HomeMy WebLinkAbout13. Authorize agreement with MWH Constructors, Inc. for constructability review and related pre-bid services for Solids Handling Facility Improvements, DP 7348 Page 1 of 11
Item 13.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: DECEMBER 19, 2019
SUBJECT: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A PROFESSIONAL
ENGINEERING SERVICES AGREEMENT WITH MWH CONSTRUCTORS,
INC. IN AN AMOUNT NOT TO EXCEED $400,000 FOR CONSTRUCTABILITY
REVIEW AND RELATED PRE-BID SERVICES FOR THE SOLIDS
HANDLING FACILITY IMPROVEMENTS, DISTRICT PROJECT 7348
SUBMITTED BY: INITIATING DEPARTMENT:
NATE HODGES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
Board of Directors' (Board) authorization is required for the General Manager to execute a professional
engineering services agreement in an amount greater than $100,000.
BACKGROUND
The Solids Handling Facility Improvements, District Project 7348 (Solids Project), is currently under
design and expected to be ready for bid in early 2020. Prior to bidding, staff will provide a project update
and request approval to advertise by the Board at a future Board Meeting. The project design is being
done by Black and Veatch Corporation (B&V) and includes major renovation of the following solids
handling processes:
• Sludge Blending and Storage
• Sludge Dewatering
• Multiple Hearth Furnaces (MHFs)
December 19, 2019 Regular Board Meeting Agenda Packet- Page 213 of 260
Page 2 of 11
• Building and MHFs Seismic Improvements
• Air Pollution Control (Wet Scrubbers)
• Ash Handling Improvements
Due to the size and complexity of this project, staff has determined that third-party construction
management (CM) is required. The CM scope of work is divided into two parts:
1. Pre-bid services that include review services for constructability, construction cost estimate, bid
documents, and assistance with pre-qualifications of contractors and specialized trades.
2. Construction management, including inspection services, specialty inspection, start-
up/commissioning services, project documentation, and other related services during construction.
Staff issued a formal Request for Proposal on September 9, 2019 to provide third-party CM that would
include pre-bid services, construction management, inspection, special inspection, and other related
services. Central San received proposals from eight CM firms: 4Leaf, Inc., Carollo Engineers, CDM
Smith, Consolidated CM, HDR, Inc., K&B Construction Inspection Services, Inc., Kennedy Jenks, and
MWH Constructors, I nc. B&V was not allowed to submit as it would be a conflict of interest to perform
construction management on their own design.After reviewing the proposals and conducting interviews
with the top ranking firms (Carollo Engineers, CDM Smith, HDR, Inc., and MWH Constructors, Inc.), staff
selected MWH Constructors, Inc. (MWH)for this project. MWH is a national construction and global firm.
With their involvement as CM, they will be not be able to bid on the construction contract.
Staff received the Solids Project 90-percent design submittal on November 25, 2019.A construction
management review of the submittal is needed at this time in order for B&V to incorporate such input into
the final design. Staff is requesting this agreement now with MWH in order to begin part 1 identified above
to complete the pre-bid services.
One specific tool that MWH employs in their constructability review is a time lapse software model that can
simulate the construction as projected by the designer. MWH can integrate B&V's design model and
construction schedule to analyze the sequence of construction to find building conflicts and identify
potential sequence issues. MW H will also review the engineer's estimate and provide a second opinion
from a contractor's point of view. With over 700 drawings and 1,700 pages of technical specifications, staff
needs additional support that MW H can provide.
Staff will request an increase in the MWH agreement for additional construction management services for
the duration of the project at the time of award of the construction contract.
ALTERNATIVES/CONSIDERATIONS
The Board could consider the following alternatives or provide other direction:
1. The Board may choose not to authorize the agreement with the selected CM firm at this time and
wait until bids are opened for the project construction next spring; however, this is not recommended
as these services are needed now to validate the constructability of the design and confirm the
engineer's cost estimate for the State Revolving Fund loan application.
2. The Board may direct staff to perform these activities in-house or differently. Staff is currently
performing review and oversight of the project. However, MW H, being a contractor, has specialized
construction knowledge and experience that is particularly applicable for the Solids Project with the
software model and schedule analysis. Therefore, this alternative is not recommended.
December 19, 2019 Regular Board Meeting Agenda Packet- Page 214 of 260
Page 3 of 11
FINANCIAL IMPACTS
The MW H agreement for pre-bid services is estimated to cost up to $400,000. These costs were
budgeted under the Solids Handling Facility Improvements on page 182 of the Fiscal Year 2019-20
Capital Improvement Budget.
