HomeMy WebLinkAbout04.c. Review draft Position Paper to award a construction contract in the amount of $26,584,000 to C. Overaa & Company, the lowest responsive bidder for the Filter Plant and Clearwell Improvements, Phase 1A, District Project 7361; find that the project i Page 1 of 14
Item 4.c.
CENTRAL SAN BOARD OF DIRECTORS
. , , .
POSITION PAPER
. , 0
DRAFT
MEETING DATE: AUGUST4, 2020
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT I N THE AMOUNT OF $26,584,000 TO C. OVERAA& COMPANY,
THE LOWEST RESPONSIVE BIDDER FOR THE FILTER PLANTAND
CLEARWELL IMPROVEMENTS, PHASE 1A, DISTRICT PROJECT 7361;
FIND THAT THE PROJECT IS EXEMPT FROM THE CALIFORNIA
ENVIRONMENTAL QUALITYACT (CEQA); AND AUTHORIZE THE
GENERAL MANAGER TO: 1)AMEND AN EXISTING AGREEMENT WITH
STANTEC CONSULTING SERVICES, INC. IN AN AMOUNT NOT TO
EXCEED $1,300,000 FOR ENGINEERING SERVICES DURING
CONSTRUCTION, AND 2) EXECUTE A PROFESSIONAL ENGINEERING
SERVICES AGREEMENT IN AN AMOUNT NOT TO EXCEED
$2,100,000 WITH MWH CONSTRUCTORS, INC. FOR CONSTRUCTION
MANAGEMENT SERVICES
SUBMITTED BY: INITIATING DEPARTMENT:
CHATHURAABEYRATHNA, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is required for the General Manager to execute the Contract Documents subject to submittal
requirements and to execute professional engineering services agreements over the amount of$200,000.
BACKGROUND
Coronavirus (COVID-19) Impact: The Filter Plant and Clearwell Improvements, Phase 1A, District
Project 7361 (Project), is expected to start field construction activities this year and be completed by
October of 2022. The construction contract for this Project includes provisions and costs to mitigate and
prevent the spread of COVI D-19, which includes handwash stations, personal protective equipment, and
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 34 of 69
Page 2 of 14
other safety items or practices recommended by the State Occupational Safety and Health Administration
and guidelines from the Contra Costa County Health Services.
History and Project Approach with Future Recycled Water Projects: Central San's recycled water
facilities have provided a reliable supply of recycled water to its wastewater treatment plant (plant) since
1977. 1 n the mid-1990s, Central San modified these facilities to produce California Title 22 Water Quality
Requirements for Recycled Water(Title 22) and delivery to off-site customers in Zone 1.
While Central San's plant remains the largest user of recycled water, some of the recycled water facilities
are nearing the end of their useful lives, which is leading to reliability concerns and the need to address
critical infrastructure at the Filter Plant and Clearwell (storage and distribution facilities).
On May 3, 2018, the Board authorized an agreement with Stantec Consulting Services, I nc. (Stantec)to
provide design services for the Filter Plant and Clearwell I mprovements. Stantec reviewed the condition of
the facilities, provided disinfection alternatives, hydraulics, seismic assessment, process and automation
solutions, and alternative filtration technology information.
Staff and Stantec took a long-term approach on this Project and evaluated the possible impacts of future
projects, including the Concord Community Reuse Project and the Water Exchange Project. When
looking at possible solutions, the team evaluated Central San's immediate needs, which include the most
critical items that require replacement to restore reliability, and that would not conflict with or potentially
leave stranded assets when other projects are implemented like the Water Exchange Project.
Several recent failures have shaped and focused staff's recommendations for the recycled water facilities.
The east Clearwell cover experienced failures leading to a repair project that included decommissioning
the east cell and doing improvements to allow the west cell to operate. In 2018, a high-voltage (12kV)
electrical feeder from Substation 82 (Central San's main PG&E interconnection)to Substation 40 at the
Filter Plant failed. Substation 40 experienced another failure in early 2019, which triggered a cascading
series of events that led to a 16-minute, plant-wide power outage. These incidents reflect that, despite
staff's good operation and maintenance practices, the recycled water facilities are showing signs of
significant deterioration, which is starting to impact reliability.
