HomeMy WebLinkAbout05.a.1) Handout-CSOD Construction UpdateItem No. 5.a.1
CSOD Facility
Construction Update
October 21, 2010
CSOD Administration, Crew and
Warehouse Facility
• Original Contract Time
• Time added
547 days
23 days
• Current Contract Time
• Time Elapsed
• Construction Delay
570 days
284 days - 50%
32 days*
*Made up 14 days in September
1
CSOD Administration, Crew and
Warehouse Facility
• Original Contract Amt $8,455,000
• Change Orders 15 / $105,118 / 1.2%
• Total Project Amt $8,560,118
• Total Paid to BCI $2,519,387
Issues of Concern
• Construction is behind schedule
— CCCSD and Contractor are evaluating
schedule to determine if adjustments to
sequence of activities or activity durations
are appropriate
• Preparing the site for winter weather
— Hydro- seeded bare slopes and installed
BMPs to protect against sediment pollution
in storm water runoff
2