The final CM scope of work and fee is currently being negotiated with MW H and the final cost ceiling will
be presented for Board authorization when staff awards the construction contract, which is expected in late
summer 2020. Depending on the services recommended by staff, the total agreement may reach over
$6.5 million.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at its meeting on December 10,
2019, and recommended approval of the subject.
RECOMMENDED BOARD ACTION
Authorize the General Manager to execute a professional engineering services agreement with MW H
Constructors, I nc. in an amount not to exceed $400,000 for constructability review and related pre-bid
services for the Solids Handling Facility Improvements, District Project 7348.
Strategic Plan re-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 1 - Manage assets optimally throughout their lifecycle, Strategy 2- Facilitate long-term capital renewal and
replacement
ATTACHMENTS:
1. Presentation
December 19, 2019 Regular Board Meeting Agenda Packet- Page 215 of 260
SOLIDS HANDLING FACILITY IMPROVEMENTS
DISTRICT PROJECT 7348 UPDATE AND
CONSTRUCTION MANAGEMENT
- - Board Meeting
December 19, 2019
Jean-Marc Petit
Director of Engineering and Technical Services
Edgar J. Lopez
Capital Projects Division Manager
RECOMMENDED
SOLIDS HANDLING FACILITY PROJECT
1 2 7 4 5 8 3 6
f
®r"
lit 'e
_ r
J —J
iiQ
SLUDGE BLENDING/5-GE LIME.IDDITIOX MULE HEARTH AIRPOLLUTION SCBSEISMH A-- EMERGENCY URGE
SYSTEM NANACES CONTADL AEFAOFIT LDW -DUT
Z
CENTRAL SAN
1
LARGE AND COMPLEX PROJECT
• Safety oversight I
• Construction coordination and r
A
sequence
• Shear walls and seismic
modifications(building and
incinerators) J
• New wet scrubbers
• Commissioning new systems
and operating existing facilities
Solids Conditioning Building
(SCB)contains critical "
equipment not scheduled for +.
replacement(cogeneration
system, boilers,scum
thickener,and others)
:e 3
CENTRAL SAN
PROJECT STATUS
• Key equipment pre-
selected at 12/20/18 KEY EQUIPMENT PRE-SELECTED
Board meeting
• Received 90% Design Cenhfuge9(4)
Submittal on 11/25/19, homAnd"u
separation
includes 700 drawings Technologies.
c.
and 1,700 pages of Cake Pumps(4) T'
hom Schwing
technical specifications BiosPL
Alr Pollution
• Completed Request for Consent
Proposal (RFP)for third- v'o le"°m
party contract documents "lemationpt.Inc
review and construction
management(CM) u cemoe.ao,aoiseoamn+rr:• Q`.
services
1. 4
CENTRAL SAN
2
PROJECT SCHEDULE
• State Revolving Fund(SRF)Loan -�•*'
Application update before
12/31/2019 - -
• Complete contract documents
review by MWH Constructors, Inc. I 1 ly
(MWH)by March 2020
• Schedule contractor's informational
workshops for early January 2020
• Pre-qualify general contractors,
electrical subcontractors,and
possibly others by February 2020 --
• Complete final contract documents
to be ready for bidding by April 2020
Update Board and request
authorization to advertise project
a
s
SOLIDS PROJECT SITE AND STAGING AREAS
0.
NyPpwer � s
j r
ser area *: �}
•' Sludge Blending Tanks(SBT)
CENTRAL SAN
3
ANTICIPATED DESIGN AND CONSTRUCTION
SCHEDULE
Equipment Pre-Selection �J
Final Design
Constructability Review
by CM and Contractor Ili
Pre-Selection
Bid and Award Phase .
Construction I...�....'
CM Services
V Equipment Pre-Selection:January 2018—September 2018
Final Design Phase:May 2018—March 2020
Constructability Review by CM and Pre-Selection of Contractor:December 2019—March 2020
Bid and Construction Phase:April 2020—December 2023
Construction will require careful coordination with Operations and Maintenance
Fiscal Year(FY) ` J
CENTRAL SAN
ANTICIPATED CASH FLOW FOR PROJECT
FORECASTED OVER THE NEXT FIVE YEARS AS OF
DECEMBER 20, 2018
$30 M
FY 2019-20 Budget
$25 M for DP 7348:
$93.4 Million (M)*
$20 M
■rngineering Preliminary E m1plPiNg Tes5ng
Central San Manage.ent
$15 M ■ranwlteat Dm1gnlranstrutllm Mwegemem
■ranua,�uan
$10 M _ _ ■tgd"a Mrrt
$5 M
0
0 6
0 }Y IOIY I W019 FT]11i9 J0 FY POM li FY 102111 FYIa]11:5
* Revised Total Project Cost Estimate is approximately$130 million(update
to be provided at a future Board workshop),of which SRF Loan is expected
to fund up to$99 million.
a
CENTRAL SAN
4
ice~ r is�
6z IM
L�
II
■
-ilk ` 1 -�
—, II II II
• Manage construction project while Central San staff focuses on project impact to daily
operations and maintenance.