Staff recommended to divide the Filter Plant and Clearwell Improvements into three phases, with the most
critical elements proceeding first, as follows:
• Phase 1A (immediate replacement needs): Electrical renovation, recycled water storage tanks,
Clearwell pump improvements, rehabilitation of one of the four existing filters (additive bid item), and
Basin C modifications.
• Phase 1 B (within five to ten years): Rehabilitation of the remaining three filters and the Filter Building,
other electrical replacement, upgrades to the Applied Water Pump Station (AW PS), hydraulic
improvements to bypass the Forebays, and adding a chlorine contact basin. This phase would
complete the remainder of the renovations to meet the long-term needs for the plant and Zone 1
customers.
• Phase 2: Improvements to provide additional recycled water supply to serve the future Concord
Community Reuse Project. (Phase 2 is not included in the Fiscal Year(FY) 2020-21 Ten-Year
Capital Improvement Plan and budget.)
Project Scope and Bidding: On October 17, 2019, the Board authorized staff to proceed with the final
design of Phase 1 A. The Project focuses primarily on providing reliable recycled water storage,
distribution to end users, and address deficient electrical systems. In addition, it includes rehabilitating one
of the four existing filters. Soil produced from the partial demolition of the Clearwell will be used to raise
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 35 of 69
Page 3 of 14
the wet weather overflow Basin C embankment and its roadways which is critical for flood protection at the
plant.
Central San staff, with assistance from Stantec, prepared the project documents. The Engineer's estimate
for construction is $31,000,000 for the base scope of work, which includes a new electrical Clearwell
substation, demolition and regrading of the Clearwell, addition of two new storage tanks, recycled water
pump modifications, and the Basin C improvements. Two additive bid items were included for the
replacement of Filter No. 3 and electrical improvements to the Applied Water Pump Station. The total for
the additive items was estimated at$3,500,000 ($2,750,000 for Filter No. 3 and $750,000 for the AW PS).
This Project was advertised on June 8 and 15, 2020. The bid documents included life cycle costs based
on the selection of steel or concrete recycled water storage tanks. These life cycle costs were used to
allow for more competition between the two types of structures and was recommended due to the limited
pool of tank contractors for each material of construction. The life cycle costs were added to the
contractor's base bid price for the purpose of award. However, the actual construction contract will include
the bidder's base bid price plus any additive bid items selected by Central San.
Eight sealed bids were received and publicly opened on July 29, 2020, with an adjusted base bid price
ranging from $23,710,000 to $37,265,000. The Capital Projects Division conducted a technical and
commercial review of the bids and determined that C. Overaa & Company (Overaa) is the lowest
responsive and responsible bidder with an adjusted base bid amount of $23,710,000 as shown in
Attachment 2. Staff contacted Overaa regarding the low bid amount and they confirmed that they are
comfortable with their bid. Overaa is currently completing the Mechanical and Concrete Renovations,
District Project 7351, and are performing well on that project.
Overaa provided a base bid price of$23,070,000 and included steel tanks within their bid. The additive bid
items totaled $3,514,000 and was in line with the Engineer's estimate of$3,500,000. Staff is
recommending to proceed with the work and include the additive items to the construction contract.
Replacing the filter will increase reliability of the Filter Plant since the existing filter is in poor condition. The
Applied Water Pump Station pumps and electrical upgrades were initially scheduled under Phase 1 B but
were reprioritized to Phase 1 A due to concerns about the condition of the variable frequency drives that
are showing signs of failure and, therefore, need to be replaced sooner. Staff will recommend awarding a
contract for$26,584,000, which includes the base bid price and the additive items. The bid documents
notified all bidders and included specification that allowed Central San to add or not accept the additive
items to the construction contract.
