HomeMy WebLinkAbout04.b. Review draft Position Paper to award a construction contract in the amount of $1,222,200 to Bockmon & Woody Electric Company, Inc., the lowest responsive bidder for the Plant Control System Input and Output (I/O) Replacement Project – Phase 2, Seco Page 1 of 6
Item 4.b.
CENTRAL SAN BOARD OF DIRECTORS
vie POSITION PAPER
Hill Tim DRAFT
MEETING DATE: MAY 12, 2020
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT I N THE AMOUNT OF $1,222,200 TO BOCKMON & WOODY
ELECTRIC COMPANY, INC., THE LOWEST RESPONSIVE BIDDER FOR
THE PLANT CONTROL SYSTEM INPUT AND OUTPUT (1/0)
REPLACEMENT PROJECT— PHASE 2, SECONDARY
PROCESS, DISTRICT PROJECT 733913; CONSIDER EXEMPTION FROM
THE CALIFORNIA ENVIRONMENTAL QUALITYACT (CEQA); AND
AUTHORIZE UP TO A 15-PERCENT CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
NATE MORALES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is also required for the General Manager to execute the Contract Documents subject to
submittal requirements and include up to a 15-percent contingency.
BACKGROUND
Coronavirus COVI D-19 1 mpact: Plant Control System 1/0 Replacement Project— Phase 2, Secondary
Process, District Project 7339B (Project) may start in July 2020 and be completed by December 2020,
with the bulk of construction performed beyond August. Staff has included conditions in the Contract
Documents that account for the health and safety guidelines provided by the Contra Costa County latest
order, such as provisions and costs associated with handwash stations, personal protective equipment,
and other safety items. Staff has sequenced the work and milestones to allow the contractor to complete
the contract within the duration of the Project and plans to issue an early administrative Notice to Proceed
to procure the equipment.
The wastewater treatment plant (plant) primarily uses Quantum Programmable Logic Controllers (PLC)
May 12, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 10 of 55
Page 2 of 6
connected to Quantum 1/0 cards manufactured by Schneider Electric. PLC 1/0 cards are critical for
equipment and instrumentation communication for process control, monitoring, and data acquisition. The
first plant PLC 1/0 card was installed in the mid-1980s. Today, the number of 1/0 cards in use has grown
to nearly 1,800. Approximately 900 of these 1/0 cards are outdated and replacement units cannot be
purchased from the manufacturer, and they are no longer supported by their service department (software
or hardware). Central San has maintained an inventory of spare 1/0 cards to replace units as they fail or
need to be reprogrammed and tested, but that spare supply has depleted in recent years.
This Project is the second of a multiphase effort to replace PLCs with modern Schneider Electric
equipment at the plant. The Project will address long-term reliability for the PLC system by replacing
PLCs in the secondary process area, salvaging the PLC 1/0 cards to restock the replacement inventory,
and continuing the implementation to modern networking PLC systems and matching the new system that
was installed during Phase 1 at the Filter Plant. This Project also includes the replacement of several
critical variable frequency drives (VFDs)for the secondary process. This includes six VFDs for the Return
Activated Sludge (RAS) pumps and three Waste Activated Sludge (WAS) pumps associated with the
North Quad Secondary Clarifiers. I n addition, the six VFDs for RAS pumps for the South Quad
Secondary Clarifiers which were recently replaced under the Treatment Plant Piping Renovations, Phase
9 project, will receive updated controls.
Central San staff prepared the plans and specifications for the Project. The Engineer's estimate for
construction was $1,300,000. This Project was advertised on March 31 and April 7, 2020.
Nine sealed bids ranging from $1,222,200 to $1,695,000 were received and publicly opened on May 6,
2020. The Engineering Department conducted a technical and commercial review of the bids and
determined that Bockmon & Woody Electric Company, Inc. is the lowest responsive and responsible
bidder.A summary of bids received is shown in Attachment 2.
Central San will administer the construction contract, submittals and schedules, and will provide contract
management, administration, office engineering, and construction inspection.
CEQA
Staff has concluded that this Project is exempt from the CEQA under Central San's CEQA Guidelines
Section 15301, since it involves minor alterations to existing public facilities involving no expansion of use,
and CEQA Guidelines Section 15302, since it involves replacement of existing public facilities at the
same location and with the same purpose.Approval of this Project will establish the Board's independent
finding that this Project is exempt from CEQA.
ALT ERNAT IVES/CONSIDERAT IONS
The Board may elect to postpone or phase the construction which would require that the Board reject all
bids. This is not recommended since there are several project elements that should not be deferred
including critical VFD replacements and associated controls equipment and PLC work.
If the VFDs and associated PLCs were bid separately, there would be re-work associated and the costs
would ultimately increase. The Plant Control System 1/0 Replacement Project has already been phased
to effectively replace equipment while getting the maximum expected life of the existing equipment and
balancing an adequate spare parts inventory.Additional delays are not recommended.