• Identify cost efficiencies throughout the project from a constructor's point of view.
• Help identify and mitigate project risks.
• Provide daily input related to contractor's schedule and changes.
• Track SRF loan required documentation. 9
PROJECT CONSTRUCTION ORGANIZATIONAL CHART
CENTRAL SAN PROJECT
MANAGEMENT TEAM
• Coordinate with Central San staff
and all parties
• Manage project budgets
• Approve progress payments,
invoices,change orders(COs),etc.
• Major decision maker
CENTRAL SAN CONSTRUCTION MANAGEMENT DESIGN ENGINEERS
OPERATIONS& (MWH Constructors,Inc.) Services During Construction
MAINTENANCE Construction management (Black&Veatch Corporation)
(O&M)STAFF Safety oversight
CONTRACTOR --- Daily inspection Review submittals
• Review and -- Answer requests for
implement Document tracking information
• Point of contact with Start u ort
shutdowns contractor P support
• Operating and Design clarifications
of Conduct progress meetings Review final O&M manuals
uilding Review paymentsand asset information
es Manage and review Produce electronic record
A�Mai,ntenance
sioning contractor's schedule drawings
• Claims or dispute services
• Coordinate shutdowns
• Specialty inspection
(electrical or others)
• Start up and commissioning _
• Manage project closeout
documentation `•10
• SRF records compliance ��
5
CM SELECTION PROCESS
• Staff issued a formal RFP on September 9, 2019 to provide
third-party CM that would include pre-bid services, construction
management, inspection, special inspection, and other related
services.
• Central San received proposals from eight CM firms: 4Leaf,
Inc., Carollo Engineers, CDM Smith (CDM), Consolidated CM,
HDR, Inc., K&B Construction Inspection Services, Inc.,
Kennedy Jenks, and MWH. Black&Veatch Corporation (B&V)
was not allowed to submit, as it would be a conflict of interest to
perform CM on their own design.
• After reviewing the proposals and conducting interviews of the
top-ranking firms (Carollo Engineers, CDM, HDR, and MWH),
staff selected MWH for the project. MWH is a national and
global construction firm and with their involvement as CM, they
will not be able to bid on the construction contract.
rCENTRAL SAN
I
I i
k �
WHY MWH
CONSTRUCTORS?
With over 700 drawings and over 1,700 pages of
technical specifications,staff needs additional
review support and MWH has the experienced
II I staff to help.
• One specific tool that MWH employs in their
constructability review is a time lapse software
model that can simulate the construction as
projected by the designer.MWH can integrate
�6+ B&V's design model and construction schedule
IP to analyze the sequence of construction to find
building conflicts and identify potential sequence
issues.
MWH will also review the engineer's estimate
- - and provide a second opinion from a contractor's
point of view.
iz
6
Introducing MWH Constructors
MWH TODAY CM:., by the Numbers
I
• 20%1 Owned by Senior Leadership
• In excess of$1 B Bonding (exclusive of SFPUC has.. $ B fn Wet lnfrasuuaure Capital
$1 B project) rraprovement pr pd5
• Staff of 2,200+ 74 years deliserirg complex construction
Ower managemeMe%penenre
• Stand-Alone Global Construction and CM
10 wa[erlwasterrater
Services Company [aliform CAA Team Treatment Plans New.
ma^ate Expanslon contracts m
wast ra etor rroatmvnt Planes the past Syears
Sawcraga a Solrtl Waste l Partnered wa /Ztas[ rer
DCONSTRUCTORS G)Water Treatment a Dosalina[inn Plains x rh-we thin cbe ns In Lallf"la
®water Transmission pinus
Building a Better World mwatnr sulll, 60
--
or roused Professiwsals
�`•' based in[alifomia
13
DIGITAL DELIVERY TO SUPPORTCOST AND
CONSTRUCTABILITY REVIEWS
Construction BIM Project Review
■ 4� f Critical to Succes
17... 4
L--- --
INPUT FROM DESIGN BIM MANAGE AND AS-BUILT INTEGRATION
AND SCHEDULE TEAMS COORDINATE [Enhanced with Mobile and Reality Capture]
14
7
STAFF RECOMMENDATION
Staff recommends that the Board authorize the General
Manager to execute a professional engineering services
agreement with MWH Constructors, Inc. in an amount
not to exceed $400,000 for constructability review and
related pre-bid services for the Solids Handling Facility
Improvements, District Project 7348.
QUESTIONS?
ri
L
%
H..
` 16
8