HomeMy WebLinkAbout06. Public hearing to consider increasing construction contract retention to 10% (District Project 8436) Page 1 of 10
Item 6.
CENTRAL SAN BOARD OF DIRECTORS
vie
. , . , , . .
POSITION PAPER
MEETING DATE: JULY 25, 2019
SUBJECT: CONDUCT PUBLIC HEARING TO CONSIDER ADOPTING RESOLUTION
NO. 2019-041 FINDING THAT, IN ACCORDANCE WITH CALIFORNIA
PUBLIC CONTRACT CODE SECTION 7201, THE PUMP STATION
UPGRADES - PHASE 1, DISTRICT PROJECT 8436, IS SUBSTANTIALLY
COMPLEX TO JUSTIFY INCREASING THE CONSTRUCTION CONTRACT
RETENTION AMOUNT FROM FIVE PERCENT TO TEN PERCENT
SUBMITTED BY: INITIATING DEPARTMENT:
KEITH GELLERMAN, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey Kenton L. Alm
General Manager District Counsel
ISSUE
California Public Contract Code Section 7201 states that the maximum a public agency may hold as the
construction contract retention is five percent. However, a public agency may find, at a properly noticed
and normally scheduled Board hearing, that a project is substantially complex so as to justify that a higher
amount of retention should be withheld.
BACKGROUND
Staff requests that the Board of Directors (Board) conduct a hearing to consider increasing the
July 25, 2019 Special Board Meeting Agenda Packet- Page 35 of 72
Page 2 of 10
construction contract retention from five percent to ten percent for the Pump Station Upgrades - Phase 1,
District Project (DP) 8436 (Project). The finding to increase the construction contract retention must be
made prior to bidding the Project. If approved by the Board, the increased retention amount and resolution
will be included in the bid documents. The Project is currently scheduled to advertise for public bid in late
August and early September of this year.
The Project proposes renovation at three pump stations, including two of the largest pump stations at
Central San, Moraga and Orinda Crossroads Pump Stations. The Moraga Pump Station is located at
1790 School Street in Moraga, adjacent to a creek and near a school. The Orinda Crossroads Pump
Station is at 10 Camino Pablo in Orinda at Theatre Square. The complex elements of the Project include,
but are not limited to:
• Upgrading electrical and controls for the new electrical wet weather pumps, including new switchgear
and variable speed drives;
• Upgrading backup generators and automatic transfer switch improvements;
• Replacing the wet weather diesel engine driven pumps with electric motors at the Moraga and
Orinda Crossroads Pump Stations;
• Reconditioning or replacing pumps, valves, and gates;
• Replacing/adding surge tanks;
• Replacing six dry-pit pumps with new submersible pumps (bid alternate);
• Adding grinders to the Moraga Pump Station (bid alternate);
• All construction must occur at fully operational pump stations where no alternative redirection of flows
are available;
• Stations located in high-use residential and midtown commercial areas with limited available work
space; and
• Requires oversight and coordination between three pump stations with construction occurring during
the same time.
Due to the complexity of the work, long equipment lead times, and wet weather construction restrictions,
the Project is expected to require a minimum of 24 months to complete. The construction cost estimate
for the Project including all bid alternates is approximately$24 million.
The general contractor, subcontractors, and suppliers will have to carefully coordinate the work to ensure
the timely and safe completion of the Project. The timeframe for most construction activities and critical
work is limited to dry weather, which entails the summer months. Construction at Moraga and Orinda Pump
Stations, including Flush Kleen Pump Station will require timely completion of the project milestones. Any
slippage or missing deadlines will likely result in issues between the contract parties and others. I n the
event that claims should arise from subcontractors or suppliers, a ten-percent retention is more likely to
provide sufficient funds to help address such notices or resolve claims.
Staff believes that the Project is sufficiently complex to justify a ten-percent construction contract retention
as the planned improvements require major modifications to the mechanical, electrical, instrumentation,
and controls systems at the Moraga, Orinda Crossroads, and Flush Kleen Pump Stations. Staff
anticipates that the general contractor will use a number of subcontractors and suppliers and that the
coordination of this work on multiple sites concurrently will be challenging.