Several strategies were evaluated and tested to optimize the filtration capabilities of the existing gravity
filters. Stantec and staff tested and performed a business case analysis for the following four alternatives:
1. Continue with aluminum sulfate (alum) as the coagulant and continue to use existing media
2. Continue with alum and replace filter media to a larger particle size
3. Change to a proprietary coagulant polymer and reuse existing filter media
4. Change to a proprietary coagulant and replace filter media
Under a separate study, staff evaluated a Tertiary Membrane Alternative Analysis. Preliminary evaluation
indicated that while a membrane would provide higher water quality (i.e., lower solids and turbidity), the
capital cost would be approximately 20-percent higher than gravity filters. I n addition, the Operations and
Maintenance cost is also higher due to electrical costs and replacement of the membranes. Therefore,
staff recommends proceeding with the upgrade to Filter No. 3 under Phase 1A.
Construction Management: Staff will oversee and coordinate the Project with the help of a construction
management firm and engineering support from Stantec.
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 36 of 69
Page 4 of 14
Stantec was selected to provide pre-design, final design, and engineering services during construction
(ESDC) under a formal Request for Proposal (RFP) in January of 2018 which included the scope and
anticipated costs for the Project. ESDC includes submittal and shop drawing review, responding to
contractor design questions, design clarifications, other designer support services, and support with Title
22 verification.
Staff recently issued a RFP to provide third-party construction management (CM) services that would
include a construction manager, inspection, specialty inspection, and start-up and commissioning services.
Central San received proposals from six firms: Carollo Engineers, Inc.; Consolidated CM; EPC
Consultants; HDR Engineering, I nc.; MW H Constructors, I nc.; and Psomas. Stantec was not allowed to
submit as it would be a conflict of interest to perform construction management on their own design.After
reviewing the proposals and conducting an interview, staff selected MW H Constructors, Inc.
CEQA: Staff has concluded that this Project is exempt from CEQA under District CEQA Guidelines
Section 15302, because it involves alteration of an existing sewer facility at substantially the same
locations and with the same purpose and level of activity as the facilities being replaced. Approval of this
Project will establish the Board's independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
The Board could consider the following alternatives, which are not recommended by staff:
1. Award the base bid only($23,070,000) and reject both additive bid items (totaling $3,514,000)for
the Project. Improvements to Filter No. 3 were included to address a poor performing and deficient
filter at$2,715,000, and improvement to the Applied Water Pump Station at$799,000 were included
to increase resiliency by replacing the variable frequency drives and pumps which are at the end of
their useful life.
2. Award the base bid and any combination of the additive bid items.
3. Reject all bids, which is not recommended. This Project will address several critical infrastructure
deficiencies at the Filter Plant and provide long-term storage reliability for the recycled water
systems for the plant and Zone 1 customers.
FINANCIAL IMPACTS
The total estimated project cost is $38,504,000, which includes planning, filter piloting, design,
construction contract, contingency, construction management, and consultant costs as shown in
Attachment 3. The Project is included in the FY 2020-21 Budget on page 257 with an estimated total
project budget of$38,589,000.
