HomeMy WebLinkAbout06. Receive July 2019 Financial Statements and Investment Reports Page 1 of 36
Item 6.
,jjlk CENTRAL SAN
CENTRAL CONTRA COSTA SANITARY DISTRICT
September 5, 2019
TO: HONORABLE BOARD OF DIRECTORS
FROM: CHRISTOPHER THOMAS, FINANCE ADMINISTRATOR
KEVIN MIZUNO, FINANCE MANAGER
REVIEWED BY: PHILIP LEIBER, DIRECTOR OF FINANCE AND ADMINISTRATION
ANN SASAKI, DEPUTY GENERAL MANAGER
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE JULY2019 FINANCIAL STATEMENTS AND INVESTMENT
REPORTS
Attached for review are the Financial Statements and Investment Reports for the month of July 2019. The
attached monthly budget-to-actual reports exclude Operations and Maintenance (O&M)fund detail by
division as this information is generated and monitored internally.
Although early in the fiscal year, J my 2019 budgetary results for the O&M, Sewer Construction, Self
Insurance, and Debt Service funds suggest current year activities to date are generally on target with no
noteworthy or alarming unfavorable budgetary variances identified at this time. Staff will continue to
monitor the budget closely throughout the fiscal year and bring any matters requiring budgetary direction
and action to the Board at a later date as necessary.
Receipt of the July 2019 Financial Statements is recommended by the Finance Committee.
Strategic Plan re-In
GOAL THREE: Be a Fiscally Sound and Effective Water Sector Utility
Strategy 2- Manage costs
ATTACHMENTS:
1. July 2019 Financial Statements and Investment Reports
September 5, 2019 Regular Board Meeting Agenda Packet- Page 57 of 201
Pale 1 of 35
CENT CONTRA COSTA SANITARY DISTRICT
August 19,2019
TO: THE BOARD OF DIRECT
VIA: KEVIN MIZUNO W,
FROM: CHRIS THOMAS C-7
SUBJECT: O&M Variance Analysis
The following are brief year-to-date variance explanations through period ending July 31,2019
YTD
Total FY YTD YTD Fav/(Unfav)
O&M Revenues: Budget Budgeted Actual Variance Explanation
Total $ 89,560,370 $ 531,895 $ 499,262 $ (32,633) No significant variance
O&M Expenses:
Total Labor Charges $ 52,789,084 $ 4,342,671 $ 4,250,833 $ 91,838 Some positions budgeted for in July are filled later in the fiscal year resulting in savings.
Chemicals 1,620,000 134,997 22,210 112,787 Chemical consumption lower than budgeted.
Utilities 4,209,350 350,773 41,565 309,208 Lower due to delay in invoices.
Repairs&Maintenance 5,242,867 436,883 133,713 303,170 Budget is spread evenly throughout the year, however actual activity occurs sporadically
every month. Variance should be minimal by year end.
Professional&Legal Services 874,300 72,850 1,052 71,798 Lower due to delay in invoices.
Outside Services 3,639,547 369,092 221,488 147,604 Lower due to delay in invoices.
Materials&Supplies 2,152,127 179,299 76,149 103,150 Budget is spread evenly throughout the year, however actual activity occurs sporadically
every month. Variance should be minimal by year end.
Other Expenses 2,464,834 84,861 27,786 57,075 Budget is spread evenly throughout the year, however actual activity occurs sporadically
every month. Variance should be minimal by year end.
Unfunded Liabilities 12,436,841 1,036,383 933,224 103,159 Variance due to vacancy projections spread evenly throughout the year, however actual
staffing terminations and additions occurs sporadically during the year.
All Other 2,155,825 935,895 845,068 90,827 Minor variances for multiple account categories.
Total $ 87,584,775 $ 7,943,704 $ 6,553,088 $ 1,390,616.
September 5, 2019 Regular Board Meeting Agenda Packet- Page 58 of 201
Page 2 of 35
j&W lics entral Contra Costa Sanitary District
Protecting public health and the environment
Revenue Report MTD
Fund: 001 - RUNNING EXPENSE(O&M)
July 2019 Fiscal Period 1/2020
Report Generated on Aug 19, 2019 8:14:05 AM
Category MTD Estimate MTD Actual MTD%Rev YTD Estimate YTD Actual YTD%Rev Annual Estimate Unrealized Balance Annual%Rev
Concord $0 ($45,667) 0.0% $0 ($45,667) 0.0% $14,570,000 $14,615,667 -0.3%
HHW $8,000 $5,935 -25.8% $8,000 $5,935 -25.8% $968,000 $962,065 0.6%
Other $414,729 $415,628 0.2% $414,729 $415,628 0.2% $4,931,500 $4,515,872 8.4%
Sewer Service Charges $109,166 $123,366 13.0% $109,166 $123,366 13.0% $69,090,870 $68,967,504 0.2%
Total Revenue $531,895 $499,262 -6.1% $531,895 $499,262 -6.1% $89,560,370 $89,061,108 0.6%
Page 3 of 35
ACV ts entral Contra Costa Sanitary District
Protecting public health and the environment
Expense Report - District Summary MTD
Fund: 001 -RUNNING EXPENSE(O&M)
July 2019 Fiscal Period 01/2020
Report Generated on Aug 19, 2019 8:12:50 AM
$8,000,000.00 Budget
$7,943,704
Actual
$7,000,000.00
$6,553,088
$6,000,000.00
$5,000,000.00
$4,000,000.00
$3,000,000.00
$2,000,000.00
$1,000,000.00
$0.00
Jul(1)2019
Fiscal Periods
Page 4 of 35
AwLcentral Contra Costa Sanitary District
Protecting public health and the environment
