Loading...
HomeMy WebLinkAbout04.b. (Handout) Updated Estimate Item 4.b. (Handout) ATTACHMENT 3 Updated Estimate PLANT CONTROL SYSTEM 1/0 REPLACEMENT PROJECT—PHASE 2,SECONDARY PROCESS DISTRICT PROJECT 7339B POST-BID/PRECONSTRUCTION ESTIMATE %of Construction No. Item Description Amounts Cost 1 CONSTRUCTION a. Construction Contract $1,222,200 b. Contingency at 15% $183,800 c. PLC Hardware $60,000 SUBTOTAL-CONSTRUCTION $1,466,000 100% 2 CONSTRUCTION MANAGEMENT a. District Forces (Construction Management and Engineering) $150,000 b. Consultant-As-needed Engineering Services $30,000 c. Operations Support $30,000 SUBTOTAL-CONSTRUCTION MANAGEMENT $210,000 14% 3 PREBID EXPENDITURES a. District Forces - Planning and Design $130,000 -As-Built Documentation and Field Investigation $55,000 SUBTOTAL-PREBID EXPENDITURES $185,000 13% 4 TOTAL ESTIMATED PROJECT COST-PHASE 2 $1,861,000 5 PAST EXPENDITURES- PHASE 1 $1,310,000 6 TOTAL ESTIMATED PROJECT COST- PHASES 1 &2 $3,171,000