HomeMy WebLinkAbout10. Authorize increase in cost ceiling for Emtec agreement, part of ERP Replacement Project, and adopt amendments to FY 2019-20 Budget to incorporate funding for ERP Project Page 1 of 14 Item 10. CENTRAL SAN BOARD OF DIRECTORS POSITION PAPER MEETING DATE: JUNE 20, 2019 SUBJECT: AUTHORIZE AN INCREASE IN THE AMOUNT OF $80,000 TO THE EMTEC CONSULTING SERVICES LLC PROFESSIONAL CONSULTING SERVICES AGREEMENT (A COMPONENT OF THE ENTERPRISE RESOURCE PLANNING (ERP) REPLACEMENT, DISTRICT PROJECT 8250)APPROVED AT THE LAST BOARD MEETING, FORA NEW COST CEILING OF $2,365,000; AND (1) CONCURRENTLY INCREASE THE TOTAL COST FOR THE ERP PROJECT BY$80,000, BRINGING THE ERP PROJECT TOTAL TO $5,205,000; AND (2)ADOPT AMENDMENTS TO THE FISCAL YEAR 2019-20 DISTRICT BUDGET ADOPTED AT THE JUNE 6, 2019 BOARD MEETING TO INCORPORATE CHANGES ASSOCIATED WITH FUNDING FOR THE ERP PROJECT SUBMITTED BY: INITIATING DEPARTMENT: PHILIP LEIBER, DIRECTOR OF FINANCEAND ADMINISTRATION-FINANCE ADMINISTRATION REVIEWED BY: ANN SASAKI, DEPUTY GENERAL MANAGER Roger S. Bailey General Manager ISSUE At the last Board meeting on June 6, the Board authorized the Enterprise Resource Planning (ERP) Replacement, District Project 8250 (Project). At the same meeting, the Board adopted the Fiscal Year 2019-20 District Budget; however, the Budget did not include the appropriate transfers from the Capital Improvement Budget (CI B) project contingency fund to cover the Project costs. The Board asked staff to bring back for approval at this meeting amendments to the Budget to incorporate the needed CI B contingency fund transfers necessary to fund the Project. Additionally, due to project phasing changes, the cost estimate for the implementation component of the Project was understated by$80,000. An increase in that amount is necessary to reflect total Project costs. June 20, 2019 Regular Board Meeting Agenda Packet- Page 63 of 120 Page 2 of 14 BACKGROUND During the development of the FY 2019-20 Budget, which commenced in January and resulted in the presentation of a draft budget book to the Board on May 2, 2019, certain assumptions were made regarding the scope and cost of the Project.As negotiations with the vendors involved in this project continued through late May, certain updates were required to the cost projection. These cost updates were reflected in the recommended Project budget presented to and approved by the Board on June 6, 2019. However, they were not reflected in the draft budget. Additionally, the final proposed Emtec Consulting Services LLC contract amount should be $2,365,000, which is $80,000 higher than the $2,285,000 that was included in the Project budget of$5,125,000 and approved by the Board on June 6. This additional $80,000 was due to the use of a prior cost estimate not reflective of the latest phasing approach discovered when putting the final contract together. There is no change to the scope of work. Staff proposes to fund this by an additional $80,000 transfer from the FY 2019-20 Cl B contingency. While a funding increase of this magnitude could be permitted without Board approval under Board Policy No. BP 037 - Delegation ofAuthority to General Manager(which allows changes of up to ten-percent or $200,000 for professional services contracts greater than $1,000,000), for transparency and the fact that this contract has not yet been executed and was only approved by the Board at the last meeting, staff believes it would be appropriate to obtain approval of this change. The cost change affecting the FY 2019-20 Budget is limited to the transfer of$1,105,000 from the CI B contingency to the Project. This, along with the transfer of funds ($500,000)from DP 8240 (IT Development) in FY 2018-19, will bring the Project budget to $5,205,000. Redlined changes to the