Expense Report - District Summary MTD
Fund: 001 - RUNNING EXPENSE(O&M)
July 2019 Fiscal Period 01/2020
Report Generated on Aug 19, 2019 8:12:50 AM
Category Period Budget Period Actual Period Variance % YTD Budget YTD Actual YTD Variance % Annual %
Budget
SALARIES&WAGES $3,152,929 $3,002,415 $150,514 4.8% $3,152,929 $3,002,415 $150,514 4.8% $38,060,443 7.9%
EMPLOYEE BENEFITS $1,560,433 $1,630,990 ($70,557) -4.5% $1,560,433 $1,630,990 ($70,557) -4.5% $19,177,010 8.5%
CAPITALIZED ADM OVERHEAD ($370,691) ($382,572) $11,881 -3.2% ($370,691) ($382,572) $11,881 -3.2% ($4,448,369) 8.6%
DIRECTOR FEES&EXPENSES $12,053 $10,534 $1,519 12.6% $12,053 $10,534 $1,519 12.6% $144,650 7.3%
CHEMICALS $134,997 $22,210 $112,787 83.5% $134,997 $22,210 $112,787 83.5% $1,620,000 1.4%
UTILITIES $350,773 $41,565 $309,208 88.2% $350,773 $41,565 $309,208 88.2% $4,209,350 1.0%
REPAIRS&MAINTENANCE $436,883 $133,713 $303,170 69.4% $436,883 $133,713 $303,170 69.4% $5,242,867 2.6%
HAULING&DISPOSAL $98,842 $9,534 $89,308 90.4% $98,842 $9,534 $89,308 90.4% $1,186,175 0.8%
PROFESSIONAL&LEGAL SERV $72,850 $1,052 $71,798 98.6% $72,850 $1,052 $71,798 98.6% $874,300 0.1%
OUTSIDE SERVICES $369,092 $221,488 $147,604 40.0% $369,092 $221,488 $147,604 40.0% $3,639,547 6.1%
SELF-INSURANCE EXPENSE $825,000 $825,000 $0 0.0% $825,000 $825,000 $0 0.0% $825,000 100.0%
MATERIALS&SUPPLIES $179,299 $76,149 $103,150 57.5% $179,299 $76,149 $103,150 57.5% $2,152,127 3.5%
OTHER EXPENSES $84,861 $27,786 $57,075 67.3% $84,861 $27,786 $57,075 67.3% $2,464,834 1.1%
UNFUNDED LIABILITIES $1,036,383 $933,224 $103,159 10.0% $1,036,383 $933,224 $103,159 10.0% $12,436,841 7.5%
Total Expenses $7,943,704 $6,553,088 $1,390,616 17.5% $7,943,704 $6,553,088 $1,390,616 17.5% $87,584,775 7.5%
Color Key: 0 to 10%over budget > 10%over budget M
Page 5 of 35
ACV Central Contra Costa Sanitary District
Protecting public health and the environment
Expense Report - By Department MTD
Fund: 001 - RUNNING EXPENSE (O&M)
July 2019 Fiscal Period 01/2020
Report Generated on Aug 19, 2019 8:15:04 AM
$3,000,000 ❑Period Budget $3,000,000 ❑YTD Budget
❑Period Actual ❑ YTD Actual
$2,500,000 $2,500,000-
$2,000,000 $2,000,000-
$1,500,000- $1,500,000-
$1,000,000- $1,000,000-
$500,000- $500,000
$0
$0 LL
?-k�G� `�\G° �\ °
Q��c e�Q��e S�P��° ��� Pa `5���� ����G°���°��°
Period Budget Period Actual Period Variance YTD Budget YTD Actual YTD Variance
ADMINISTRATION $2,690,691 $2,408,837 $281,854 $2,690,691 $2,408,837 $281,854
ENGINEERING $1,354,963 $1,180,479 $174,484 $1,354,963 $1,180,479 $174,484
COLLECTION SYSTEM OPS. $1,247,796 $999,070 $248,726 $1,247,796 $999,070 $248,726
PLANT OPERATIONS $2,276,829 $1,678,140 $598,689 $2,276,829 $1,678,140 $598,689
PUMP STATIONS $241,210 $168,048 $73,162 $241,210 $168,048 $73,162
RECYCLED WATER $132,215 $118,516 $13,699 $132,215 $118,516 $13,699
Totals $7,943,704 $6,553,088 $1,390,616 $7,943,704 $6,553,088 $1,390,616
Page 6 of 35
CENTRAL CONTRA COSTA SANITARY DISTRICT
RUNNING EXPENSE FUND
TEMPORARY INVESTMENTS
July,2019
INVESTMENTS
(cents omitted) INTEREST INCOME
DATE OF
Days to ANNUAL CASH B.O.M. PURCHASE E.O.M. E.O.M %of CURRENT B.O.M. E.O.M.
NO. ISSUER TYPE PURCHASE MATURITY Maturity YIELD OUTLAY FACE VALUE(MATURITY) FACE VALUE MKT VALUE Portfolio MONTH CUMULATIVE CUMULATIVE
519 State of Calif. LAW 10/99- ....... 1 (1) $12,000,000 $15,000,000 ($3,000,000) $12,000,000 $12,020,541 100.00% $29,721 $0 $29,721
RE09 FHLB FED AGENCY 12/24/18 7/22/19 0 2.558% 5,000,000 (5,000,000) 0.00% 7,263 7,263
RE10 FHLB FED AGENCY 12/24/18 7/23/19 0 2.558% 5,000,000 (5,000,000) 0.00% 7,608 7,608
RE11 FHLMC FED AGENCY 3/4/19 7/23/19 0 2.443% 5,000,000 (5,000,000) 0.00% 7,394 7,394
RE12 FHLB FED AGENCY 3/22/19 7/23/19 0 2.410% 5,000,000 (5,000,000) 0.00% 7,364 7,364
(3) $12,000,000 $35,000,000 ($23,000,000) $12,000,000 $12,020,541 100.00% 59,350 59,350
(2)
$59,350 $0 $59,350
NOTE:(1) Annual yield of Local Agency Investment Fund(LAIF)varies with the composition of the Fund.
The yield as of July,2019 was 2.379%.
(2) The face value indicates the value of the investment if held until maturity,which is the usual District Practice.
(3) The weighted average yield of the total Running Expense portfolio is 2.4437%.
(4) The market value of the portfolio on July,2019 wa!$12,020,541.
(5) The District has sufficient funds available combined with secured SSC and Property Tax received in December and April to cover
six months of cash flow needs.
COMPLIANCE STATEMENT:
All investments comply with the District's internal investment policy approved by the Board of Directors
September 5, 2019 Regular Board Meeting Agenda Packet- Page 63 of 201
Page 7 of 35
' Central Contra Costa sanitary District
Protecting public health and the environment
Balance Sheet
Fund:001-RUNNING EXPENSE(O&M)
July 2019 Fiscal Period 1/2020
Summarized by Account
Report Generated on Aug 19,2019 8:06:06 AM