ALT ERNAT IVES/CONSIDERAT IONS
The Board has increased retention on construction contracts on several projects, including the Primary
Renovations, DP 7285 and more recently on the Headworks Screening Upgrades, DP 7327. The
decision to increase the retention amount was beneficial for each project since it allowed staff enough
funds to help resolve issues with equipment or disputes with subcontractors. Central San's contract
documents has a provision that allows staff to lower the retention during construction, which has been done
July 25, 2019 Special Board Meeting Agenda Packet- Page 36 of 72
Page 3 of 10
with contractors in the past.
The Board may elect to not hold the hearing and keep the retention amount at five percent or provide
another alternative. However, this is not recommended due to the substantial complexity of the Project.
FINANCIAL IMPACTS
No financial impact is expected. General contractors may choose to increase their bid to cover the costs
of holding additional retention; however, staff believes it would likely be minimal, if any, since bidders are
under low bid requirements in order to compete for the contract.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on July 9, 2019 and
recommended to conduct a public hearing on a regularly scheduled Board meeting and to postpone
CEQA until Project Award.
RECOMMENDED BOARD ACTION
Conduct public hearing to consider adopting proposed Resolution No. 2019-041 finding that, in accordance with
California Public Contract Code Section 7201, the Pump Station Upgrades - Phase 1, District Project 8436, is
substantially complex to justify increasing the construction contract retention amount from five percent to ten
percent.
Strategic Plan Tie-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations, Strategy 2- Strive to
minimize the number of sanitary sewer overflows
GOAL FIVE:Maintain a Reliable Infrastructure
Strategy 3- Protect District personnel and assets from threats and emergencies
ATTACHMENTS:
1. Proposed Resolution
2. Presentation
July 25, 2019 Special Board Meeting Agenda Packet- Page 37 of 72
Page 4 of 10
ATTACHMENT 1
RESOLUTION 2019-041
A RESOLUTION OF THE CENTRAL CONTRA COSTA SANITARY DISTRICT
INCREASING THE RETENTION AMOUNT TO TEN PERCENT FOR THE
PUMP STATION UPGRADES - PHASE 1, DISTRICT PROJECT 8436
WHEREAS, the Central Contra Costa Sanitary District's (Central San) Orinda
Crossroads and Moraga Pump Stations are a part of the collection system and are
critical to the conveyance of wastewater; and
WHEREAS, in 2011 the Legislature modified Public Contract Code Section 7201 to
set the maximum amount that could be withheld by a special district as retention on a
construction contract at five percent and that this retention amount could only be
increased if the public agency found the specific project was sufficiently complex to
warrant it; and
WHEREAS, the Pump Station Upgrades — Phase 1, District Project (DP) 8436 is a
complicated and critical project for Central San; and
WHEREAS, the project includes replacing the 1 ,000 horsepower wet weather
engines, installing new electrical motors and electrical systems for wet weather
pumping, replacing surge tanks, and upgrading controls, all of which need to be
coordinated and constructed in a facility that operates 24 hours a day; and
WHEREAS, the project is in a highly visible residential and midtown commercial
location with limited workspace, where no alternative redirection of flows is available;
and
WHEREAS, the General Contractor, subcontractors, and suppliers will have to
coordinate a substantial amount of the work to ensure the timely and safe completion
of the project during dry weather summer conditions; and
WHEREAS, the nature of the proposed work, schedule, and long lead time for
equipment increases the likelihood of prime contractor, subcontractor, and vendor or
supplier issues and potential claims; and
WHEREAS, the project will require challenging oversight and coordination between
the project locations since the construction will occur at the same time; and
WHEREAS, the Board of Directors held a noticed public hearing on July 25, 2019, to
establish that the Pump Station Upgrades — Phase 1 , DP 8436, is sufficiently
complex to require an increased retention amount of ten percent.
NOW, THEREFORE, BE IT RESOLVED by the Board of Directors of the Central
Contra Costa Sanitary District as follows:
July 25, 2019 Special Board Meeting Agenda Packet- Page 38 of 72
Page 5 of 10
Central Contra Costa Sanitary District
Resolution No. 2019-041
Page 2 of 2
1. That, after holding a noticed public hearing, the Board of Directors finds that in
accordance with Public Contract Code Section 7201, the Pump Station
Upgrades — Phase 1, DP 8436, is a complex project. Furthermore, that this
project's complexity necessitates a retention amount greater than five percent.
