HomeMy WebLinkAbout06.a.3) Rept-CSOD Construction Update6.a.$) Central Contra Costa Sanitary District October 29, 2010 File: 8208.51.5.14 TO: HONORABLE BOARD OF DIRECTORS VIA: JAMES M. KELLY, GENERAL MANAGER ANN E. FARRELL, DIRECTOR OF ENGINE RING TAD J. PILECKI, CAPITAL PROJECTS DIVISION MANAGE FROM: ALEX ROZUL, SENIOR ENGINEER SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY, CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208 At the October 21, 2010 Board meeting, staff reported that the contractor was 32 calendar days behind schedule. The contractor's work is progressing steadily with current activities focused on completing the building frame and exterior, and preparing the site for the wet weather season. As of October 29, 2010, the contractor remains at 32 calendar days behind schedule with 272 calendar days remaining. Staff will keep the Board updated on the construction progress. /cb NAPESUP \CONST\District Projects \8208 \BD Memo CSOD Schedule 10- 28.doc