FINANCIAL IMPACTS
The total estimated project cost is $1,801,000, which includes planning, design, 1/0 cards pre-purchase,
construction contract, contingency, and construction management costs as shown in Attachment 3. The
Project is included in the Fiscal Year(FY) 2019-20 Capital I mprovement Budget on page 180 with a total
estimated project budget of $4,498,000. There is adequate funding for this phase of the project through
May 12, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 11 of 55
Page 3 of 6
FY 2019-20 and FY 2020-21.
Staff is recommending a 15-percent contract contingency due to the nature and risks associated with
renovation work and to provide for additional work if urgently needed at the plant.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at the May 12, 2020 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of$1,222,200 for the construction of the Plant Control
System 1/0 Replacement Project— Phase 2, Secondary Process, District Project 7339B, to
Bockmon & Woody Electric Company, Inc., the lowest responsive bidder; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements and include up to a 15-percent contingency.
Strateguc Plan Tie-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL FOUR: Develop and retain a highly trained and innovative workforce
Strategy 3- Meet or exceed industry safety standards
GOAL FIVE:Maintain a Reliable Infrastructure
Strategy 1 - Manage assets optimally throughout their lifecycle, Strategy 2- Facilitate long-term capital renewal and
replacement
GOAL SIX: Embrace Technology, Innovation and Environmental Sustainability
Strategy 3- Encourage the review and testing of technology to optimize and modernize business operations
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post-Bid/P reconstruction Estimate
May 12, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 12 of 55
Page 4 of 6
a
CO ZZ:3 r-Po CLEARWELL
b rG3 BASIN
o a
I+�cyzb NORTH
BASIN
0 ED
33w 43
■� 13 FILTER p DRAIN BACK O
\ PLANT CHANNEL
Nr
0 oa
o
0 400 800
FEET
ii
PROJECT
L J AREA
NORTH \ QQ ;
\ CLARIFIERS SOUTH
BASIN
AERATION
TANKS
/may
SOUTH \ `•
CLARIFIERS)
LARIFIERSSOLIDS
o �J
BUILDING
PRIMARY
TANKS
as
as
0
Attachment
Y CENTRAL SAN PLANT CONTROL SYSTEM 1/0 REPLACEMENT
o '
PROJECT - PHASE 2, SECONDARY PROCESS 1
a
■
DISTRICT PROJECT 7339B
Page 5 of 6
ATTACHMENT 2
PLANT CONTROL SYSTEM 1/0 REPLACEMENT PROJECT — PHASE 2, SECONDARY PROCESS
DISTRICT PROJECT 7339B
SUMMARY OF BIDS
PROJECT NO.: 7339B NO. OF ADDENDA: 4 DATE/TIME: MAY 6, 2020/2:00 PM
PROJECT NAME: PLANT CONTROL SYSTEM 1/0 REPLACEMENT PROJECT — PHASE 2,
SECONDARY PROCESS
PROJECT MANAGER: NATE MORALES
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $1,300,000
NO. BIDDER BID PRICE
1 Bockmon & Woody Electric Co., Inc. $1,222,200
Stockton, CA
2 Con J. Franke Electric, Inc. $1,234 700
Stockton, CA '
3 Telstar Instruments $1,239,931
Concord, CA
4 Anvil Power Inc. $1,334'600
San Francisco, CA
5 D.W. Nicholson Corporation $1,354'500
Hayward, CA
6 C. Overaa & Co. $1,400,000
Richmond, CA
7 Fort Bragg Electric, Inc. $1'508,646
Fort Bragg, CA
8 Blocka Construction, Inc. $1,623,000
Pleasanton CA
Saboo, Inc.
9 Brentwood, CA $1,695,000
BIDS OPENED BY: /s/ Katie Young
DATE: May 6, 2020 at 3:00 p.m. via livestream due to COVID-19
May 12, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 14 of 55
Page 6 of 6
ATTACHMENT
PLANT CONTROL SYSTEM 1/0 REPLACEMENT PROJECT—PHASE 2, SECONDARY PROCESS
DISTRICT PROJECT 7339B
POST-BID/PRECONSTRUCTION ESTIMATE
%of
Construction
No. Item Description Amounts Cost
1 CONSTRUCTION
a. Construction Contract $1,222,200
b. Contingency at 15% $183,800
SUBTOTAL-CONSTRUCTION $1,406,000 100%
2 CONSTRUCTION MANAGEMENT
a. District Forces(Construction Management and Engineering) $150,000
b. Consultant-As-needed Engineering Services $30,000
c. Operations Support $30,000
SUBTOTAL-CONSTRUCTION MANAGEMENT $210,000 15%
3 PREBID EXPENDITURES
a. District Forces
- Planning and Design $130,000
-As-Built Documentation and Field Investigation $55,000
SUBTOTAL-PREBID EXPENDITURES $185,000 13%
4 TOTAL ESTIMATED PROJECT COST-PHASE 2 $1,801,000
5 PAST EXPENDITURES-PHASE 1 $1,310,000
6 TOTAL ESTIMATED PROJECT COST- PHASES 1 &2 $3,111,000
May 12, 2020 EOPS Regular Committee Meeting Agenda Packet- Page 15 of 55