The current Stantec agreement value is $3,262,000. The amendment for ESDC has been negotiated to
an estimated value of$1,300,000, which will result in a new agreement value of$4,562,000.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at the August 4, 2020 meeting and
recommended
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 37 of 69
Page 5 of 14
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract, including the additive bid items, in the amount of$26,584,000 to
C. Overaa& Company, the lowest responsive bidder for the construction of the Filter Plant and Clearwell
Improvements, Phase 1A, District Project 7361; and
3. Authorize the General Manager to:
a. Execute the Contract Documents subject to submittal requirements;
b. Amend an existing agreement with Stantec Consulting Services I nc. in an amount not to exceed
$1,300,000, increasing the cost ceiling to $4,562,000 to include engineering services during
construction and Title 22 support; and
c. Execute an agreement with MW H Constructors, I nc. in an amount not to exceed $2,100,000 for
construction management services.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service, Strategy 2—Maintain a positive reputation
GOAL TWO:Environmental Stewardship
Strategy 1—Achieve 100%compliance in all regulations
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
GOAL FIVE:Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life, Strategy 3—Protect personnel and assets from
threats and emergencies
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post Bid/P reconstruction Estimate
4. Presentation
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 38 of 69
Page 6 of 14
ill 'I
� iiP ii N
0 250 500
FEET
ISI I�
ill li
ill 11
1
BASIN C LEVEE I,n 111
RAISE '11 II
� SII 11
!11 II
Basin B j 1
\ Basin C 111 1
r11 11
11
'1 11
dl 11
�1 ,I
!x!11 11
'11 11
�1I II
11
I �I 11
[Alum ;11 11
CONSTRUCTION Basin C Sludge
Ponds
STAGING AREA x'11 1I1
SUBSTATION 48
11
f O RECYCLED WATER II 11
o PUMP STATION jj11 11
J j CLEARWELL AND ,�11 111
RECYCLED WATER 11
STORAGE TANKS 1 11
FILTER j,1I 11
PLANT CONSTRUCTION j 1 11
I
SUBSTATION 40 STAGING AREA
EAPPLIED WATER II
3 '
PUMP STATION 0
D FILTERED WATER
LIFT STATION 11
Basin A 11
I North 11
SUBSTATION 82
CENTML SAN FILTER PLANT AND Attachment
CLEARWELL IMPROVEMENTS, PHASE 1A 1
DISTRICT PROJECT 7361
LOCATION MAP
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 39 of 69
Page 7 of 14
ATTACHMENT 2
FILTER PLANT AND CLEARWELL IMPROVEMENTS, PHASE 1A
DISTRICT PROJECT 7361
SUMMARY OF BIDS
PROJECT NO.: 7361 NO. OF ADDENDA: 4 DATE/TIME: JULY 29, 2020/2:00 PM
PROJECT NAME: FILTER PLANT AND CLEARWELL IMPROVEMENTS, PHASE 1A
PROJECT MANAGER: CHATHURA ABEYRATHNA
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $31,000,000 (BASE BID)
NO. BIDDER ADJUSTED
BASE BID PRICE * BASE BID PRICE
1 C. Overaa & Company $23,710,000 $23,070,000
Richmond, CA
2 Auburn Constructors, LLC $27,374,300 $26,734,300
Sacramento, CA
3 Shimmick Construction Company, Inc. $27,640,500 $27,000,500
Suisun City, CA
4 Western Water Constructors, Inc. $28,326,600 $27,686,600
Santa Rosa, CA
5 Mountain Cascade, Inc. $29,704,905 $29,064,905
Livermore, CA
6 Steve P. Rados, Inc. $32,953,000 $32,313,000
Sacramento, CA
7 Flatiron West Inc. $34,045,000 $33,405,000
Benicia, CA
8 Balfour Beatty $37,265,000 $37,175,000
Fairfield, CA
*Adjusted base bid price is the basis for award and includes life cycle costs between the steel and
concrete storage tank options.
BIDS OPENED BY: /s/ Katie Young
DATE: July 29, 2020 at 3:00 p.m. via livestream due to COVID-19
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 40 of 69
Page 8 of 14
ATTACHMENT 3
FILTER PLANT AND CLEARWELL IMPROVEMENTS, PHASE 1A
DISTRICT PROJECT 7361
POST-BID/PRECONSTRUCTION ESTIMATE
No. Item Description Amounts Construction
Cost
1 CONSTRUCTION
a. Construction Contract w/additive items $26,584,000
b. 10% Contingency $2,600,000
c. Title 22 Reporting &Acceptance (Stantec) $200,000
d. Permit $100,000
SUBTOTAL-CONSTRUCTION $29,484,000 100%
2 CONSTRUCTION MANAGEMENT
a. District Forces
- Project Management $775,000
-Operational Support $225,000
- Regulatory Support $120,000
b. Consultants
- Stantec ESDC* $1,100,000
- MWH Construction Management Services $2,100,000
- Material Testing $200,000
- Geotechnical $100,000
SUBTOTAL-CONSTRUCTION MANAGEMENT $4,620,000 16%
3 PREBID EXPENDITURES
a. Engineering- Planning and Pilot Studies $2,000,000
b. Engineering- Design and Permitting $2,300,000 8%
c. Permitting $100,000
SUBTOTAL- PREBID EXPENDITURES $4,400,000 15%
4 ITOTAL ESTIMATED PROJECT COSTS I 1 1 $38,504,000
*The Stantec agreement amendment will include$1.1 M for ESDC and $200k for Title 22 support(listed under construction).
