HomeMy WebLinkAbout10. Award contract to Sonnikson and Stordahl Construction for Treatment Plant Safety Enhancements - Phase 5, DP 7364 Page 1 of 6
Item 10.
CENTRAL SAN BOARD OF DIRECTORS
vie
. , Hill. , , . .
POSITION PAPER
MEETING DATE: FEBRUARY20, 2020
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $687,500 TO
SONNIKSONAND STORDAHL CONSTRUCTION, INC., THE LOWEST
RESPONSIVE BIDDER FOR THE TREATMENT PLANT SAFETY
ENHANCEMENTS — PHASE 5, DISTRICT PROJECT 7364; CONSIDER
EXEMPTION FROM THE CALIFORNIA ENVIRONMENTAL QUALITYACT
(CEQA); AMEND AN EXISTING AGREEMENT WITH BLACK AND VEATCH
CORPORATION IN THE AMOUNT OF $120,000 FOR CONSTRUCTION
SUPPORT SERVICES;AND AUTHORIZE UP TOA 15-PERCENT
CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
CRAIG MIZUTANI, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is required for the General Manager to execute the Contract Documents subject to submittal
requirements and include up to a 15-percent contingency. The General Manager also needs Board
authorization to amend an existing professional engineering services agreement, which is over the General
Manager's delegated authority.
BACKGROUND
The Treatment Plant Safety Enhancements — Phase 5, District Project (DP) 7364 (Project) includes
facility improvements to construct an exterior emergency exit stairway for the control room and electrical
February 20, 2020 Regular Board Meeting Agenda Packet- Page 83 of 161
Page 2 of 6
room in the Solids Conditioning Building (SCB). The stairway was identified as a safety improvement
during a fire safety study conducted a few years ago. There is currently a single exit path from the control
room and the additional exit stairway will provide a secondary and more direct egress route during an
emergency. It will also provide an additional means to access other floors of the SCB and the other
nearby facilities.
Due to the major seismic improvements planned under the Solids Handling Facility Improvements, DP
7348 (Solids Project), staff decided to coordinate and design the new stairway using the Solids Project
design team lead by Black and Veatch Corporation (B&V). Overall, the scope of work performed under
the Project consists of building a new exterior three-story metal stairway and platform system on the
southeast area of the SCB. The new stairway will also be needed as the existing SCB stairway will be
modified and temporarily out of service during the Solids Project. Other work including foundation,
modifications to the existing building exterior, and lighting will be done under the Project.A project location
map is shown in Attachment 1.
The Engineer's construction estimate was $650,000. The Project was advertised to bid on January 6 and
13, 2020. Five sealed bids ranging from $687,500 to $1,327,000 were received and publicly opened on
January 30, 2020. The Capital Projects Division conducted a technical and commercial review of the bids
and determined that Sonnikson and Stordahl Construction, Inc. is the lowest responsive and responsible
bidder with a bid amount of $687,500. A summary of bids received is shown in Attachment 2.
Staff will administer the construction contract and will provide contract management, administration, and
office engineering. Inspection services will be provided under an existing agreement with Consolidated
Construction Management, Inc. Staff recommends retaining B&V to provide construction support services
for this Project because of their roles as the architect and structural firm in preparing the plans and
specifications. B&V will perform submittal reviews, address requests for information, and provide direction
for any proposed design changes. I n addition, B&V will coordinate with the Fire Department during the
permit process for fire and life safety purposes, and provide final record drawings for the Project. A new
amendment has been negotiated with B&V to provide services during construction in an amount not to
exceed $120,000.
CEQA:
Staff has concluded that this Project is exempt from CEQA under Central San's CEQA Guidelines
Section 15301, since it involves minor alterations to existing public facilities involving no expansion of use.
Approval of this Project will establish the Board's independent finding that this Project is exempt from
CEQA.
ALTERNATIVES/CONSIDERATIONS
The Board may elect to reject bids and postpone the construction of the Treatment Plant Safety
Enhancements - Phase 5 project to a future fiscal year. However, this is not recommended as this work is
necessary prior to the Solids Project for the safety of Central San staff, outside contractors, and visitors.
FINANCIAL IMPACTS
The total estimated project cost is $1,180,000, which includes the construction contract, contingency,
construction management, and consultant costs, as detailed in Attachment 3. All planning and design pre-
bid expenditures was originated under the Solids Project and will be transferred to the Project upon
authorization of the construction award.
