CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: NOVEMBER 21, 2019
SUBJECT: AUTHORIZE THE GENERAL MANAGER TO: 1) INCREASE THE
CONSTRUCTION CONTRACT CONTINGENCY BYAN ADDITIONAL
$465,000 FOR THE PLANT OPERATIONS BUILDING SEISMIC UPGRADES
AND SERVER ROOM RELOCATION, DISTRICT PROJECTS 7362 AND
8243; AND 2) TRANSFER $465,000 FROM THE CAPITAL IMPROVEMENT
BUDGET CONTINGENCY TO FUND THESE PROJECTS
SUBMITTED BY: INITIATING DEPARTMENT:
NATHAN HODGES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
Board of Directors' authorization is required to increase the contract contingency above the budgeted
amount at time of award.
BACKGROUND
The Plant Operations Building (POB) Seismic Upgrades and Server Room Relocation, District Projects
(DP) 7362 and 8243 (Project), was awarded to CWS Construction Group, Inc. (CWS) on November 1,
2018. This Project is currently under construction and was aimed to address the following needs:
• Seismic deficiencies associated with the POB, including Operations staff offices and the main
treatment plant (plant) Control Room, Board Room, and Multi-Purpose Room (MPR). This included
asbestos and lead paint abatement required during demolition;
November 21, 2019 Regular Board Meeting Agenda Packet- Page 56 of 91
Page 2 of 20
• Identified risks (seismic and security) associated with increased use of the MPR for Central San
meetings, public use, and Emergency Operations Center(EOC);
• I mprove reliability and eliminate the risk of interrupted services (business and plant operations)
associated with the location of the Information Technology (IT) server room, which is currently
located in a flood prone basement;
• Public restroom accessibility and ADA (Americans with Disabilities Act) compliance near the MPR
and Headquarters Office Building (HOB) lobby;
• I mprove Permit Counter area due to increased daily demand; and
• Security concerns identified at the HOB lobby and MPR.
CWS' bid consisted of a base bid amount and three additive bid items. The base bid included the seismic
upgrades to the POB, improvements to the MPR, including public restrooms, and construction of a new
server room. Staff recommended and the Board awarded the additive bid item to renovate the HOB lobby.
The remaining two other additive bid items were not included in the award to CWS. The award resulted in
a construction contract of$5,665,000 and a contract contingency of 10 percent.
Staff is requesting an increase of the contingency through the transfer of the balance of the Capital
Improvement Budget (CI B)for Fiscal Year(FY) 2019-20 contingency ($465,000). This would increase
contingency from 10 percent to 18.2 percent of authorized contract contingency. The primary drivers for
the use of contingencies to date are Central San-directed change orders. The main reason for requesting
additional funds is to allow staff to have the resultant contingency capacity to address anticipated change
orders and to complete the Project.
Central San-directed costs include additional construction effort to modify elements of the Project, most of
which are associated with the POB, to address: 1) mechanical (HVAC), electrical and plumbing (MEP),
structural, architectural (including roofing and insulation), and environmental issues (lead paint and
asbestos removal) and challenges encountered during construction that were unknown at the time of bid;
2) requests from the plant Operations staff; and 3) additional work related to other POB improvements.
Another reason for the budget increase is to potentially purchase the three office trailers (including all
furnishings) installed by CWS to temporarily relocate POD staff. These trailers will be used in future
construction projects (e.g. Solids Handling Facility Improvements, DP 7348 (Solids Project) and Filter
Plant and Clearwell Improvements-Phase 1A, DP 7361)which will all require similar construction office
trailers. This would save Central San from requiring contractors to furnish and then decommission
temporary office trailers for each major construction project forecasted to be ongoing for the next decade
at the plant. The costs for the trailers will be funded through the Solids Project.
1. Mechanical, electrical, structural, architectural, environmental issues, and challenges
encountered during construction:
a) POB Remodeling and Rehabilitation - While the POB houses administrative offices on the first
floor, it is also a plant process building housing the Control Room, significant plant related MEP,
electrical services and existing electrical interconnections to critical plant equipment and controls.
The Project specifications and drawings identified new MEP work to be performed within the POB
that staff had to integrate into the existing systems. Due to the intricacies and lack of reliable as-built
drawings of the existing systems, MEP and especially electrical systems, we encountered several
vulnerabilities to the POB electrical system which led to some temporary electrical shutdowns. As a
result, the contractor was directed and paid to scan all floors for electrical conduit to thoroughly
investigate all electrical circuits, including adding electrical equipment so that future shutdowns would
November 21, 2019 Regular Board Meeting Agenda Packet- Page 57 of 91
Page 3 of 20
be prevented.As the POB remodeling work is still under construction and not completed, these
challenges and issues are ongoing and additional cost will be incurred to resolve these issues until
the Project is completed.
b) POB Steel Framing Modifications - During the installation of the complex and substantive steel
framing for the seismic retrofit, the steel connections had to be modified numerous times to
accommodate existing building structural elements and contractor requests for changes. Like the
electrical issues listed above, existing as-built drawings of the structural POB were limited.
