HomeMy WebLinkAbout06. Award construction contract for Walnut Creek Sewer Renovations, Phase 14, DP 8460 Page 1 of 7
Item 6.
CENTRAL SAN BOARD OF DIRECTORS
vie
. , Hill. , , . .
POSITION PAPER
MEETING DATE: MAY 21, 2020
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $3,572,655
TO PRECISION ENGINEERING, INC., THE LOWEST RESPONSIVE
BIDDER FOR THE WALNUT CREEK SEWER RENOVATIONS, PHASE 14,
DISTRICT PROJECT 8460; CONSIDER EXEMPTION FROM THE
CALIFORNIA ENVIRONMENTAL QUALITYACT (CEQA); AND AUTHORIZE
UP TOA 15-PERCENT CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
DAMASIO ZEPEDAARAGON, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is also required for the General Manager to execute the Contract Documents subject to
submittal requirements and include up to a 15-percent contingency.
BACKGROUND
Coronavirus COVID-19 Impact: The Walnut Creek Sewer Renovations, Phase 14, District Project (DP)
8460 (Project) is expected to start in early June of 2020 and be completed by January of 2021. Staff has
included restrictions and other conditions in the Contract Documents that prohibit construction activities on
private properties (backyard easements) until the Contra Costa County shelter-in-place order has been
May 21, 2020 Regular Board Meeting Agenda Packet- Page 49 of 505
Page 2 of 7
revised or the Project is deemed essential by Central San. Construction on public streets has been
coordinated with local jurisdictions. The construction contract for this Project includes provisions and costs
associated with the guidelines related to COVI D-19, such as handwash stations, personal protective
equipment, and other safety items. Staff has sequenced the work and milestones to allow the contractor to
complete the contract within the duration of the Project.
This Project is part of the ongoing sewer renovation within the Collection System Program aimed to
replace or rehabilitate deteriorated sewer infrastructure that is at the end of its useful life and in poor
condition. The construction work is coordinated with local jurisdictions, cities, utilities, private property
owners, and tenants.
The Project consists of replacement or rehabilitation of approximately 9,900 feet of sewer mains, primarily
six-inch clay sewers, using open-trench, pipe-bursting, sliplining, and cured-in-place-pipe construction
methods, construction of manholes, and other related work within public rights-of-way and easements.
Most of this Project is in the Sterling's Ridge and Meadow Creek neighborhoods within the unincorporated
area of Walnut Creek and several sites in the City of Walnut Creek. The base Project also includes an
urgent site in need of replacement, which has been coordinated closely with the Collection System
Operations (CSO). That site is located in the City of Pleasant Hill and it involves the rehabilitation of
approximately 1,500 feet of backyard sewers that span over 20 private properties. The construction
method for this site will include pipe-bursting which will minimize the overall construction impact to
residents.
The bid form also includes an additive bid item. This additive bid item is for a site that includes the
installation of a new aerial creek crossing, which will replace an existing sewer pipe that was undermined
by heavy rainstorms in early 2019. CSO staff has been monitoring this site since the rain events on a
routine basis, and Capital Projects constructed a temporary repair that allowed CSO to eliminate bypass
pumping equipment. Staff has prepared the design for a permanent long-term fix for this site and has
included the work as an additive bid item under this Project. The cost of this item was $325,000. The
average cost from the other bidders was $234,000. Staff is not recommending to include this item since
the work can be bid separately or on a different project to receive lower prices.
An overview map of all project sites is shown in Attachment 1.
Staff prepared the plans and specifications for the Project. The Engineer's estimate for construction was
$4,300,000, not including the additive bid item. This Project was advertised on April 6 and 13, 2020. Six
bids ranging from $3,572,655 to $5,163,185 were received and publicly opened on April 28, 2020 via
online services. The Capital Projects Division conducted a technical and commercial review of the bids
and determined that Precision Engineering, Inc. is the lowest responsive and responsible bidder with a
total bid amount of$3,572,655.A summary of bids received is shown in Attachment 2.
Central San will administer the construction contract and provide construction management, resident
engineering, survey, administration, and submittal review. Consultant surveying services will be used to
supplement staff on an as-needed basis and construction inspection will be performed by one of Central
San's consultant inspectors.
CEQA
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15302 because it involves replacement of existing facilities at substantially the same locations and with the
same purpose and level of activity as the facilities being replaced.Any capacity increases are for non-
growth inducing, wet weather purposes. The Project also is exempt under Central San CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that the activity in
question may have a significant effect on the environment. This certainty is based on Central San's
experience with numerous sewer construction projects of this nature, the relatively short distance involved,
May 21, 2020 Regular Board Meeting Agenda Packet- Page 50 of 505
Page 3 of 7
and Central San's mitigating construction specifications. These specifications are standardized general
and special conditions that are made part of the Project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with applicable federal,
state, county, district, municipal and local laws, ordinances, orders, and regulations. Approval of this
Project will establish the Board's independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Central San staff has coordinated the Project work with private property owners, the public, and cities.
Delaying or postponing the sewer work is not recommended.
Another alternative would be to reject all bids, which is also not recommended.