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 41 of 69
Page 9 of 14
Attachment 4
FILTER PLANT AND CLEARWELL
++ IMPROVEMENTS, PHASE 1A
DISTRICT PROJECT 7361
PROJECT UPDATE AND AWARD
- - Engineering and Operations
Committee Meeting
August 4, 2020
- Jean-Marc Petit, P.E.
Director of Engineering and Technical Services
Edgar J. Lopez, P.E.
Capital Projects Division Manager
PHASE 1 A SCOPE FOR RECYCLED WATER
PLANT FACILITIES IMPROVEMENTS
Replace Backwash Motors
(480V)
Recycled Water Storage:
o Replace East Clearwell Y
with two new above i .f
ground storage tanks -+'• '
(steel or pre-stressed R "
concrete)
•
Clearwell Overflow -
Structure Modifications
Rehabilitation one Filter
(#3)and Mechanical/
Instrumentations on others J _ - - _-.-•: �
Upgrade Chemical Feed
` Upgrade/Replace Electrical Gear
•
Applied Water Pum / New Recycled Pump Station
PP P Electrical Facility
Station(AWPS) Replace Substation 40-2400V
• Replace Variable Frequency
Drives for AWPS
r 2
1
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 42 of 69
Page 10 of 14
PHASE 1A MAJOR SCOPE ELEMENTS
• Two new Recycled Water Storage Tanks (3-million gallon
capacity each)—Welded Steel
• Maintain West Clearwell
• Clearwell Overflow Structure & Filter Effluent Lift Station
• Electrical Building and Substation 48 (new Transformers)
• Filter Plant Piping and Instrumentations
• Chemical Feed System: Hypochlorite Feed System
• Recycled Water Pump Station and Backwash Pumps
• Wet Weather Basin Levee (using excess soil material)
• BILid Alternatives: (Both to be included in the Phase 1A)
1. Filter No. 3 Rehabilitation
2.Applied Water Pump Station
3
CENTRALSAN
OVERALL SITE PLAN
i
''_Y - _. '"– —•..—a—— �� Crd iaiiv Cede •rm.w*+•as.rn....•r.muwr u iwi
_.�__.. — -�jI 5•�ypy] GEHEP.eLSRE PL4N ipC•161
1 4
2
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 43 of 69
Page 11 of 14
RECYCLED WATER STORAGE
MODIFICATIONS
I II r
Out Of
service
Active r
learwell West w !
CleanvjW
• New Recycled Water Storage will be two 3-million gallon
above ground reservoirs
• Both welded steel (AWWA D100) and pre-stressed
concrete (AWWA D110)were allowed. Steel selected by
C. Overaa & Company
5
American Water Works Association(AWWA)Standards describe minimum requirements for design,installation,
performance,and manufacturing of products used in the drinking water industry.