TOTAL ASSETS
Current Assets
CASH ACCOUNTS/CASH $12,187,455
CASH ACCOUNTS/PAYROLL CLEARING $20,000
CASH ACCOUNTS/PETTY CASH $3,400
CASH ACCOUNTS/TEMPORARY INVESTMENTS $12,000,000
DEFERRED OUTFLOWS/DEFERRED OUTFLOWS-GASB 68 $21,503,021
DEFERRED OUTFLOWS/DEFERRED OUTFLOWS-GASB 75 $30,400
DUE FROM/DUE FROM S/C $866,183
INVENTORY/SUPPLIES&MATERIAL INV $2,147,077
PREPAID ACCOUNTS/PREPAID CAFETERIA PLAN $46,104
PREPAID ACCOUNTS/PREPAID COMMUTER PLAN $572
PREPAID ACCOUNTS/PREPAID EXPENSES $13,918
PREPAID ACCOUNTS/PREPAID INSURANCE $456,492
PREPAID ACCOUNTS/PREPAID RETIREMENT $16,798,678
RECEIVABLE ACCOUNTS/A/R-SSC DIRECT BILL $2,469
RECEIVABLE ACCOUNTS/ACCOUNTS RECEIVABLE $16,515,972
RECEIVABLE ACCOUNTS/ACCOUNTS RECEIVABLE-COBRA ($4,095)
RECEIVABLE ACCOUNTS/ACCRUED INTEREST A/R $29,721
RECEIVABLE ACCOUNTS/COMPUTER PURCHASE PROGRAM $14,726
RECEIVABLE ACCOUNTS/DEPOSITS TO BANK ESCROW $101,362
RECEIVABLE ACCOUNTS/OVERTIME INSPECTION A/R $1,026
Current Assets $82,734,480
Net Property,Plant and Equipment
CONTRIBUTED FIXED ASSETS/ACC DEPR-CONTRIB ASSETS ($63,652,332)
CONTRIBUTED FIXED ASSETS/CONTRIBUTED SEWER LINES $162,344,781
FIXED ASSETS-C.I.P./CONSTRUCTION IN PROGRESS $45,917,681
FIXED ASSETS/ACC DEPR-BUILDINGS ($15,427,731)
FIXED ASSETS/ACC DEPR-ENTERPR SOFTWARE ($168,283)
FIXED ASSETS/ACC DEPR-FURN&EQUIP ($10,415,521)
FIXED ASSETS/ACC DEPR-OUTFALL ($3,919,770)
FIXED ASSETS/ACC DEPR-PUMPING STATIONS ($37,309,198)
FIXED ASSETS/ACC DEPR-SEWAGE COL SYS ($78,758,161)
FIXED ASSETS/ACC DEPR-TREATMENT PLANT ($235,704,155)
FIXED ASSETS/ACC DEPR-VEHICLES ($5,296,931)
FIXED ASSETS/ACCUM DEPRC-RECY WATER ($10,355,662)
FIXED ASSETS/BUILDINGS $44,379,479
FIXED ASSETS/ENTERPRISE SOFTWARE $3,365,658
FIXED ASSETS/FURNITURE&EQUIPMENT $14,579,938
FIXED ASSETS/INTANGIBLE ASSETS $4,949,507
FIXED ASSETS/LAND $17,320,570
FIXED ASSETS/OUTFALL SEWERS $11,371,574
FIXED ASSETS/PUMPING STATIONS $57,327,020
FIXED ASSETS/RECY WATER INFRASTRUCTURE $20,292,366
FIXED ASSETS/SEWAGE COLLECTION FACIL $394,084,852
FIXED ASSETS/TREATMENT PLANT $354,976,293
FIXED ASSETS/VEHICLES $7,490,960
Net Property,Plant and Equipment $677,392,935
TOTAL ASSETS $760,127,415
TOTAL LIABILITIES AND FUND EQUITY
Total Liabilities
ACCOUNTS PAYABLE/SALES TAX PAYABLE ($6,801)
CURRENT LIABILITIES/ACCOUNTS PAYABLE ($1,865,673)
CURRENT LIABILITIES/ACCRUED COMPENSATED ABS. ($5,047,603)
Page 8 of 35
' Central Contra Costa sanitary District
Protecting public health and the environment
Balance Sheet
Fund:001-RUNNING EXPENSE(O&M)
July 2019 Fiscal Period 1/2020
Summarized by Account
Report Generated on Aug 19,2019 8:06:06 AM
CURRENT LIABILITIES/ACCRUED WAGES PAYABLE ($1,258,104)
CURRENT LIABILITIES/CAFETERIA PLAN PAYABLE ($36,085)
CURRENT LIABILITIES/COMMUTER PLAN PAYABLE ($1,266)
CURRENT LIABILITIES/MISC DEPOSITS/LIABILITIES ($139,931)
CURRENT LIABILITIES/OTHER PAYROLL WITHHOLDING ($1,664)
CURRENT LIABILITIES/PERMIT CLEARING ($1,329)
CURRENT LIABILITIES/REFUNDABLE DEPOSITS ($42,080)
CURRENT LIABILITIES/RETIREMENT CONTRIB W/H $3
CURRENT LIABILITIES/WORKERS'COMP INS PAYABLE $800,416
DEF.COMP.CONTRIB W/H/ICMA 457/401A ($19,382)
DEF.COMP.CONTRIB W/H/ICMA TIER III HRA $19,499
DUE TO/DUE TO S/C ($54,873)
DUE TO/DUE TO S/I ($825,000)
LIABILITIES-LONG TERM/DEFERRED INFLOWS-GASB 68 ($28,076,634)
LIABILITIES-LONG TERM/NET OPEB LIAB-GASB 75 ($46,350,454)
LIABILITIES-LONG TERM/NET PENSION LIAB-GASB 68 ($63,806,000)
LIABILITIES-LONG TERM/POST EMP.BENEFIT-PENSION $8,420,816
LIABILITIES/UNEARNED INTEREST $0
MEDICAL LIABILITIES/CALPERS MEDICAL $480,155
MEDICAL LIABILITIES/DELTA DENTAL $117
MEDICAL LIABILITIES/DISABILITY INS $6,620
MEDICAL LIABILITIES/HEALTH NET $335,765
MEDICAL LIABILITIES/KAISER PERMANENTE ($337,108)
MEDICAL LIABILITIES/LIFE INS $6,147
MEDICAL LIABILITIES/OCCUPATIONAL HEALTH ($1,001)
MEDICAL LIABILITIES/VSP VISION CARE ($11)
REIMBURSEMENT FEES ($71,318)
Total Liabilities ($137,872,777)
Total Fund Equity
FUND EQUITY/AVAILABLE FUND BALANCE ($42,245,414)
FUND EQUITY/CAPITAL COST SHARING ($123,029,998)
FUND EQUITY/CONTRIBUTED SEWER LINES ($162,344,781)
FUND EQUITY/EXPENDITURE SUMMARY $6,553,088
FUND EQUITY/GENERAL FIXED ASSET GROUP ($225,386,993)
FUND EQUITY/STATE R FED CAPITAL GRANT ($75,301,279)
YEAR TO DATE REVENUES/REVENUE SUMMARY ($499,262)
Total Fund Equity ($622,254,638)
TOTAL LIABILITIES AND FUND EQUITY ($760,127,415)
Page 9 of 35
CENTRAL CONTRA COSTA SANITARY DISTRICT
August 19,2019
TO: THE BOARD OF DIRPeTQRS
VIA: KEVIN MIZUNO
FROM: CHRIS THOMAS
SUBJECT: Sewer Construction Variance Analysis
The following are brief year-to-date variance explanations through period ending July 31,2019:
YTD
Total FY YTD YTD Fav/(Unfav)
SIC Revenues: Budget Budgeted Actual Variance Explanation
Facilities Capacity Fees, Interest income received was
Total $ 65,598,130 $ 602,413 $ 832,440 $ 230,027 higher than budgeted.
