5 of 17
WALNUT CREEK, PHASE 14
1
New Manhole Base Final Paving
Cured-in-Place Pipe
-
-<r...
I 7
7
LAFAYETTE, PHASE 14
Sewer Main Closed-Circuit Television Sewer Main Open Cut
- t
ate'
Sewer Main Trench . .,,
r.
y.
s
� 8
8
4
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 32 of 66
Page 6 of 17
� �Pa:, e ns;• V P,n, a
s �nn�nLd a ,o
Pump Station
(PS) Upgrades
gNLNN'NY O Phase 1 Pump Stations
O ® Na O Phase 2 Pump Stations
Oakland
ti
o
� ea�����e�o�F m Pnw@•a mPn,¢asa�
ireamertcone<<loc sv cciiM
CC6n PumMnO SlatimS
e.n Ise.e,man�m cel uc�
_ nHW wl¢annwr3z6 BVO people nn MahbyW as
cane
��r tm Vrre pen¢nGoneoN ane Clallon nmr —1 ATELYaOWNER
�NwagneRancn
RRw .la��cary
r l7�iCe Pumping Slab—
I9
9
PUMP STATION UPGRADES -
PHASE 1 , DISTRICT PROJECT (DP) 8436
• Total Project Budget: $35 million (M)
!
• Contractor: Mountain Cascade, Inc.
• Contract Price: approx. $25.6 M G
• Estimate completion by Dec. 2021
• Major electrical and mechanical
renovation at Moraga, Orinda
Crossroads, and Flush Kleen Pump
Stations - ®
i F J
10
5
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 33 of 66
Page 7 of 17
PUMP STATION UPGRADES -
MAJOR ITEMS COMPLETED
I•
�t y
Moraga PS Wet Well Coated Coating Wet Well at Grinder Structure
Orinda Crossroads PS Built and Coated at
Moraga PS
11
PUMP STATION UPGRADES -
MAJOR ITEMS IN PROGRESS
T
New Generator and Electrical Equipment $
at Flush Kleen PS
Removed Suspended
Ceilings at Moraga and New Pumps
Orinda Crossroads at Flush Kleen PS
Pump Stations
' 12
12
6
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 34 of 66
Page 8 of 17
OTHER CS PROJECTS AND ITEMS TO COME
Projects in Process
• Bid new Cured-in-Place Pipe Contract this fiscal year;
current contract is closed
• Continue Pump Station Upgrades— Phase 2 design, which
includes renovation of three Martinez pump stations
• Planning phase work for Large Diameter Pipeline Inspection
Program
Items to Come
• Solicit Requests for Proposal for various as-needed services
_.. ' 13
13
TREATMENT PLANT (TP) PROGRAM
HIGHLIGHTS
14
7
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 35 of 66
Page 9 of 17
SOLIDS HANDLING FACILITY IMPROVEMENTS
(SOLIDS PROJECT , DP 7348
1 2 2 3 4 5 6 7 8
O
y r
EXISTING SLUDGE MULTIPLE AIR POLLUTION ASH HANDLING EMERGENCY CENTRIFUGE
DIGESTER BLENDING/ HEARTH SCB SEISMIC
DEMOLITION STORAGE FURNACES CONTROL AND LOADOUT SLUDGE DEWATERING RETROFIT
LOADOUT SYSTEM
*L 15
15
SOLIDS PROJECT
II ii Black&Veatch Corporation provided
100% Final Draft Design submittal for
■ � final review
MWH Constructors, Inc. (MWH)hired
for construction management,
including constructability review
Major elements include solids blending
tanks, dewatering and cake pumps,
II �� furnace modifications, new wet
■��.; {� t 1 scrubbers, building seismic upgrades,
ash handling, etc.