The Project construction budget was included in the Fiscal Year 2019-20 Capital Improvement Budget on
page 194 at$700,000; additional funds are required to complete the Project. The increase in project cost
is due to the following factors:
February 20, 2020 Regular Board Meeting Agenda Packet- Page 84 of 161
Page 3 of 6
• The budgetary figure was derived from a single stairway without platforms and access to other
building exits;
• Current building and fire code compliance added costs for additional lighting and other egress
related items; and
• Additional design was needed to meet the seismic standards developed under the Solids Project,
which resulted in more structural components to build.
There are sufficient funds available in the Solids Project budget; therefore, a budget transfer in the amount
of $480,000 will be made to fund this Project.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the February 4, 2020 meeting
and recommended approval of the subject.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of$687,500 for the construction of the Treatment Plant
Safety Enhancements — Phase 5, District Project 7364, to Sonnikson and Stordahl Construction,
Inc., the lowest responsive bidder;
3. Authorize an amendment to the existing professional services agreement with Black and Veatch
Corporation in the amount of $120,000 for engineering construction support services; and
4. Authorize the General Manager to execute Contract Documents subject to submittal requirements
and include up to a 15-percent contingency.
Strategic Plan Tie-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL FOUR: Develop and retain a highly trained and innovative workforce
Strategy 3- Meet or exceed industry safety standards
GOAL FIVE:Maintain a Reliable Infrastructure
Strategy 3- Protect District personnel and assets from threats and emergencies
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post Bid/P reconstruction Estimate
February 20, 2020 Regular Board Meeting Agenda Packet- Page 85 of 161
Page 4 of 6
0 200 400
FEET
Basin A South \' \
\\\ c�1i- \
\� s04,
CONSTRUCTION \�\ lli �,
SITE
SOLIDS
NDITIONI
PROJECT AREA BUILDING
SOLIDS CONDITIONING BUILDING i 1
❑ � I I
O a II
00
Aeration CLA IERS
Tanks (SOUT UAD)
o PRIMARY
O S DIMENTATI N i
TANKS i
0
I
�1
No o0 El
i
o
❑ PUMP AND BLOWER
BUILDING
° -- D
w O POD HOB
j/� P�PGE IMHOFF PLACE
Central Contra Costa Treatment Plant Attachment
Y Sanitary District Safety Enhancements - Phase 5
AIM t 1
District Project 7364 Location
AM
Map
February 20, 2020 Regular Board Meeting Agenda Packet- Page 86 of 161
Page 5 of 6
ATTACHMENT 2
TREATMENT PLANT SAFETY ENHANCEMENTS — PHASE 5
DISTRICT PROJECT 7364
SUMMARY OF BIDS
PROJECT NO.: 7364 NO. OF ADDENDA: 2 DATE/TIME: JANUARY 30, 2020/2:00 PM
PROJECT NAME: TREATMENT PLANT SAFETY ENHANCEMENTS — PHASE 5
PROJECT MANAGER: CRAIG MIZUTANI
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $650,000
NO. BIDDER BID PRICE
1 Sonnikson & Stordahl Construction, Inc. $687,500
Martinez, California '
2 GSE Construction Company Inc. $768,800
Livermore, California
3 Aztec Consultants, Inc. $858,300
San Ramon, California
4 Saboo Inc. $873,000
Brentwood, California '
5 CWS Construction Group, Inc. $1,327,000
Novato, California
BIDS OPENED BY /s/Katie Young DATE: January 30, 2020
February 20, 2020 Regular Board Meeting Agenda Packet- Page 87 of 161
Page 6 of 6
ATTACHMENT 3
TREATMENT PLANT SAFETY ENHANCEMENTS - PHASE 5
DISTRICT PROJECT 7364
POST-BID/PRECONSTRUCTION ESTIMATE
No. Item Description Amounts Construction
Cost
1 CONSTRUCTION
a. Construction Contract $687,500
b. Contingency at 15% $103,500
c. Permits $4,000
SUBTOTAL - CONSTRUCTION COST $795,000 100%
2 CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $30,000
- Operations Support $5,000
b. Consultants
- B&V (Consultant) $120,000
- Inspection $35,000
SUBTOTAL- CONSTRUCTION MANAGEMENT $190,000 24%
3 PRE-BID EXPENDITURES
Planning and Design (Staff and Consultants) $195,000 24%
4 TOTAL ESTIMATED CONSTRUCTION COST $1,180,000
February 20, 2020 Regular Board Meeting Agenda Packet- Page 88 of 161