HomeMy WebLinkAbout04.a. Receive update on construction projects within the FY 2020-21 Capital Improvement Budget Page 1 of 10
Item 4.a.
CENTRAL SAN
October 13, 2020
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE UPDATE ON CONSTRUCTION PROJECTS WITHIN THE FISCAL
YEAR 2020-21 CAPITAL IMPROVEMENT BUDGET
Attached is a presentation on Fiscal Year 2020-21 Capital Improvement Budget projects update.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations
GOAL THREE: Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
GOAL FIVE:Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life
GOAL SIX: Innovation and Optimization
Strategy 2—Improve and modernize operations through technology and efficiency measures
GOAL SEVEN:Agility andAdaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
ATTACHMENTS:
1. Presentation
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 3 of 14
Page 2 of 10
d Mayor Construction
Project Updates
Engineering & Operations Committee Meeting
October 13, 2020
Edgar J. Lopez, P.E.
Capital Projects Division Manager
OUTFALL IMPROVEMENTS — PHASE 7
x x,ys
Contractor: Power Engineering
Construction Company
Schedule: July 2020 — January 2021_
z
CENTRALSAN
1
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 4 of 14
Page 3 of 10
OUTFALL IMPROVEMENTS - PHASE 7
' ° . T T
WNW
-
proted
713020,9.04 AM
Contract: $4.45 million
SO
Change Orders: $15 thousand
Paid to Date: $2.28 million (September 30)
Percent Complete: 51%
` 3
CENTRALSAN
OUTFALL -
IMPROVEMENTS
- PHASE 7
Work Completed
• Bypass and Dewatering - y
• Testing and Inspection
• Access Manholes
• Condition Assessment • r'
• Repair of Existing Seals
Work To Follow:
• Complete Cathodic s
Protection --
• Install New Seals
(250 Quantity)
• Complete Seismic f
Improvements—
Structure 9000 ,
• Replace Large Valve 4
CENTRALSAN
2
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 5 of 14
Page 4 of 10
PHASE 1 A SCOPE FOR RECYCLED WATER
PLANT FACILITIES IMPROVEMENTS
• Replace Backwash Motors ^,
(480V)
• Recycleplaced Water Storage:
o ReEast Clearwell
with two new above
ground storage tanks
(steel or pre-stressed
concrete)
•
Clearwell Overflow
Structure Modifications
• Rehabilitate one Filter
(#3)and Mechanical/
Instrumentations on others - -
• Upgrade Chemical Feed
1.
Upgrade/Replace Electrical Gear
• New Recycled Pump Station
y Applied Water Pump j h Electrical Facility
Station(AWPS) Substation 40-2400V
Variable Frequency Drives
(VFDs)for AWPS
F 5
PHASE 1 A SCOPE FOR RECYCLED WATER
PLANT FACILITIES IMPROVEMENTS
Contractor: C. Overaa & Company
Contract Price: $26,584,000
Notice to Proceed: Expected by Mid-October
Completion Date: November 30, 2022
Work Completed:
• Executed Contract
• Submittal Reviews Ongoing
• Permits Obtained
• Mobilizing Soon
6
CENTRALSAN
3
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 6 of 14
Page 5 of 10
PUMP STATION (PS) UPGRADES -
PHASE 1 , DISTRICT PROJECT 8436
Scope of Work: Major mechanical, electrical and controls
upgrades to Moraga, Orinda Crossroads, and Flush Kleen
Pump Stations
Contractor: Mountain Cascade, Inc.
Contract Price: $25,634,551 (no change orders to date)
Completion Date: December 31, 2021 (28% time elapsed)
Paid to Date: $2,289,177 (September 30)
� 7
CENTRALSAN
PUMP STATION UPGRADES -
MAJOR ITEMS COMPLETED OR PROGRESS
Moraga PS Wet Well Moraga PS Header Closed-circuit New Generator at Flush Kleen PS
Bypass Piping Television Inspection
\ 8
CENTRALSAN
4
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 7 of 14
Page 6 of 10
PUMP STATION UPGRADES -
MAJOR ITEMS COMPLETED OR PROGRESS
(
Moraga PS Wet Forms/Rebar for Grinder Structure Pouring Grinder Structure Slab
Weather Pump
Inspection
9
CENTRALSAN
PUMP STATION UPGRADES -
MAJOR ITEMS COMPLETED OR PROGRESS
Grinder Structure Bypass Pumps
Surge Tank Enclosure
(Exterior) Surge Tank Enclosure
(Interior)
'\io
CENTRALSAN
5
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 8 of 14
Page 7 of 10
OTHER PUMP STATION WORK COMPLETED
-j � il
Three New VFDs for Wet Weather Rebuilt 100-horsepower(HP) New VFD for 100-HP Pump
Pumps at Lower Orinda PS Pump at San Ramon PS at San Ramon PS
CENTRAL SAN
PUMP STATION UPGRADES -
MAJOR ITEMS SCHEDULED
• Work scheduled to be completed prior to October 31, 2020
• All mechanical and electrical equipment at Flush Kleen PS
• Moraga PS grinder structure completed and coated
• Wet wells coated at Moraga and Orinda Crossroads Pump Stations
• Work scheduled to be completed prior to October 31, 2021 at
Moraga and Orinda Crossroads Pump Stations
• Installing new dry weather pumps
• Replacing diesel engines with new electric motors for wet weather pumps
• Installing new and much larger generators
• Replacing/installing all electrical/controls equipment(Switchgear, motor
control centers(MCCs),VFDs, etc.)
• Installing new surge tanks
• Expanding the wet well at Orinda Crossroads PS
iz
CENTRAL SAN
6
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 9 of 14
Page 8 of 10
COLLECTION SYSTEM -
SEWER RENOVATION PROJECTS
Sewer Renovation Projects:
• Danville, Phase 3— 6,100 feet of sewer mains and 47 laterals
(80% complete)
• Walnut Creek, Phase 14 —9,810 feet of sewers (26% complete)
• Martinez, Phase 6— 9,000 feet of sewers (43% complete)
• Lafayette, Phase 14 — 12,131 feet of sewers (20% complete)
Total Contracts: $12.4 million ($4.3 million paid as of September 30)
C-1
13
CENTRAL SAN
DANVILLE, PHASE 3
Pipe Pull Back for HDD'd Lateral Pit-Launched HDD Drill Rig
w
; 5 ^' -, -� Sewer Main Open Cut
Open-cut I ateral Re-route
14
Horizontal Directional Drilling(HDD) CENTRAL SAN
7
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 10 of 14
Page 9 of 10
MARTINEZ, PHASE 6
1'
15
CENTRAL SAN
WALNUT CREEK, PHASE 14
04�1ti
-T
-vwxMMa
-rte
CENTRAL SAN
8
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 11 of 14
Page 10 of 10
LAFAYETTE, PHASE 14
• 5
AM1 p:55 aUW 2 20
loci 17
SEWER RENOVATION -
MAJOR ITEMS COMPLETED OR PROGRESS
New Pipe Crossing Creek(Via Ferrari) Pier/Junction Support(Via Ferrari)
Nor- CENTRAL SAN
9
October 13, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 12 of 14