• Total project costs, including
h R� contingency, under review
• Update State Revolving Fund Loan
Application; reviewing Loan
!� Agreement for$171.3 M
n II
• Finalized emergency solids hauling
and disposal contract 16
16
8
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 36 of 66
Page 10 of 17
SOLIDS PROJECT STATUS
Pre-Qualifications of Contractors:
TmTrTTT • General Contractor(GC)and
�
Electrical Subcontractor(EC) pre-
T4ff,
qualification began September 2020
3 i • Seven GCs and eight ECs
- submittals received; all pre-qualified
Construction Management Review:
MWH is updating the cost estimate
based on 100% Draft Submittal
• MWH and third-party electrical
designer will provide review support
of design documents
• MWH is preparing constructability
review using a 4D-Model for
construction sequencing
17
SOLIDS PROJECT SCHEDULE
• State Revolving Fund (SRF):
• Increased SRF funding request
• Met with SRF legal team on October 22, 2020
• Awaiting SRF initial funding; draft Agreement
expected soon
• Final Agreement will be executed after bid
opening and award of project
• Design:
• Advertisement depends on acceptance
of 100% Final Design and review
• SRF information to be fully addressed in
bid documents
• Bid Period: February 2021 —April 2021
• Anticipated Award: July—August 2021
• Notice to Proceed: estimated October 2021
• Construction Complete: estimated October
2025
• Construction Period: 1,400 days
18
9
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 37 of 66
Page 11 of 17
OTHER RELATED ACTIVITIES TAKING PLACE
Staging Area Improvements:
• Design in progress to improve:
• Contractor staging area
• Security and access to the treatment plant
• Bid early 2021
• Construct spring/summer 2021
Abandoned Digester Demolition:
• Staff evaluating bids received
• Uniform Public Construction Cost Accounting Act (UPCCAA)
Informal Project or Change Order
Treatment Plant Safety Enhancements- Phase 5:
• Install emergency stairway from the Solids Control Building Control
Room
• Construction is underway
' 19
19
MECHANICAL AND CONCRETE RENOVATIONS,
DP 7351
• Construction completed
Y Minor warranty work to complete
_ Installed new gates at the influent
• and nearby structures
Rehabilitated Primary
Sedimentation Tanks (PSTs) 3
and 4 concrete and adjacent
structures
• Replaced and installed new gates
i in the PSTs
Also completed:
• Odor control scrubber
rehabilitation
• PSTs 3 and 4 flight rail
system replacement �;a
20
10
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 38 of 66
Page 12 of 17
OUTFALL IMPROVEMENTS - PHASE 7, DP 7353
J
Contractor: Power Engineering Construction
Company
Contract: $4.5 M < ' 21
21
OUTFALL IMPROVEMENTS - PHASE 7 (CONTD.)
• Regulatory project(Inspected every
5 - 10 years)
a
• Construction completed:
• Bypass and dewatering
Testing and inspection
• Access manholes
• Condition assessment
• Repair of existing seals
• Complete cathodic protection
• Install new seals (250 Quantity)
Complete seismic improvements at
Structure 9000
• Replace large valve (2 remaining)
22
22
11
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 39 of 66
Page 13 of 17
OUTFALL IMPROVEMENTS — PHASE 7 (CONTD.)
a
C`
CA 94553
iates
' 23
23
OTHER TP PROJECTS AND ITEMS TO COME
• Design for the Electric Blower Improvements, DP 7377,
60% complete
• Completed condition assessments under Steam and Aeration
Blower Systems Renovation, DP 7349
• Started construction of the Influent Pump Electrical
Improvements, DP 7328
• Completed construction of the Plant Control System Input/Output
Replacement- Phase 1, DP 7339
Started or completed several UPCCAA informal projects
24
12
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 40 of 66
Page 14 of 17
RECYCLED WATER PROGRAM
HIGHLIGHTS
25
2s
FILTER PLANT AND CLEARWELL IMPROVEMENTS —
PHASE 1A, DP 7361
New electrical substation and
motor control center(MCC)
48
Replace backwash pumps
_(480V)
Two new steel storage tanks- 'R
3,000,000 gallons each
Clearwell(CW):
• East Clearwell
decommissioned
• West Clearwell in
service ;$
• Rehab 1 Filter&Mechanical .:?3
• Upgrade chemical systems for
coagulation and disinfection .y
eplace Substation 40-2400V
Project Scope
26
26
13
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 41 of 66
Page 15 of 17
FILTER PLANT AND CLEARWELL IMPROVEMENTS —
PHASE 1A, DP 7361
Contractor: C. Overaa & Company
Contract Price: $26,584,000
Total Estimated Project Budget: $38,589,000
Notice to Proceed: October 13, 2020
Completion Date: October 30, 2022
Work Completed:
• Executed Contract
• Submittal Reviews - Ongoing
• Permits Obtained
• Earthwork Underway - Clearwell demo and using
soils to raise Levee C
Pq
00��V 0127
27
CONSTRUCTION PHOTOS
Leveeof Basin C
4
I&R
' 28
28
14
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 42 of 66
Page 16 of 17
GENERAL IMPROVEMENTS (GI)
PROGRAM HIGHLIGHTS
29
OTHER GI PROJECTS
• Ongoing Equipment and Vehicle Replacement Program projects
• IT Development: Equipment procurement in progress
• Asset Management: e-Builder Program Management
• Enterprise Resource Planning Software replacement is in progress
ORACLE'
ERP Cloud
IT=Information Technology I so
30
15
January 19, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 43 of 66
Page 17 of 17
QUESTIONS?
31
31
16