Total FY YTD YTD YTD
S/C Expenses: Budget" Budgeted Actual Remaining %Spent
Total $ 74,669,521 $ 2,066,477 $ 1,627,894 $ 438,583 78.78%
' Includes 18119 carry-over($8,493,521)
September 5, 2019 Regular Board Meeting Agenda Packet- Page 66 of 201
Page 10 of 35
AWLcentral Contra Costa Sanitary District
Protecting public health and the environment
Revenue Report MTD
Fund: 002-SEWER CONSTRUCTION (Capital)
July 2019 Fiscal Period 1/2020
Report Generated on Aug 19, 2019 8:14:05 AM
Category MTD Estimate MTD Actual MTD%Rev YTD Estimate YTD Actual YTD%Rev Annual Estimate Unrealized Balance Annual%Rev
Concord $0 $0 0.0% $0 $0 0.0% $11,630,000 $11,630,000 0.0%
Other $602,413 $774,917 28.6% $602,413 $774,917 28.6% $21,749,000 $20,974,083 3.6%
Sewer Service Charges $0 $57,523 0.0% $0 $57,523 0.0% $32,219,130 $32,161,607 0.2%
Total Revenue $602,413 $832,440 38.2% $602,413 $832,440 38.2% $65,598,130 $64,765,690 1.3%
Page 11 of 35
Sewer Fund (Capital) Spending FY 19-20
$2,500,000
$2,066,477
$2,000,000
$1,500,000 $1,627,894
$1,000,000
$500,000
July
-Projected* -Actual
Columnl July
Projected* $ 2,066,477
Actual 1,627,894
*Projected-Current year budget allocated by month based on historical spending in previous 2 years
September 5, 2019 Regular Board Meeting Agenda Packet- Page 68 of 201
Page 12 of 35
PROGRAM/GM185L4-Modified in Excel CAPITAL IMPROVEMENT BUDGET REPORT ACCOUNTING
CENTRAL CONTRA COSTA SANITARY DISTRICT PERIOD ENDING:7/31/2019 PERIOD 1/2020
(A-B) D E G(C+D+E) H I(F-G)
PROJECT TOTAL TOTAL FY 2019-20 BUDGET ADJUSTED APPROVED TOTAL TOTAL
PROJ BUDGETS EXPENDITURES PROJECT APPROVED ADJUSTMENTS BUDGET EXPENDITURES SPENT IN REMAINING BUDGET
NO PROJECT TITLE PYS(THRU FYE 18-19) PYS(THRU FYE 18-19) CARRY-FORWARD BUDGET FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20
TYPE CS Collection System $ 16,633,417 17,490,252 (856,835) 27,129,000 - 27,129,000 26,272,165 455,064 25,817,128
TYPE TP Treatment Plant 44,592,999 39,917,024 4,675,975 28,631,000 - 28,631,000 33,306,975 578,999 32,727,971
TYPE GI General Improvements 8,695,483 5,883,070 2,812,413 5,369,000 30,000 5,399,000 8,211,413 519,320 7,692,088
TYPE RW Recycled Water 5,239,894 3,377,926 1,861,968 4,152,000 - 4,152,000 6,013,968 74,511 5,939,476
CIB Contingency - - 895,000 (30,000) 865,000 865,000 - 865,000
AL DISTRICT $ 75,161,793 $ 66,668,272 $ 8,493,521 $ 66,176,000 $ $ 66,176,000 r 1,627,894 $ 73,041,66
N:\Accounting\GMTEMPI\Financials and Closing\2020 Financials\Capital Project report-FY 19 20.xlsx July 19
September 5, 2019 Regular Board Meeting Agenda Packet- Page 69 of 201
Page 13 of 35
PROGRAM/GM185L4-Modified in Excel CAPITAL IMPROVEMENT BUDGET REPORT ACCOUNTING
CENTRAL CONTRA COSTA SANITARY DISTRICT PERIOD ENDING:7/31/2019 PERIOD 1/2020
(A-B) D E G(C+D+E) H I(F-G)
PROJECT TOTAL TOTAL FY 2019-20 BUDGET ADJUSTED APPROVED TOTAL TOTAL
PROJ BUDGETS EXPENDITURES PROJECT APPROVED ADJUSTMENTS BUDGET EXPENDITURES SPENT IN REMAINING BUDGET
NO PROJECT TITLE PYS(THRU FYE 18-19) PYS(THRU FYE 18-19) CARRY-FORWARD BUDGET FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20
5991 PH Sewer Renovation Phase 2 460,000 277,771 182,229 - - 182,229 - 182,229
6534 Harper Lane Area CAD 800,000 412,260 387,740 387,740 387,740
*6602 South Jackson CAD 411,290 391,290 20,000 - - 20,000 - 20,000
*6603 North Jackson CAD 276,557 53,313 223,244 223,244 223,244
6679 Coredell Drive CAD 123,443 54,906 68,537 - - 68,537 - 68,537
*7367 Concord Main Metering Station 250,000 245,826 4,174 4,174 1,797 2,377
8419 Collection System Planning LT 985,000 984,958 42 200,000 200,000 200,042 11,600 188,442
8436 Moraga/Crossroads PS Project 3,747,000 3,218,526 528,474 4,600,000 4,600,000 5,128,474 36,542 5,091,932
8441 CIPP Contract 17-20 400,000 275,923 124,077 200,000 200,000 324,077 1,175 322,902
8442 PS Equipment Piping Replacement PH2 61,000 - 61,000 103,000 103,000 164,000 - 164,000
8443 LG Diameter Pipe line Inspection 250,000 18,484 231,516 515,000 515,000 746,516 - 746,516
8444 Force Main Inspection Program 125,000 - 125,000 - - 125,000 - 125,000
*8446 Lafayette Sewer Renovation Phase 12 4,033,600 3,715,186 318,414 - - 318,414 12,036 306,378
8447 Pump Station Security Improvement 156,000 - 156,000 51,000 51,000 207,000 - 207,000
8448 Manhole Modifications 712,000 860,375 (148,375) 309,000 309,000 160,625 - 160,625
8449 Collection System Modeling Support 200,000 130,135 69,865 103,000 103,000 172,865 2,359 170,506
8450 Development Sewerage Support 1,130,000 1,309,893 (179,893) 900,000 900,000 720,107 79,586 640,521
8451 C.S.Sewer Renovation 62,527 - 62,527 4,473,000 4,473,000 4,535,527 - 4,535,527
8452 Lafayette Sewer Ren.Ph.13 500,000 1,561,461 (1,061,461) 3,817,000 3,817,000 2,755,539 64,904 2,690,635
8454 So.Orinda Sewer Ren.Ph.7 500,000 860,185 (360,185) 3,637,000 3,637,000 3,276,815 26,128 3,250,687
8455 W.C.Sewer Renov.Ph.13 500,000 2,604,854 (2,104,854) 3,621,000 3,621,000 1,516,146 69,180 1,446,966
8456 Danville Sewer Ren.Ph.3 500,000 381,637 118,363 4,100,000 4,100,000 4,218,363 7,891 4,210,472
8457 Pump Station Upgrades-Ph.2 50,000 - 50,000 500,000 500,000 550,000 - 550,000
*8458 Martinez Sewer Renov.Ph.6 100,000 11,405 88,595 - 88,595 29,352 59,243
*8459 Lafayette Sewer Renov.Ph.14 100,000 24,336 75,664 - - 75,664 41,464 34,200
*8460 WC Sewer Renov.Ph.14 100,000 53,907 46,093 46,093 32,632 13,461
*8461 So.Orinda Sewer Ren.Ph.8 100,000 43,621 56,379 - - 56,379 38,418 17,961
Rounding 27
