HomeMy WebLinkAbout07.a.1) Construction Update on CSOD FacilityCentral C ontra t; November 10, 2010 File: 8208.51.5.14 TO: HONORABLE BOARD OF DIRECTORS. VIA: JAMES M. KELLY, GENERAL MANAGERY ; �- N ANN E. FARRELL, DIRECTOR OF ENGINEERING �. Y � TAD J. PILECKI, CAPITAL PROJECTS DIVISION MANAGER" FROM: ALEX ROZUL, SENIOR ENGINEER SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY, CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208 At the November 4, 2010 Board meeting, staff reported that the contractor was 32 calendar days behind schedule. The contractor's work is progressing steadily with current activities focused on completing the building frame and exterior, and preparing the site for the wet weather season. As of November 10, 2010, the contractor had not submitted an update to his schedule, and thus remains at 32 calendar days behind schedule with 260 calendar days remaining. Staff will keep the Board updated on the construction progress. /cb NAPESUP \CONST\District Projects \8208 \131D Memo CSOD Schedule 11- 10.doc