HomeMy WebLinkAbout04.a. Receive update on Solar Energy Project procurement schedule Page 1 of 1
Item 4.a.
CENTRAL SAN
September 21, 2020
TO: REAL ESTATE, ENVIRONMENTAL AND PLANNING COMMITTEE
FROM: MELODY LABELLA, RESOURCE RECOVERY PROGRAM MANAGER
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE UPDATE ON SOLAR ENERGY PROJECT PROCUREMENT
SCHEDULE
The following is the anticipated procurement schedule for the Solar Energy Project on Central San's
Lagiss Property:
• October 1, 2020, Board meeting: Set a Public Hearing for November 5, 2020, to consider award of
a Power Purchase Agreement (PPA)
• October 12, 2020, Real Estate, Environmental & Planning (REEP) Committee meeting: Review
draft Position Paper to conduct a Public Hearing to consider award of a PPA and authorize the
General Manager to execute a PPA
• November 5, 2020, Board meeting: Conduct a Public Hearing to consider award of a PPA and
Authorize the General Manager to execute a PPA
Staff looks forward to reviewing this schedule and answering any questions at the September 21, 2020,
REEP Committee meeting.
Strategic Plan Tie-In
GOAL TWO: Environmental Stewardship
Strategy 4- Reduce reliance on non-renewable energy
GOAL THREE: Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
September 21, 2020 Special REEP Committee Meeting Agenda Packet- Page 4 of 14