lftal FY 2019-20 CS Amount 16,633,417 17,490,252 (856,835) 27,129,000 27,129,000 26,272,165 455,064 25,817,1
*Italic Projects open but not in CIB for 19/20
TYPE TP Treatment Pla
*6172 Sludge Blending Tank Repair 776,000 - 776,000 - - 776,000 246 775,754
7292 Switchgear Refurbishment-Ph.2 684,548 473,274 211,274 200,000 200,000 411,274 - 411,274
7304 Instr&Controls PLC Upgrade 500,000 470,528 29,472 - 29,472 11 29,461
7315 Applied Research and Innovations 557,274 290,336 266,938 300,000 300,000 566,938 - 566,938
7317 Plant Control System Network Upgrades 765,000 281,461 483,539 120,000 120,000 603,539 85,135 518,404
*7320 Plant Energy Optimization 1,094,000 1,004,604 89,396 - - 89,396 11 89,385
*7322 Fire Protection System Ph.2 1,406,000 1,340,832 65,168 65,168 2,268 62,900
*7326 Equipment Replacement FY 15-FY 24 1,629,000 1,628,975 25 - - 25 59,852 (59,827)
N:\Accounting\GMTEMPI\Financials and Closing\2020 Financials\Capital Project report-FY 19 2O.xlsx July 19
September 5, 2019 Regular Board Meeting Agenda Packet- Page 70 of 201
Page 14 of 35
PROGRAM/GM185L4-Modified in Excel CAPITAL IMPROVEMENT BUDGET REPORT ACCOUNTING
CENTRAL CONTRA COSTA SANITARY DISTRICT PERIOD ENDING:7/31/2019 PERIOD 1/2020
(A-B) D E G(C+D+E) H I(F-G)
PROJECT TOTAL TOTAL FY 2019-20 BUDGET ADJUSTED APPROVED TOTAL TOTAL
PROJ BUDGETS EXPENDITURES PROJECT APPROVED ADJUSTMENTS BUDGET EXPENDITURES SPENT IN REMAINING BUDGET
NO PROJECT TITLE PYS(THRU FYE 18-19) PYS(THRU FYE 18-19) CARRY-FORWARD BUDGET FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20
7327 Headwork's Screening Upgrade 8,305,000 8,304,264 736 - - 736 5,440 (4,704)
7328 Influent Pump Electrical improvements 610,000 431,527 178,473 800,000 800,000 978,473 12,515 965,958
7330 Piping Renovation Phase 9 3,180,000 3,127,343 52,657 - - 52,657 2,937 49,720
7339 T.Plant Control System 1/0 Replacement 1,370,000 1,286,269 83,731 1,100,000 11100,000 1,183,731 81 1,183,650
7341 WC/Grayson Creek Levee Rehab 100,000 76,528 23,472 200,000 200,000 223,472 41,280 182,192
7348 Solids Handling Facility Improvements 9,914,000 9,243,507 670,493 6,550,000 6,550,000 7,220,493 80,353 7,140,140
7349 Aeration&Energy Upgrade 1,500,000 749,790 750,210 3,500,000 3,500,000 4,250,210 51,720 4,198,490
7351 Mechanical&Concrete Renovation 5,044,000 5,534,806 (490,806) 6,400,000 6,400,000 5,909,194 140,017 5,769,177
7352 UV Disinfection Upgrades 500,000 294,751 205,249 600,000 600,000 805,249 6,175 799,074
7353 1 Outfall Improvements Ph.7 100,000 1 54,551 1 45,449 1 500,000 1 1 500,000 545,449 1 7,652 1 537,797
N:\Accounting\GMTEMPI\Financials and Closing\2020 Financials\Capital Project report-FY 19 2O.xlsx July 19
September 5, 2019 Regular Board Meeting Agenda Packet- Page 71 of 201
Page 15 of 35
PROGRAM/GM185L4-Modified in Excel CAPITAL IMPROVEMENT BUDGET REPORT ACCOUNTING
CENTRAL CONTRA COSTA SANITARY DISTRICT PERIOD ENDING:7/31/2019 PERIOD 1/2020
(A-B) D E G(C+D+E) H I(F-G)
PROJECT TOTAL TOTAL FY 2019-20 BUDGET ADJUSTED APPROVED TOTAL TOTAL
PROJ BUDGETS EXPENDITURES PROJECT APPROVED ADJUSTMENTS BUDGET EXPENDITURES SPENT IN REMAINING BUDGET
NO PROJECT TITLE PYS(THRU FYE 18-19) PYS(THRU FYE 18-19) CARRY-FORWARD BUDGET FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20
7354 TP Security Improvements 137,000 41,951 95,049 718,000 718,000 813,049 378 812,671
7355 Odor Control Upgrade Ph.1 - - - - -
7357 Plant Wide Instrumentation Upgrade 290,000 77,858 212,142 450,000 450,000 662,142 - 662,142
*7358 Innovation Bioenergy Demo 300,000 270,796 29,204 - 29,204 29,204
7359 Solids Conditioning Bldg.roof replacement 1,300,000 1,195,265 104,735 - - 104,735 - 104,735
7360 Existing Plant Facility Drawing 200,000 158,215 41,785 100,000 100,000 141,785 4,411 137,374
7362 POB Seismic Upgrades 3,331,177 2,850,440 480,737 2,793,000 2,793,000 3,273,737 40,341 3,233,396
7363 Treatment Plant Planning 900,000 719,153 180,847 500,000 500,000 680,847 37,930 642,917
7364 TP Safety Enhancement Ph.5 100,000 10,000 90,000 600,000 600,000 690,000 246 689,754
7369 Piping Renovation-Phase 10 - 750,000 750,000 750,000 - 750,000
7370 Annual Infrastructure Replacement - - - 2,200,000 2,200,000 2,200,000 - 2,200,000
7371 Condition Assessment of Buried Pipelines - 250,000 250,000 250,000 250,000
Rounding (5)
tal FY 2017-18 TP Amount 39,917,024 4 28,631,000 28,631,00
*Italic Projects open but not in CIB for 19/20
TYPE GI General Improvements
8207 General Security and Access $ 134,977 134,975 2 150,000 150,000 150,002 - 150,002
8230 Capital Legal Services 178,665 142,411 36,254 20,000 20,000 56,254 - 56,254
8236 District Easements 258,047 224,799 33,248 75,000 75,000 108,248 3,187 105,061
8240 IT Development 2,738,794 2,456,461 282,333 500,000 500,000 782,333 10,451 771,882
N:\Accounting\GMTEMPI\Financials and Closing\2020 Financials\Capital Project report-FY 19 2O.xlsx July 19
September 5, 2019 Regular Board Meeting Agenda Packet- Page 72 of 201
Page 16 of 35
PROGRAM/GM185L4-Modified in Excel CAPITAL IMPROVEMENT BUDGET REPORT ACCOUNTING
CENTRAL CONTRA COSTA SANITARY DISTRICT PERIOD ENDING:7/31/2019 PERIOD 1/2020
(A-B) D E G(C+D+E) H I(F-G)
PROJECT TOTAL TOTAL FY 2019-20 BUDGET ADJUSTED APPROVED TOTAL TOTAL
PROJ BUDGETS EXPENDITURES PROJECT APPROVED ADJUSTMENTS BUDGET EXPENDITURES SPENT IN REMAINING BUDGET
NO PROJECT TITLE PYS(THRU FYE 18-19) PYS(THRU FYE 18-19) CARRY-FORWARD BUDGET FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20 FY 2019-20
8243 Server Room Relocation 2,000,000 1,351,513 648,487 - - 648,487 14,496 633,991