FINANCIAL IMPACTS
The total estimated project cost is $5,173,000 which includes planning, design, bid price, contingency,
construction management, and consultant costs as detailed in Attachment 3.
This Project is being funded by the Collection System Sewer Renovation, Phase 1, DP 8451 as planned.
There is adequate funding in DP 8451 for this Project, as shown in Attachment 3. After award, the budget
modifications will be reflected in the latest Capital Improvement Budget. DP 8451 is a program project
that is aimed to plan, design, and fund construction of sewer replacement projects.
Staff is recommending a 15-percent contract contingency on this Project since additional work may be
added to the Project to urgently repair or replace nearby sewers and the risks associated with renovation
work.
Presently, staff does not foresee any additional financial impact on this Project due to COVI D-19.
COMMUNITY OUTREACH
Central San has conducted several forms of outreach for this Project. Initial project design letters were
sent in the summer of 2019 informing residents of upcoming design work. Throughout the course of
design, staff addressed email and phone inquiries regarding the Project and conducted outreach with
several easement homeowners as well as some teleconferencing during the shelter-in-place order. On
March 17, 2020, letters were sent out to the public informing them that a detailed project presentation had
been posted on Central San's website in lieu of a public face-to-face meeting, as initially intended, as a
result of social distancing requirements for COVI D-19. The public was encouraged to reach out with any
additional questions or concerns they may have. To date, no further questions or concerns have been
received and staff plans to continue providing written and phone notifications.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this Project at the meeting on May 12, 2020, and
recommended Board approval.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of$3,572,655 for the construction of the Walnut Creek
Sewer Renovations, Phase 14, District Project 8460, to Precision Engineering, Inc., the lowest
May 21, 2020 Regular Board Meeting Agenda Packet- Page 51 of 505
Page 4 of 7
responsive bidder; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements and include up to a 15-percent contingency.
Strategic Plan Tie-In
GOAL ONE:Provide Exceptional Customer Service
Strategy 1 - Build external customer relationships and awareness, Strategy 3- Maintain a strong reputation in the
community
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations, Strategy 2- Strive to
minimize the number of sanitary sewer overflows
GOAL FOUR:Develop and retain a highly trained and innovative workforce
Strategy 3- Meet or exceed industry safety standards
GOAL FIVE:Maintain a Reliable Infrastructure
Strategy 2- Facilitate long-term capital renewal and replacement, Strategy 3- Protect District personnel and assets
from threats and emergencies
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post-Bid/P reconstruction Estimate
May 21, 2020 Regular Board Meeting Agenda Packet- Page 52 of 505
CENTRAL SAN -
WAR I
Martin
f
� 680 ° "� o ' d �
1� JON -
.
� 24 . . - -
Moraga
an amon
a INS
A r 680
a
Project Ar -
Note: 0 4,000
110001=3001= Map Displayed in North American
Datum
Page 6 of 7
ATTACHMENT 2
WALNUT CREEK SEWER RENOVATIONS, PHASE 14
DISTRICT PROJECT 8460
SUMMARY OF BIDS
PROJECT NO.: 8460 NO. OF ADDENDA: 1 DATE/TIME: APRIL 28, 2020/2:00 PM
PROJECT NAME: WALNUT CREEK SEWER RENOVATIONS, PHASE 14
PROJECT MANAGER: DAMASIO ZEPEDA ARAGON
PROJECT LOCATION: CENTRAL SAN SERVICE AREA
ENGINEER'S ESTIMATE: $4,300,000
NO. BIDDER BID PRICE
1 Precision Engineering, Inc. $3,572,655
San Francisco, California
2 K.J. Woods Construction, Inc. $3,688,000
San Francisco, California
3 Cratus, Inc. $3,982,225
San Francisco, California
4 Andes Construction, Inc. $4,071,595
Oakland, California
5 Westland Contractors, Inc. $4,552,529
Oakland, California
6 California Trenchless, Inc. $5,163,185
Hayward, California
BIDS OPENED BY: /s/ Katie Young
DATE: April 28, 2020 at 3:00 p.m. via livestream due to COVID-19
May 21, 2020 Regular Board Meeting Agenda Packet- Page 54 of 505
Page 7 of 7
ATTACHMENT 3
WALNUT CREEK SEWER RENOVATIONS, PHASE 14
DISTRICT PROJECT 8460
POST-BID/PRECONSTRUCTION ESTIMATE
% Of
Item Description Amounts Construction
No. Cost
1. CONSTRUCTION
a. Construction Contract $3,572,655
b. 15% Contingency $535,345
c. Permits $65,000
SUBTOTAL- CONSTRUCTION COST $4,173,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $170,000
- Public Relations/Right-of-Way $20,000
- Operations (CSO) $10,000
b. Consultants
- Inspection $150,000
- Material Testing/Arborist/Others $50,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $400,000 10%
3. PREBID EXPENDITURES
a. Engineering (Design, Survey, Right-of-Way, Drafting) $600,000
SUBTOTAL - PREBID EXPENDITURES $600,000 14%
4. TOTAL ESTIMATED PROJECT COST $5,173,000
May 21, 2020 Regular Board Meeting Agenda Packet- Page 55 of 505