Opportunities to conduct extensive field verifications during the design were not feasible. Therefore,
the structural engineer had to re-design and modify many of the connections to adapt the design to
actual field conditions and to accommodate contractor's means and methods.As the work is not
completed, these steel framing modifications are ongoing and additional cost will be incurred to
resolve these issues until the Project is completed.
c) Server Room -Additional subgrade civil preparation work had to be done for the new server room
once the excavation was completed to add electrical conduits. Building control joints and roofing
details were required to be modified to connect the existing POB structure with the new server room
structure.Additional electrical conduits were needed to be installed for the server room to
accommodate the future cooling requirements; this work is now completed.
d) Lead Paint,Asbestos, and POB Atrium - During the modifications of the existing steel, lead paint
and asbestos removal was identified. In addition, removal of asbestos in the sidewalls of the planters
and water feature box(pool) in the POB atrium area by the lunch room is needed. Removal and
abandonment of the planters and of the pool will make better use of the space in the atrium area. I n
addition, the pool uses potable water and requires unnecessary ongoing maintenance which would
be eliminated. The planters are in disrepair and cause some safety and potential health concerns.
This abatement work needs to proceed before the finished space is completed and staff moves
back into the building; this work is ongoing.
2. Accommodate Requests from the Plant Operations:Additional work to accommodate requests
made by Operations during construction include:
a) POB restrooms and shower and locker room facilities: I n order to perform the heavy structural
modifications in these facilities, they had to be closed to staff during construction. Initially, it was
anticipated that staff would use other Central San restrooms and shower and locker room facilities;
however, due to the Memorandum of Understanding labor provisions and requirements, temporary
shower and locker room facilities (one for each gender)were installed for the Project. The cost for
additional rental will continue until staff can move back into the POB and use the locker rooms and
showers. With the remodeling of the existing POB locker rooms and showers coming to an end, the
additional rental cost for these temporary facilities should be ending too.
b) Modifications to add offices to accommodate the consolidation of the regulatory compliance
engineers, manager, and POD staff to the POB office space area. This work is completed.
c) Minor re-design of the administration area. This work is completed.
d) Upgrades and replacement of some of the existing power source to better protect plant electrical
equipment. This activity is ongoing.
3. Additional Work Related to other POB improvements: Other improvements to the POB that were added
to CWS'scope of work include:
a)Additional security modifications to the MPR doors in order to accommodate emergency exit
November 21, 2019 Regular Board Meeting Agenda Packet- Page 58 of 91
Page 4 of 20
procedures and restrict public access to the plant. This work is ongoing.
b) Re-routing of the existing HOB lobby electrical to provide for improved safety and access. This
work is completed.
ALTERNATIVES/CONSIDERATIONS
Alternative 1: Reject the additional contingency amount, which is not recommended. The current
contingency of 10 percent is insufficient to cover all the work stated above and to pay for normal change
orders expected to complete a project of this size and complexity. This Project is still under construction
and the additional funds are needed to complete the Project.
Alternative 2: Revise the approved percentage of the requested additional contingency amount to a lower
percentage of dollar amount. The current contingency of 10 percent is insufficient to cover all the work
stated above and to pay for normal change orders expected to complete a project of this size and
complexity. This Project is still under construction and the additional funds are needed to complete the
Project. Under this alternative, staff may need to come back to the Board for additional funds at a later
Board meeting in order to complete the Project.
Purchasing the three office trailers from CWS is a long-term cost saving to Central San as compared to
rental cost that would need to be incurred on future capital projects that are upcoming at the plant site.
These office trailers would be used and made available for future construction to house Construction
Management staff, inspectors, project administration staff, and to provide spaces to hold construction
progress meetings.
FINANCIAL IMPACTS
To date, a total of$494,454 has been issued in change orders and charged to the Project. This
constitutes 8.73 percent contract contingency.
Staff is requesting to increase the construction contract contingency by an additional $465,000 for the
Plant Operations Building Seismic Upgrades and Server Room Relocation, District Projects 7362 and
8243. This is the remaining amount of the C I B Contingency available for FY 2019-20 which would be
transferred from the Capital Program Contingency to fund these projects.
The General Manger will transfer the funds needed upon approval by the Board of the additional
contingency. Staff will continue to closely manage the construction and review all contractor submitted
potential change order requests.Any contingency funds not used will be returned to the Sewer
Construction Fund.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed and discussed this subject on November 19, 2019,
and its recommendation will be presented to the Board at the November 21, 2019 meeting.