8249 CSO Dump Pad Modifications 60,000 12,409 47,591 - 47,591 189 47,402
8250 ERP Replacement 600,000 - 600,000 3,105,000 3,105,000 3,705,000 8,500 3,696,500
8251 Capital improvement program&Budget Improvement - 350,000 350,000 350,000 - 350,000
**8252 POB E.V.Charging Station - - - - 30,000 30,000 30,000 - 30,000
8516 District Equipment Acquisition 876,000 798,811 77,189 100,000 100,000 177,189 - 177,189
8517 Vehicle Replacement Program 1,849,000 821,691 1,027,309 1,069,000 1,069,000 2,096,309 482,047 1,614,262
9999 Capital Project Clearing(Accounting Use Only)** - (60,000) 60,000 - 60,000 450 59,550
Rounding (5)
tal FY 2017-18 GI Amo 8,695,483 5,369,000 30,000 5,39 9,320 7,692,088
Not in 19/20 Budget. New projects opened in July 2019. Funds transferred fr Contigency 9990
TYPE RW Recycled Water
N:\Accounting\GMTEMPI\Financials and Closing\2020 Financials\Capital Project report-FY 19 2O.xlsx July 19
September 5, 2019 Regular Board Meeting Agenda Packet- Page 73 of 201
Page 17 of 35
FY 19-20 CAPITAL BUDGET TRANSFERS
PERIOD ENDING:7/31/19
position paper
06/20/19&GM
memo
19/20 Contingency
PROD.# PROJECTS TOTAL Balance
8252 POB E.V.Charging Station 30,000 30,000
9990 Capital Projects-Contingency (30,000) (30,000) 865,000
Total 865,0
September 5, 2019 Regular Board Meeting Agenda Packet- Page 74 of 201
Page 18 of 35
O&M PROJECTS- EXPENDITURE LIST ACCOUNTING
PERIOD ENDING: 07/31/19 1/2020
0M043 - Naval Weapons Station
Prior years Project expended
Expenditure type through 18-19 1 Jul.'19 Aug.'19 Sept.'19 Oct.'19 Nov.'19 Dec.'19 Jan.'20 Feb.'20 Mar.'20 Apr.'20 May'20 Jun.'20 2019-20 YTD to date
Salary&Benefits $ 17,429 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 17,429
Technical Services $ 75,169 1,938 - - - - - - - - - - - 1,938 $ 77,106
Total $ 92,598 $ 1,938 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,9381$ 94,535
0M080 - CoCo Farm(Kiewit Future Farm Proposal)
Prior years Project expended
Expenditure type I through 18-19 1 Jul.'19 Aug.'19 Sept.'19 Oct.119 Nov.'19 Dec.'19 Jan.'20 Feb.'20 Mar.'20 Apr.'20 May'20 Jun.'20 2019-20 YTD to date
Salary&Benefits $ 210,665 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 210,665
Other Charges $ 74,996 - - - - - - - - - - - - - $ 74,996
Total $ 285,661 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 285,661
0M083 - Refinery Recycled Water Exchange
Prior years Project expended
Expenditure type through 18-19 1 Jul.'19 Aug.'19 Sept.'19 Oct.'19 Nov.'19 Dec.'19 Jan.'20 Feb.'20 Mar.'20 Apr.'20 May'20 Jun.'20 2019-20 YTD to date
Salary&Benefits $ 84,070 $ 8,921 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 84,070
other Charges $ - - - - - - - - - - $ - $ -
Total $ 84,070 1$ 8,921 $ $ $ $ $ $ $ $ $ $ $ $ $ 84,070
N:\Accounting\GMTEMPI\Financials and Closing\2020 Financials\O&M Projects Activity YTD 19 20.xlsx
September 5, 2019 Regular Board Meeting Agenda Packet- Page 75 of 201
Page 19 of 35
Page 20 of 36
CENTRAL CONTRA COSTA SANITARY DISTRICT
SEWER CONSTRUCTION FUND
TEMPORARY INVESTMENTS
July, 2019
INVESTMENTS
(cents omitted) INTEREST INCOME
DATE OF Days to ANNUAL CASH B.O.M. PURCHASE E.O.M. E.O.M. %of CURRENT B.O.M. E.O.M.
NO. ISSUER TYPE PURCHASE MATURITY Maturity YIELD OUTLAY FACE VALUE (MATURITY) FACE VALUE MKT VALUE Portfolio MONTH CUMULATIVE CUMULATIVE
519 State of Calif. LAIF 8/86-2/90 ---- 1 (1) $25,000,000 $29,500,000 ($4,500,000) $25,000,000 $25,042,795 43.10% $54,880 $0 $54,880
941 US Gov't T-Bill 2/28/19 8/29/19 28 2.49 3,950,860 4,000,000 4,000,000 3,994,000 6.90% 8,370 0 8,370
942 US Gov't T-Bill 3/4/19 8/29/19 28 2.50 3,951,742 4,000,000 4,000,000 3,994,000 6.90% 8,404 0 8,404
944 T-Bill US Tbill 3/21/19 9/19/19 49 2.50 4,938,575 5,000,000 5,000,000 4,986,550 8.62% 10,463 0 10,463
945 FHLB Agency Gov 4/3/19 10/1/19 61 2.44 4,940,169 5,000,000 5,000,000 4,982,200 8.62% 10,247 0 10,247
946 FHLMC Fed Agency 5/28/19 11/12/19 103 2.37 4,946,100 5,000,000 5,000,000 4,970,250 8.62% 9,946 0 9,946
947 FHLB FHLB Note 6/13/19 12/11/19 153 2.20 4,946,077 5,000,000 5,000,000 4,962,400 8.62% 9,793 0 9,793
948 FHLB Govt/FHLB 6/21/19 11/18/19 122 2.02 4,957,917 5,000,000 5,000,000 4,968,500 8.62% 8,921 0 8,921
(4) $57,631,440 $62,500,000 ($4,500,000) $58,000,000 $57,900,695 100.00% 121,024 0 121,024
(3), (6) (5)
0
$121,024 $0 $121,024
NOTE: (1) Annual Yield of Local Agency Investment Fund (LAIF)varies with the composition of the Fund.
The yield as of July 2019 was 2.379%.
(2) The face value indicates the value of the investment if held until maturity, which is the usual District practice.
(3) The weighted average yield of the total Sewer Construction portfolio is 2.3792%.
(4) The market value of the portfolio on July 31, 2019 was$57,900,695.
GASB 31 requires adjusting investments to market value. The District will adjust annually, but report market values monthly.
(5) The District has sufficient funds available combined with secured SSC and Property Tax received in December and April to cover
six months of cash flow needs.
(6) There was an adjustment made to reduce the investment balance on the District's general ledger for year end in the amount of$8.5M.
This was to reimburse the Running Expense Fund for Sewer Construction payroll related expenses that were paid out of the RE Fund's bank account throughout the year.
The transfer will be made with the County Treasurer during August 2019.
COMPLIANCE STATEMENT: All investments comply with the District's internal investment policy approved by the Board of Directors.
