Item No. 9.a.1
Recent Construction
Challenges Requiring
Board Input
August 5, 2010
Item No. 9.a.1
Hall Drive Sewer ~ .
Renovation Project R/W
Issues
• Staff unable to obtain easements for 43 and
47 Camino Encinas.
• Planned sewer construction will be deleted
from the project and' included in 2011 project
•-Staff will continue to pursue property rights
which may include eminent domain action
Results in contract cost reduction of $100,000
of which $24,000 was for drilling pipe
1
N ~ ~~t ,x,yi.
'.
K~.p • ~ •-; s a
s
Item No. 9.a.1
Hall Drive Sewer Re-Drill
• On July 19th after the main line was installed,
discovered discrepancy with elevation
between main line and existing sewer lateral
• Lateral elevation at the house was lower than
depicted in design. t
• Best solution was to lower the main line
elevation by re-drilling main line.
Item No. 9.a.1
Hall Drive Sewer Re-Drill
• Original Bid
for drilling pipe
• Re-Drill - 380 LF
• Deeper excavation
• Total
• Delete drilling 150 LF
Camino Encinas
1,512 LF @ $160/ft
$60,800
$9, 820
$70, 620
($24,000)
• Net Amount of Change Order. _. $46,620
1,
4
2
,~ «
J
Item No. 9.a.1
Hall Drive Sewer Re-Drill
• Executed Change Order - $46,620 within
GM authority
• Informed the Capital Project committee,
then proceeded with Change Order
• Demonstrates possible future problem if
urgent issue > $50,000.
• Possible solutions to be discussed with
Capital Projects Committee Aug 1 im
Item No. 9.a.1
CSOD Sub-contractor.
Substitution Request
• Whiting/Stillwater Concrete Construction
(WCC), sub-contractor for concrete
construction has walked off the job due to
financial problems '
• Bobo Construction will self perform concrete.
work on the current schedule critical path
• Future specialty concrete work that WCC was
to perform will require a replacement
subcontractor, and BCI intends to replace
WCC
` 3
~~
Item No. 9.a.1
Public Contract Code
Section 4107
• Requires "awarding authority or duly
authorized officer" approval to substitute a
subcontractor
• Identifies situations to allow substitution
• Requires notice to the sub-contractor and
gives him 5 working days to object.
• If there is an objection, requires a hearing to
complete approval
CSOD Sub-contractor
Substitution Request
Item No. 9.a.1
• Staff recommends approving Item 10.c., a
position paper requesting delegation to the
General Manger to approve the sub-
contractorsubstitution
• Staff will present proposed solution for
addressing this issue at the Capital Projects
Committee meeting Aug 11t"
• Any proposed solution will be brought back to
the full Board for approval
4