HomeMy WebLinkAbout03.b. Review draft position paper to authorize the General Manager to execute a construction contract change order in an amount not to exceed $350,000 with C. Overaa & Company for additional bypass work under the Mechanical and Concrete Renovations, Dist Page 1 of 5
Item 3.b.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: SEPTEMBER 3, 2019
SUBJECT: REVIEW DRAFT POSITION PAPER TO AUTHORIZE THE GENERAL
MANAGER TO EXECUTE A CONSTRUCTION CONTRACT CHANGE
ORDER IN AN AMOUNT NOT TO EXCEED $350,000 WITH C. OVERAA &
COMPANY FOR ADDITIONAL BYPASS WORK UNDER THE MECHANICAL
AND CONCRETE RENOVATIONS, DISTRICT PROJECT 7351
SUBMITTED BY: INITIATING DEPARTMENT:
EDGAR J. LOPEZ, CAPITAL PROJECTS ENGINEERING AND TECHNICAL SERVICES-
DIVISION MANAGER CAPITAL PROJECTS
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
Authorization from the Board of Directors (Board) is required in order to execute a construction contract
change order in an amount greater than $200,000.
BACKGROUND
On November 15, 2018, the Board awarded a construction contract to C. Overaa & Company (Overaa) in
the amount of$10,604,000 for the Mechanical and Concrete Renovations, District Project 7351 (Project).
This Project generally consists of concrete structure rehabilitation, major mechanical replacement and
improvements in the Influent Structure and Primary Sedimentation Tanks (PSTs), safety repairs, and work
within other critical structures at the treatment plant (plant). To complete rehabilitation of structures and to
facilitate replacement of critical gates, the Project includes two major bypass pumping efforts; the first at
the Influent Structure and the second at the PSTs effluent structures. The bypass for the Influent Structure
has been completed with successful results. However, the current bypass at the PSTs has been
challenging and cannot meet all the safety and reliability needs for the proposed work under the Project. It
should be noted that while the Influent Structure bypass was successful and staff resolved all the issues
related to that scope of the project, bypassing the Influent Structure and PSTs has never been done at
Central San.
Although the PSTs bypass system as currently installed can be used to perform some of the planned
work, a large portion of the rehabilitation work cannot safely proceed unless the bypass system is
modified. Staff, Overaa, consultants, and the bypass subcontractor(Rain for Rent), have exhausted all
September 3, 2019 Special EOPS Committee Meeting Agenda Packet- Page 5 of 15
Page 2 of 5
options available, including revising the work sequence, operational changes, flow diversion, and modifying
the bypass system design to consider all scenarios. In the end, the best and safest bypass approach
would be to change the piping configuration and discharge point from its current location at Structure C to
the secondary selector channel, which is a further distance away. This change would require two additional
30-inch temporary pipelines, restraints, other equipment, and modifications to the pump discharge. The
selector channel is approximately 950 feet away and will impact access through the plant. The value of all
the repairs and mechanical work during the bypass is approximately$2.5 million.
Time is of the essence; if the proposed work is to proceed this fall as scheduled, then a change order or
work directive will have to be issued as soon as possible. Staff is negotiating the change order with Overaa
and plans to have a refined cost estimate by the time the Engineering and Operations Committee meets
on September 3, 2019.
ALTERNATIVES/CONSIDERATIONS
Alternative No.1: Proceed with the authorization as proposed, which is the recommended alternative.
One consideration and advantage of the additional bypass system, if approved, would be the ability for
staff to investigate and perform a condition assessment of the 72-inch primary effluent channel that feeds
the primary effluent pumps. Like several structures under this Project, the 72-inch primary effluent channel
has been in operation since its inception and has never been out of service. This alternative would allow for
potential concrete repairs of the 72-inch effluent line, which already shows signs of corrosion at the
adjoining structure. Staff would strongly recommend the condition assessment of this critical passageway.
Alternative No. 2:Another alternative is to reschedule the portion of rehabilitation work that cannot be
accomplished with the current bypass, which would be the case if the Board elects not to authorize the
change order. The rehabilitation work is necessary and delaying to a future project would be more costly
since it would require reinstallation of the proposed bypass pumping system. The postponed rehabilitation
work includes repair of a critical bypass valve, Structure B gate, and other adjoining concrete structures.
The current estimated cost for the postponed items is $2.5 million, which would include the bypass costs
valued at over$1 million. Staff does not recommend postponing the work or this alternative since the work
is needed within the next two-three years which will not be able to happen due to several other conflicting
plant projects, including the Outfall Improvements-Phase 7 project.
Alternative No. 3: Do nothing approach, which means do not complete rehabilitation. Some of the
structures are used by Operations on a daily basis, and others are needed for critical bypassing of the
PSTs during emergencies or future project/maintenance activities. This alternative is not recommended.
FINANCIAL IMPACTS
The costs to include the additional bypass system is estimated at$350,000, which includes temporary
piping, labor, equipment and materials needed to perform the bypass safely and reliably.At award, the
project contingency was set at$1 million. To date, staff has issued approximately$102,000 in change
orders and with this proposed work would reach $452,000.Approximately $548,000 project contingency
would be remaining under the Project.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the September 3, 2019 meeting and
recommended
September 3, 2019 Special EOPS Committee Meeting Agenda Packet- Page 6 of 15
Page 3 of 5
RECOMMENDED BOARD ACTION
Authorize the General Manager to execute a construction contract change order with C. Overaa &
Company in an amount not to exceed $350,000 under the Mechanical and Concrete Renovations, District
Project 7351.
Strategic Plan Tie-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL THREE: Be a Fiscally Sound and Effective Water Sector Utility
Strategy 2- Manage costs
GOAL FOUR: Develop and retain a highly trained and innovative workforce
Strategy 3- Meet or exceed industry safety standards
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 2- Facilitate long-term capital renewal and replacement, Strategy 3- Protect District personnel and assets
from threats and emergencies
ATTACHMENTS:
1. Project Reference Photographs
September 3, 2019 Special EOPS Committee Meeting Agenda Packet- Page 7 of 15
Page 4 of 5
Reference Photographs
Mechanical and Concrete Renovations, District Project 7351
-
HUinEY���11��R�i�y�:.➢ aJ-
• r.
Primary Sedimentation Tanks (PST) Bypass System as of August 27, 2019
September 3, 2019 Special EOPS Committee Meeting Agenda Packet- Page 8 of 15
Page 5 of 5
. r L ...........
YLS�M
L4fr }4
Current Construction Activities in PST Nos. 3 and 4
September 3, 2019 Special EOPS Committee Meeting Agenda Packet- Page 9 of 15