September 5, 2019 Regular Board Meeting Agenda Packet- Page 76 of 201
Page 20 of 35
' Central Contra Costa sanitary District
Protecting public health and the environment
Balance Sheet
Fund:002-SEWER CONSTRUCTION(Capital)
July 2019 Fiscal Period 1/2020
Summarized by Account
Report Generated on Aug 19,2019 8:06:06 AM
TOTAL ASSETS
Current Assets
CAD RECEIVABLE/AVAD-ALHAMBRA VLY AR $820,003
CASH ACCOUNTS/CASH $2,372,786
CASH ACCOUNTS/TEMPORARY INVESTMENTS $49,500,000
DUE FROM/DUE FROM R/E $54,873
RECEIVABLE ACCOUNTS/ACCOUNTS RECEIVABLE $8,038,468
RECEIVABLE ACCOUNTS/ACCRUED INTEREST A/R $54,880
RECEIVABLE ACCOUNTS/CAD RECEIVABLE $394,662
Current Assets $61,235,671
Net Property,Plant and Equipment
FIXED ASSETS-C.I.P./CONSTRUCTION IN PROGRESS $1,627,881
Net Property,Plant and Equipment $1,627,881
TOTAL ASSETS $62,863,552
TOTAL LIABILITIES AND FUND EQUITY
Total Liabilities
ACCOUNTS PAYABLE/SALES TAX PAYABLE ($1,293)
CURRENT LIABILITIES/ACCOUNTS PAYABLE ($1,519,478)
CURRENT LIABILITIES/PROJECT RETENTION PAYABLE ($903,660)
CURRENT LIABILITIES/REFUNDABLE CONST BONDS ($170,786)
DUE TO/DUE TO R/E ($866,183)
LIABILITIES/UNEARNED INTEREST ($154,804)
Total Liabilities ($3,616,204)
Total Fund Equity
EXPENDITURE SUMMARY/TRANSFER TO CIP ($1,627,881)
FUND EQUITY/AVAILABLE FUND BALANCE ($58,414,909)
FUND EQUITY/EXPENDITURE SUMMARY $1,627,881
YEAR TO DATE REVENUES/REVENUE SUMMARY ($832,440)
Total Fund Equity ($59,247,349)
TOTAL LIABILITIES AND FUND EQUITY ($62,863,552)
Page 21 of 35
AwLcentral Contra Costa Sanitary District
Protecting public health and the environment
Revenue Report MTD
Fund: 003-SELF-INSURANCE
July 2019 Fiscal Period 1/2020
Report Generated on Aug 19, 2019 8:14:05 AM
Category MTD Estimate MTD Actual MTD%Rev YTD Estimate YTD Actual YTD%Rev Annual Estimate Unrealized Balance Annual%Rev
Other $85,491 $855,531 900.7% $85,491 $855,531 900.7% $1,025,900 $170,369 83.4%
Total Revenue $85,491 $855,531 900.7% $85,491 $855,531 900.7% $1,025,900 $170,369 83.4%
Page 22 of 35
ACV Central Contra Costa Sanitary District
Protecting public health and the environment
Expense Report - By Department MTD
Fund: 003-SELF-INSURANCE
July 2019 Fiscal Period 01/2020
Report Generated on Aug 19, 2019 8:15:04 AM
$250,000 ❑Period Budget $250,000 ❑YTD Budget
❑Period Actual ❑ YTD Actual
$200,000 $200,000-
$150,000-'
200,000$150,000 ' $150,000-
$100,000- $100,000-
$50,000- $50,000-
$0-
50,000$0 $0
Period Budget Period Actual Period Variance YTD Budget YTD Actual YTD Variance
$226,972 $232,434 ($5,462) $226,972 $232,434 ($5,462)
Totals $226,972 $232,434 ($5,462) $226,972 $232,434 ($5,462)
Page 23 of 35
CENTRAL CONTRA COSTA SANITARY DISTRICT
SELF-INSURANCE FUND
TEMPORARY INVESTMENTS
July,2019
INVESTMENTS
(cents omitted) INTEREST INCOME
DATE OF
Days to ANNUAL CASH B.O.M. PURCHASE E.O.M. E.O.M %of CURRENT B.O.M. E.O.M.
NO. ISSUER TYPE PURCHASE MATURITY Maturity YIELD OUTLAY FACE VALUE (MATURITY) FACE VALUE MKT VALUE Portfolio MONTH CUMULATIVE CUMULATIVE
519 State of Calif. LAW 10/99- ------- 1 (1) $7,200,000 $7,200,000 ($300,000) $6,900,000 $6,911,811 100.00% $13,707 $0 $13,707
(3) $7,200,000 $7,200,000 ($300,000) $6,900,000 $6,911,811 100.00% 13,707 - 13,707
(2)
$13,707 $0 $13,707
NOTE: (1) Annual yield of Local Agency Investment Fund(LAIF)varies with the composition of the Fund.
The yield as of July,2019 was 2.379%.
(2) The face value indicates the value of the investment if held until maturity,which is the usual District Practice.
(3) The weighted average yield of the total Self-Insurance portfolio is 2.379%.
(4) The market value of the portfolio on July 31,2019 was$6,911,811.
COMPLIANCE STATEMENT:
All investments comply with the District's internal investment policy approved by the Board of Directors.
September 5, 2019 Regular Board Meeting Agenda Packet- Page 80 of 201
Page 24 of 35
' Central Contra Costa sanitary District
Protecting public health and the environment
Balance Sheet
Fund:003-SELF-INSURANCE
July 2019 Fiscal Period 1/2020
Summarized by Account
Report Generated on Aug 19,2019 8:06:06 AM
TOTAL ASSETS
Current Assets
CASH ACCOUNTS/CASH $222,454
CASH ACCOUNTS/TEMPORARY INVESTMENTS $6,900,000
DUE FROM/DUE FROM R/E $825,000
RECEIVABLE ACCOUNTS/ACCRUED INTEREST A/R $13,707
Current Assets $7,961,161
TOTAL ASSETS $7,961,161
TOTAL LIABILITIES AND FUND EQUITY
Total Liabilities
CURRENT LIABILITIES/ACCOUNTS PAYABLE ($1,246)
CURRENT LIABILITIES/GASB10 ACTUARIAL RESERVE ($1,157,797)
Total Liabilities ($1,159,043)
Total Fund Equity
FUND EQUITY/AVAILABLE FUND BALANCE $202,052
FUND EQUITY/EMPLOYMENT/POLLUTION RISK ($5,000,000)
FUND EQUITY/EXPENDITURE SUMMARY $232,434
FUND EQUITY/INS PREMS/CLAIMS/LAWSUITS ($1,381,074)
YEAR TO DATE REVENUES/REVENUE SUMMARY ($855,531)
Total Fund Equity ($6,802,118)
TOTAL LIABILITIES AND FUND EQUITY ($7,961,161)
Page 25 of 35
jorM' Central Contra Costa Sanitary District
Protecting public health and the environment
Revenue Report MTD
Fund: 004-DEBT SERVICE
July 2019 Fiscal Period 1/2020
Report Generated on Aug 19, 2019 8:14:05 AM
Category MTD Estimate MTD Actual MTD%Rev YTD Estimate YTD Actual YTD%Rev Annual Estimate Unrealized Balance Annual%Rev
Other $0 $0 0.0% $0 $0 0.0% $2,982,415 $2,982,415 0.0°%
Total Revenue $0 0.0% $2,982,415 $2,982,415 0.0%
Page 26 of 35
ACV ts entral Contra Costa Sanitary District
Protecting public health and the environment
Expense Report - By Department MTD
Fund: 004- DEBT SERVICE
July 2019 Fiscal Period 01/2020
Report Generated on Aug 19, 2019 8:15:04 AM
$80,000 ❑Period Budget $80,000 ❑YTD Budget
❑Period Actual ❑ YTD Actual
$60,000 $60,000-
$40,000-'--
60,000
$40,000 $40,000-
$20,000- $20,000-
$0- $0
�� �■
Period Budget Period Actual Period Variance YTD Budget YTD Actual YTD Variance
$69,784 $0 $69,784 $69,784 $0 $69,784
Totals $69,784 $0 $69,784 $69,784 $0 $69,784
Page 27 of 35
' Central Contra Costa Sanitary District
Protecting public health and the environment
Balance Sheet
Fund:004-DEBT SERVICE
July 2019 Fiscal Period 112020
Summarized by Account
Report Generated on Aug 19,2019 8:06:06 AM
TOTAL ASSETS
Current Assets
L.T.DEBT ACCOUNTING/REVENUE BOND RESERVE CASH $17,135
Current Assets $17,135
TOTAL ASSETS $17,135
TOTAL LIABILITIES AND FUND EQUITY
Total Liabilities
L.T.DEBT ACCOUNTING/BOND ACR INTEREST PAYABLE ($288,505)
L.T.DEBT ACCOUNTING/BONDS PAYABLE ($19,450,000)
Total Liabilities ($19,738,505)
Total Fund Equity
FUND EQUITY/AVAILABLE FUND BALANCE $22,078,000
LIABILITIES/DEFERRAL-BOND REFUNDING ($2,356,631)
Total Fund Equity $19,721,369
TOTAL LIABILITIES AND FUND EQUITY ($17,135)
Page 28 of 35
DASHBOARD DATA
(SELECTED DATA ON MATTERS
OF CONTINUING BOARD INTEREST)
September 5, 2019 Regular Board Meeting Agenda Packet- Page 85 of 201
Page 29 of 35
PENSION AND OPEB
LIABILITY AND FUNDING STATUS
Pension OPEB
Million $160 100% Million $90 100%
$140 90% $80 90%
$120 80% $70 80%
70% $60 70%
$100 60% 60%
$50
$80 50% 50%
$40
$60 40% 40%
30% $30 30%
$40
20% $20 20%
$20 10% $10 10%
$0 0% $0 0%
,LO
16;,",, LOti ,Lti�,titi� ,Lti�,0�ti ,Oti ,O`0,O`0,Otil 10ti00
,LO
iiiiiiiiiiiiiiiiiiii
UAAL Funded% iiiiiiiiiiiiiiiiiiill.IAAL Funded%
Notes:
* Pension:2018 valuation is released summer of 2019.