RECOMMENDED BOARD ACTION
Authorize the General Manager to:
1. Increase the construction contract contingency by an additional $465,000 for the Plant Operations
Building Seismic Upgrades and Server Room Relocation, District Projects 7362 and 8243; and
2. Transfer$465,000 from the Capital Improvement Budget Contingency to fund these projects.
November 21, 2019 Regular Board Meeting Agenda Packet- Page 59 of 91
Page 5 of 20
Strategic Plan Tie-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 2- Facilitate long-term capital renewal and replacement, Strategy 3- Protect District personnel and assets
from threats and emergencies
ATTACHMENTS:
1. Presentation
November 21, 2019 Regular Board Meeting Agenda Packet- Page 60 of 91
11. Updated Presentation
ATTACHMENT 1
POB SEISMIC UPGRADES,
11 DISTRICT PROJECT (DP) 7362
& SERVER ROOM RELOCATION, DP 8243
UPDATE
Board Meeting
November 21, 2019
- Jean-Marc Petit
Director of Engineering and Technical Services
Edgar J. Lopez
Capital Projects Division Manager
PROJECT BACKGROUND
• Several key project elements were identified over the past nine years in the Capital Improvement
Budgets(CIBs),2009 Seismic Study,and reaffirmed in both the Comprehensive Wastewater
Master Plan(CWMP)and Security Study in 2017
• A Request for Proposal(RFP)was issued in 2016 for a preliminary design consultant for the
server room,following flooding and damage to the servers in the basement.A RFP was issued in
2017 for a design consultant for the Plant Operations Building(POB)seismic project and general
facility improvements
• MWAArchitects was selected and the design contract awarded on May 18,2017 for a combined
project
Combined POB Seismic Upgrades,DP 7362 and Server Room Relocation,DP 8243 into one bid
package and is funded from many CIB projects and programs
Completed Design between May 2017—July 2018
• Previously presented to the Engineering&Operations(E&O)Committee on July 9,2018 for an
update on project status and recommendation approval to advertise project to bid.Presented to
the Board on July 19,2018 for approval to advertise project to bid
• Completed Design and Advertised for Bid on July 31 and August 5,2018.Opened bids on
September 10,2018
Presented to the E&O Committee on September 17,2018 and authorized by the Board on
November 1,2018
• Tour of POB Seismic Retrofit Project(Special Board Meeting)on July 11,2019
2
KWHIM-1912,ME
1
staying
�❑
POB ~ea
i
Main Sate
MPR
0
Tempmary Pvo'
Staff Relocation
Lobby
mr—ements
Temporary POC]
New$pn@q Staff Relocation =
Roam I
ARERAM P
Centrd Coma Cpl ,ti'rAL'H]1t\r
sanitary of:rrict POB SEISArIiC:IIPi;RAUE5&SERVER ROOM RL:LUL'AIlU\
DISTRICT PROJECT 7362&$243 1
PROJECT LOCATION
3
ISSUES AND CONCERNS BEING ADDRESSED
BY THIS PROJECT:
1. Seismic deficiencies associated with the POB, MPR (also used as
the Emergency Operations Center(EOC)), Board Room, and
Operations staff offices and main Control Room
2. Identified risks (seismic and security)associated with increased
use of the MPR for Central San meetings, public use, and EOC;
3. Improve reliability and eliminate the risk of interrupted services
(business and plant operations)associated with the location of the
Information Technology (IT)server room, which is currently located
in a flood prone area;
4. Public restroom accessibility and ADA(Americans with Disabilities
Act)compliance near the MPR and HOB lobby;
5. Improve Permit Counter area due to increased daily demand;
Security concerns identified with HOB lobby and MPR; and
6. Asbestos and lead paint abatement as required.
r--� 4
CENTRALSAN
2
-�irihwvm. 'ri,
yppp u
. .- .. . . .- . ... SCD
CENTRAL SAN
� 1
yF� _
I I �-
1
HEAVY DUTY
STRUCTURAL SEISMIC
BRACING
CENTRAL SAN
i,
STRUCTURAL SEISMIC BRACING
STRUCTURAL SEISMIC BRACING
_ � I
41,
S
CENTRAL SAN
MPR SEISMIC BRACING
• y.
11�10 4 �
�c=CD
CENTRALSAN
� 4
Ste.
STRUCTURAL WORK
IN MPR
MPR
+fie• _-,-— -=- --.. _
CENTRALSAN
��. 1 � 1►
Lt 1!
t+
POB HALLWAY BY MPR
POB OFFICES
r'
��=CD
CENTRALSAN
~r
POD OFFICES
STRUCTURAL SEISMIC
q ' BRACING
CENTRAL SAN
POB STAFF SHOWER
AND LOCKER ROOMS
��=CD
CENTRALSAN
}
I` I
ASBESTOS AND LEAD REMOVAL
�c=CD
CENTRALSAN
I
IT Staff
��� ■i�!�'��'���SO� f ISTT
/ IM Him,
h 60M
W-c�CD
-
CENTRALSAN
rs SERVER ROOM
r' RELOCATION
PROJECT
' ti .