OVERALL PROJECT SCHEDULE
Activity Board Actions Date
Request for Proposals from Consultants January 16,2018
Issued
Preliminary Design Awarded to Stantec E&O April 25,2018
Board May 3,2018
Alternative Analysis December 2018
Final Design Amendment with Stantec E&O April 16,2019
Board May 2,2019
Final Design Complete May 1,2020
Announcement to Board E&O May 12,2020
Project Ready for Bidding Board May 21,2020
Anticipated Bid Opening July 29,2020
Board Award E&O August 4,2020
Board August 20,2020
Construction(Estimated Schedule) October 1,2020 to
December 31,2022
Project Close Out January 2023
Fs
3
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 44 of 69
Page 12 of 14
SUMMARY OF BIDS
ENGINEER'S ESTIMATE: $31.000.000(BASE BID)
NO. BIDDER ADJUSTED
BASE BID PRICE* BASE BID PRICE
1 C.Overaa&Company 23,710,000 23,070,000
Richmond,CA
2 Auburn Constructors,LLC 27,374,300 26,734,300
Sacramento,CA
3 Shimmick Construction Company,Inc. 27,640,500 27,000,500
Suisun City,CA
4 Western Water Constructors,Inc. 28,326,600 27,686,600
Santa Rosa,CA
5 Mountain Cascade,Inc. 29,704,905 29,064,905
Livermore,CA
6 Steve P.Rados,Inc. 32,953,000 32,313,000
Sacramento,CA
7 Flatiron West Inc. 34,045,000 33,405,000
Benicia,CA
6 Balfour Beatty 37,265,000 37,175,000
Fairfield,CA
Adjusted base bid price is the basis for award and includes life cycle costs between the steel and
concrete storage tank options. `
PROJECT TOTAL COST ESTIMATE
No. Item Description Amounts Construction
Cost
1 CONSTRUCTION
a.Construction Contract w/additive items $26,584,000
b.10%Contingency $2,600,000
c.Title 22 Reporting&Acceptance(Stantec) $200,000
d.Permit $100,000
SUBTOTAL-CONSTRUCTION $29,484,000 100
2 CONSTRUCTION MANAGEMENT
a.District Forces
Project Management $775,000
Operational Support $225,000
Regulatory Support $120,000
b.Consultants
Stantec ESDC* $1,100,000
MWH Construction Management Services $2,100,000
-Material Testing $200,000
Geotechnical $100,000
SUBTOTAL-CONSTRUCTIONMANAGEMEN $4,620,000 16%
3 PREBID EXPENDITURES
a. Engineering-Planning and Pilot Studies $2,000,000
b. Engineering-Design and Permitting $2,300,000 8
c. Permitting $100,000
SUBTOTAL-PREBID EXPENDITURES $4,400,000 15%
OTAL ESTIMATED PROJECT COSTS $38,504,000 `
4
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 45 of 69
Page 13 of 14
ALTERNATIVES/CONSIDERATIONS
The Board could consider the following alternatives,which are not
recommended by staff:
1. Award the base bid only($23,070,000)and reject both additive bid
items (totaling$3,514,000)for the Project. Improvements to Filter
No. 3 were included to address a poor performing and deficient filter
at$2,715,000, and improvements to the Applied Water Pump
Station at$799,000 were included to increase resiliency by
replacing the variable frequency drives and pumps which are at the
end of their useful life.
2. Award the base bid and any combination of the additive bid items.
3. Reject all bids,which is not recommended.This Project will address
several critical infrastructure deficiencies at the Filter Plant and
provide long-term storage reliability for the recycled water systems
for the plant and Zone 1 customers. ACE `
► 9
CENTRALSAN
RECOMMENDED BOARD ACTIONS
Staff recommends the following:
• Find that the Project is exempt from CEQA;
• Award a construction contract, including the additive bid items, in the amount
of$26,584,000 to C. Overaa&Company, the lowest responsive bidder for
the construction of the Filter Plant and Clearwell Improvements, Phase 1A,
District Project 7361;
• Authorize the General Manager to:
• Execute the Contract Documents subject to submittal requirements;
• Amend an existing agreement with Stantec Consulting Services, Inc. in
the amount not to exceed $1,300,000 for engineering services during
construction and Title 22 support; and
• Execute an agreement with MWH Constructors, Inc. in the amount not to
exceed $2,100,000 for construction management services.
10
CENTRALSAN
5
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 46 of 69
Page 14 of 14
QUESTIONS
11
CENTRALSAN
-f
6
August 4, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 47 of 69