** OPEB-Valuations projected liabilities less assets as of June 30 of that year
*** Pension funded percentage excludes Section 115 Trust Assets(established in FY 2017-18).
September 5, 2019 Regular Board Meeting Agenda Packet- Page 86 of 201
Page 30 of 35
WHAT CAUSED THE PENSION URAL?
Total LlAAL of$74 Million as of 2017
Al l Other Sources
Restart of km ortization in
2007
Qisrount Rate from 7-75%to
7.25%
Qepooling Implementation
Actuarial ses from 2008
-Sw -$40 -$20 So S20 S-- $60
Millions
Notes:
* Pension:2018 valuation is released summer of 2019.
** OPEB-Valuations projected liabilities less assets as of June 30 of that year
*** Pension funded percentage excludes Section 115 Trust Assets(established in FY 2017-18).
September 5, 2019 Regular Board Meeting Agenda Packet- Page 87 of 201
Page 31 of 35
PENSION UAAL PROJECTION
Anticipated UAAL with Schedule Amortization (Blue)
and with Additional UAAL Payments to Pension Prefunding Trust to Date and at $1.25 million
prospectively (Red)
Millions {80
$70
$60
$50
$40
$30
$20
$10
$0 II ■
■
($10) 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
■Unfunded Liability $74 $67 $61 $53 $45 $34 $28 $21 $13 $4 ($6)
11 Unfunded Liability inclusive of Pension Prefunding $71 $62 $53 $43 $33 $21 $13 $4 $0 $0 $0
Trust
•Change from 2017(Standard 18 yr by annual
9% 8% 10% -12% 14% -8% 9% 11% 12% -13%
layer amortization)
•Change from 2017(with additional
-13% -13% -13% -15% -17% -11% -13% -5%
contributions)
Notes:
• Chart shows scheduled amortization (over 18 years for each annual layer of historic UAAL),assuming no additional UAAL is generated.
• Second bar shows potential further reductions in UAAL given additional discretionary contributions by Central San towards
Pension Prefunding Trust
September 5, 2019 Regular Board Meeting Agenda Packet- Page 88 of 201
Page 32 of 35
CIB TRANSFERS=CURRENT YEAR
#of transfers
Cause for Transfers Total Original Project Budgets and Transfers
z
$30,000
$25,000
1
$20,000
0
$15,000
■ t ■ o ■ `o ■ v ■ a ■ v
p o 0
a v $10 ,000
3 N V X
CO a aiv c v w
Q j u p ' z `^ m
0 p Q o
a, 0 3 v
o t z LL $5,000 + F.Cost exceeded initial budget
" ° w E.New project scope
U
m � -dew C.
New Project
C.Developer/CAD or other cost neutral
s B.Cashflow accelerations
$- AW A.Bundling/Unbundling
O��ao ak0z 'act
Notes:
There was one transfer in July 2019;the establishment of the HOB EV Charging Station Project.
September 5, 2019 Regular Board Meeting Agenda Packet- Page 89 of 201
Page 33 of 35
CIB TRANSFERS SINCE FY 2016=17
Cause for Transfers Total Original Project Budgets and Transfers
#of
transfers
16 $60,000,000
14
12 $50,000,000
10
$40,000,000
8
6
$30,000,000
4
2 $20,000,000
0
$10,000,000 '
F.Cost exceeded initial budget
v E.New project scope
D.New Protect
Y x C. Developer/CAD or other cost neutral
c 3 v
m a ac a �
d
0V Z o B.Cashflow accelerations
3 3 LL $ A.Bundling/Unbundling
0 or v
w Z
0o w a
15
.�
�� me
Notes:
There was one transfer in July 2019;the establishment of the HOB EV Charging Station Project,for a total of 42 transfers since FY 2016-17
September 5, 2019 Regular Board Meeting Agenda Packet- Page 90 of 201
Page 34 of 35
FY 2019-20 Running Expense Fund Total Cash & Investment Balances
(Actuals through July 2019)
$60.0 $59.3
$53.7
$49.8
$50.0 $47.2 $48.6 -
$43.4
$40.9
$40,0 $37.3 - $38.2
$38.4
$33.8 $32.9
$30.0 $29.0
$24.6 $24.2 $24.0
$20.0 $18.9
$10.0
$0.0
> yep O #o
Projected Balance* Actual Balance Reserve Target at Year End**
NOTES: * Projected balances were generated in June 2019 based on budgeted revenues and expenses for FY 2019-20 and applied to the actual balance at Jun 30, 2019
**The Reserve Target at Year End is the minimum balance required at June 30, 2020 to comply with the District Policy
September 5, 2019 Regular Board Meeting Agenda Packet- Page 91 of 201
Page 35 of 35
FY 2019-20 Sewer Construction Fund Total Cash & Investment Balances
(Actuals through July 2019)
$70.0
$62.5
$61.6
$60.0 $56.3 $58.3
56.1
$52.3 $51.9 $52.6 $54.0 $52.1
$50.0 $49.8 47.6 $48.1
$43.2
$40.0 $39.2
$30.0 _ $32.0
$30.4
$20.0
$10.0
$0.0
�o
MProjected Balance* MActual Balance t Reserve Target at Year End**
NOTES: * Projected balances were generated in June 2019 based on budgeted revenues and expenses for FY 2019-20 and applied to the actual balance at Jun 30, 2019
**The Reserve Target at Year End is the minimum balance required at June 30, 2020 to comply with the District Policy
September 5, 2019 Regular Board Meeting Agenda Packet- Page 92 of 201