2. That the Board of Directors finds that the retention amount for the Pump
Station Upgrades — Phase 1, DP 8436, shall be ten percent.
PASSED AND ADOPTED this 25th day of July, 2019, by the Board of Directors of the
Central Contra Costa Sanitary District by the following vote:
AYES: Members:
NOES: Members:
ABSENT: Members:
David R. Williams
President of the Board of Directors
Central Contra Costa Sanitary District
County of Contra Costa, State of California
COUNTERSIGNED:
Katie Young
Secretary of the District
Central Contra Costa Sanitary District
County of Contra Costa, State of California
Approved as to form:
Kenton L. Alm, Esq.
Counsel for the District
July 25, 2019 Special Board Meeting Agenda Packet- Page 39 of 72
Page 6 of 10
PUMP STATION (PS) UPGRADES
;t
` DISTRICT PROJECT 8436 -
PHASE 1 UPDATE
Special Board Meeting
July 25, 2019
Jean-Marc Petit, Director of Engineering and Technical Services
a Edgar J. Lopez, Capital Projects Division Manager
_ R `
tiaxira-- -
PS UPGRADES PHASING
• Phase 1, District Project `
8436:
hmo:[Men 'b,
• Orinda Crossroads PS �-
pwfee
• Moraga PS
• Flush Kleen PS o�e
• Concord Metering
Vault Improvements
(Under construction
with other project)
• Phase 2: Scheduled for
FY 2019-20 to start !.
design �p
• Martinez PS
Fairview PSP ''
• Maltby PS
` z
1
July 25, 2019 Special Board Meeting Agenda Packet- Page 40 of 72
Page 7 of 10
MORAGA - ORINDA CROSSROADS PUMP STATIONS
Facilities deliver a majority of
wastewater flows from Orinda
and Moraga and are critical
facilities
Moraga and Orinda Crossroads
Pump Stations scope includes: ..
Major electrical upgrades
Instrumentations and controls
upgrades
New standby power systems
New wet weather pumping: _ 1
Electric driven pumps ..
Replace surge tanks `
y 3
ALTERNATE BID ITEMS
Alternate Bid Items:
Orinda Crossroads and Moraga Pump Stations
Install dry pit submersible pumps for added
resiliency
Wet weather casing replacement or rehab
depending on inspection
Moraga PS Only
Install mechanized grinders
�._ (►�14
2
July 25, 2019 Special Board Meeting Agenda Packet- Page 41 of 72
Page 8 of 10
FLUSH KLEEN PUMP STATION
• Oldest PS in our System
(1950)
• Major Improvements: �.
• Electrical, instrumentation
and controls improvements
and upgrades
• Replace standby power
generator f '
d
ANTICIPATED SCHEDULE
• 100% Design Acceptance —August 6, 2019
• Pre-qualifying general contractor and electrical
subcontractors prior to advertising (ongoing)
• Public outreach ongoing with City (ongoing)
• Advertise —August 26, 2019
• Bid Opening — October 7, 2019
• Engineering & Operations Committee — October 15,
2019
• Board Award — November 7, 2019
• Notice to Proceed — November 28, 2019
• Complete construction by Spring 2022 (majority of work
during summer of 2020 and 2021)
� s
3
July 25, 2019 Special Board Meeting Agenda Packet- Page 42 of 72
Page 9 of 10
CURRENT AND FUTURE BOARD ACTIONS
Current:
• Increase construction contract retention from 5% to
10% due to the complexity of the project
Future (at award):
• Construction Management Services (Request for
Proposals in process)
• Engineering Support Services during Construction with
V.W. Housen and Associates (currently negotiating)
RECOMMENDED BOARD ACTIONS
Conduct public hearing to consider adopting Resolution No.
2019-041 finding that, in accordance with California Public
Contract Code Section 7201, the Pump Station Upgrades -
Phase 1, District Project 8436, is substantially complex to
justify increasing the construction contract retention amount
from 5% to 10%
IS
4
July 25, 2019 Special Board Meeting Agenda Packet- Page 43 of 72
Page 10 of 10
QUESTIONS?
N ` g
5
July 25, 2019 Special Board Meeting Agenda Packet- Page 44 of 72