' y 1a. __- '•�.+k`_. _i•• Tri;':`'��,.+1�!
pl
CENTRALSAN
iL
■
CENTRALSAN
MPR PUBLIC RESTROOMS
L
��=CD
CENTRALSAN
ANEW ~
r--- � low
r HOB LOBBY
Change Order Timeline
$130,000 10%
$110,000
8%
$90,000
6%
$70,000 —
$50,000 4%
$30,000
2%
$10,000
01-Nor18 12-Mar-19 06-M1y-19 04-tun-19 1 111-11 14-tun-19 25-Jul-19 26-Sep-19 08-Oct-19 24-0c1-19 19-011-19 0%
5(10,000) NTP 1 2 3 5 6 7 9 10 11 12
$130,000) �pmount —Percent of Contract —Cumulative Percentage -2%
FT
odate,a total of$494,454 has been issued in change orders and charged to the Project. 23
his constitutes 8.73 percent Project contingency.
Change Order Analysis
for POB Seismic and Server Room Projects
Change Orders Percentage to Date Change Orders Amount to Date
29.76%
$147,128
makwom,
Ir
5.97%
$29,513
•Architectural •Electrical •Fire IT•Shower Trailers •Numbing/Meth. •Structural/Environ
$494,454 or 8.73%of Project contingency
12
PENDING PROJECT BUDGET INCREASE
Pending/Possible Project Costs by Percentage
Pending/Possible Project Costs by Amount
1.12%
Ilk
$5,200 ANAg
0.86%
IN18FOO,
•Architectural •Electrical •HVAC
•IT •Structural/Environmental •E#ended Project Duration
•Project Unassigned
$465,000 from Capital Improvement Budget contingency
zs
BUILDING RETROFIT PROJECTS
OFTEN REQUIRE ADDITIONAL BUDGET
• Seismic Improvements for HOB, DP 8226, had a total project
budget at award for$5,716,000, included 15% contingency.
Added $225,000 for budget overrun.
• Pump and Blower Building Seismic Upgrades, DP 7291, was
not determined by a traditional low bid (since no bids were
originally received). Contract was done as a Guaranteed
Maximum Price Agreement and awarded for$6,780,000. This
project exceeded the total project budget of$829,000.
However, this project finished under budget.
26
CENTRALSAN
13
HISTORY OF PROJECT OVERRUN FOR
CENTRAL SAN
Over the past six years, only 3 projects out of 45 projects valued at
approximately $125,000,000, that are closed, have required additional
funding after award during construction:
• FY 14-15: 9 closed projects, 1 overrun -Walnut Creek Sewer($9,000)
• FY 15-16: 10 closed projects, zero overrun
• FY 16-17: 13 closed projects, 1 overrun -4737 property improvements
($23,000)
• FY 17-18: 5 closed projects, zero overrun
• FY 18-19: 8 closed projects, 1 overrun - Grayson Creek Project ($1 M+)
Over the past six years, 0.82% overrun for construction awards
21
CENTRALSAN
ALTERNATIVES/CONSIDERATIONS
Alternative 1: Reject the additional contingency amount,which is not
recommended.The current contingency of 10 percent is insufficient to
cover all the work stated above and to pay for normal change orders
expected to complete a project of this size and complexity.
Alternative 2: Revise the approved percentage of the requested
additional contingency amount to a lower percentage of dollar amount.
The current contingency of 10 percent is insufficient to cover all the work
stated above and to pay for normal change orders expected to complete a
project of this size and complexity.
This Project is still under construction and the additional funds are needed
to complete the Project.
Under this alternative, staff may need to come back to the Board for
additional funds at a later Board meeting in order to complete the Project.
28
CENTRALSAN
14
REVISED TOTAL ESTIMATED
PROJECT BUDGET
Total Estimated Project Cost at Award-November 1,2018 which
includes 10 percent*project contingency on$5,665,500 award to $ 8,125,000
CWS
Additional Project Increase in Contingency $ 465,000
Revised Total Estimated Project Cost-November 2019 $ 8,590,000
*To date,a total of$494,454 has been issued in change orders and charged to
the Project.This constitutes 8.73 percent Project contingency.
29
_aCENTRALSAN
BOARD ACTIONS AND RECOMMENDATIONS
Staff recommends the following:
1. Authorize the General Manager to increase the
construction contract contingency by an additional
$465,000 for the Plant Operations Building Seismic
Upgrades and Server Room Relocation, District
Projects 7362 and 8243; and
2. Authorize the General Manager to transfer $465,000
from the Capital Improvement Budget Contingency to
fund these projects.