six pages affected in the FY 2019-20 Budget document included as Attachment 1. The amendment reallocates funds within the Cl B; no changes to other budgets, or the overall revenue requirement are proposed. The adoption of a motion to increase Emtec Consulting Services LLC contract funding by$80,000, and the adoption of a budget amendment to reflect the revised Project funding of$5,205,000 will align the final contract amount and Project budget as reflected in the amended CI B. ALTERNATIVES/CONSIDERATIONS With respect to whether the $80,000 of additional Emtec Consulting Services contract funding should be authorized, the alternative would be to keep the contract at the $2,285,000 level. This would not provide adequate funding for the phased approach at the level of implementer support that is recommended and reflected in the project plan. Accordingly, this option is not recommended. With respect to whether the projects in the Cl B can be aligned with the required funding level for the project prior to the start of the fiscal year(recommended), or alternatively, funds could be transferred subsequently from project close-outs at the end of FY 2018-19. 1 t is not presently known whether funds from project close-outs are adequate to meet the required $1,105,000 funding addition required, so this alternative is not recommended at present. Should project close-outs have adequate funding, the Cl B contingency could be restored to the $2 million level during FY 2019-20. FINANCIAL IMPACTS No overall change to Central San's revenue requirement for FY 2019-20 is proposed; only a reallocation of funds within the CI B. June 20, 2019 Regular Board Meeting Agenda Packet- Page 64 of 120 Page 3 of 14 COMMITTEE RECOMMENDATION No Committee review of this issue was undertaken due to the timing between the June 6, 2019 meeting at which the Project and the FY 2019-20 Budget were approved, and the need to approve a final budget for FY 2019-20 in June before the start of the new fiscal year on July 1. RECOMMENDED BOARD ACTION Staff recommends that the Board authorize: 1. An $80,000 increase to the Emtec Consulting Services LLC professional consulting services agreement approved at the June 6, 2019 Board meeting, for a new cost ceiling of$2,365,000; 2. A concurrent$80,000 increase in the total cost for the ERP Replacement, District Project 8250, approved at the June 6, 2019 Board meeting, bringing the Project total to $5,205,000; and 3. Amendments to the Fiscal Year 2019-20 District Budget adopted on June 6, 2019 to incorporate changes associated with funding for the ERP Replacement, District Project 8250. Strategic Plan Tie-In GOAL THREE: Be a Fiscally Sound and Effective Water Sector Utility Strategy 2- Manage costs GOAL SIX: Embrace Technology, Innovation and Environmental Sustainability Strategy 3- Encourage the review and testing of technology to optimize and modernize business operations ATTACHMENTS: 1. Revised FY 2019-20 Budget pages (in strikeout) 2. Presentation June 20, 2019 Regular Board Meeting Agenda Packet- Page 65 of 120 Page 4 of 14 Attachment 1 Table 13 below is a summary of the projected FY 2019-20 Sewer Construction Fund revenues and expenditures. Further details are included in the Capital Improvement Program section. Table 13-Sewer Construction Fund Revenues and Expenditures FY r2018-19 FY 2018-19 FY 2019-20 Budget-to-Budget % Budget Actual Budget Projected Budget— Variance Variance Revenue Capacity Fees $5,900,000 $7,937,754 $5,900,000 $5,750,000 $5,750,000 ($150,000) -39/ Pumped Zone Fees $513,000 $1,301,061 $600,000 $600,000 $291,000 ($309,000) -52% Interest Income $386,000 $777,226 $570,000 $570,000 $674,000 $104,000 18% Ad Valorem Taxes $12,100,000 $13,918,715 $13,300,000 $13,300,000 $14,520,000 $1,220,000 9% Sewer Service Charge $13,967,300 $14,060,789 $27,926,268 $28,311,000 $32,219,130 $4,292,862 15% Reimbursements City of Concord $6,000,000 $6,364,725 $7,150,000 $7,150,000 $11,630,000 $4,480,000 63% Recycled Water Sales $38,500 $0 $0 $0 $0 $0 0% Developer Fees and Charges $423,000 $519,072 $443,000 $443,000 $514,000 $71,000 16% Total Revenue $39,327,800 $44,879,342 $55,889,268 $56,124,000 $65,598,130 $9,708,862 17% Expenditures Treatment Plant Program $15,045,000 $15,681,067 $16,565,000 $18,300,000 $25,631,000 $11,766,000 70% Collection System Program $15,492,000 $20,291,192 $19,347,000 $19,500,000 $27,129,000 $7,782,000 40% General Improvements Program $4,277,000 $2,222,593 $4,750,000 $3,900,000 $4,264,000 (-$486,008) 14695369000 000 -1031% Recycled Water Program $460,000 $1,309,754 $2,857,000 $2,300,000 $4,152,000 $1,295,000 45% Contingency $1,500,000 $0 $1,500,000 $0 $2,000,000 $500,000 60500 33%40 $895,000 1 Total Expenditures $42,774,000 $39,504,606 $45,319,000 $44,000,000 $66,176,000 $20,857,000 46% Carryforward $3,700,000 $6,968,827 Total Expenditure Authority $46,474,000 $52,287,827 Sewer Construction Funds Available Projected Revenue $56,124,000 $65,598,130 Projected Expenditures*** $44,000,000 $66,176,000 Reserves Contribution/(Draw) $12,124,000 ($577,570) *Projection as of April 2019. **The FY 2019-20 budget amount does not include any carryforward from past fiscal years;the Board will be notified of any carryforward amount after the close of the current fiscal year. ***Reserve calculation assumes difference between FY 2018-19 budget and projected spending will be spent in FY 2019-20. Impact of Capital Improvement Budget on Ongoing Operations&Maintenance Budget Central San's Capital Improvement Budget and the extent to which FY 2019-20 nonrecurring capital investments will affect the proposed or future years'operating budget are described later in this document. In general,given the nature and composition of the FY 2019-20 Capital Improvement Budget,these effects are minimal. Future capital projects could have more substantial impacts(e.g., additional personnel costs,additional maintenance costs,or additional utility costs or,conversely, anticipated savings such as reduced utility costs or lower maintenance costs)that would be specified further in the year such projects are budgeted. 55 June 20, 2019 Regular Board Meeting Agenda Packet- Page 66 of 120 Page 5 of 14 FY 2019-20 Capital Improvement Budget The CIB Budget to date is approximately$67.8 million. The budget needed for all ongoing and new projects in FY 2019-20 is $66.2 million. The future year estimated budget for these projects is at $335.4 million. Combined the total estimated budget for the identified projects in the FY 2019-20 CIB is $469.4 million. The 2019 Ten-Year CIP is projected to be $867.2 million as shown below in Table 1: Table 1 — FY 2019-20 CIB per Program Budget to Date FY 2019-20 Future FYs Total Estimated FY 2019 Budgets Collection System $11,649,970 $27,129,000 $97,770,000 $136,548,970 $349,511,000 Treatment Plant $42,250,451 $28,631,000 $188,522,000 $259,403,451 $413,202,000 General Improvements $8,695,483 $4,264, 8 $10,400,000 $23,359,483$24, $24,893,000$25, $5,369,000 464,483 998,000 Recycled Water $5,239,894 $4,152,000 $28,717,000 $38,108,894 $55,119,000 $z?99A 9A8 895 �000,8AA 10 $24300,000 23 CIB Contingency $0 000 $10,000,000 895,000 395,000 Totals: $67,835,798 $66,176,000 $335,409,000 $469,420,798 $867,225,000 FY 2018-19 Capital Improvement Budget Construction Commitments As of April 30, 2019, the total construction commitments authorized by the Board in FY 2018-19 or previous is $55.8 million. This includes all construction contracts, purchase orders, construction management, and supporting services to complete the construction phase within the CIB. 141 June 20, 2019 Regular Board Meeting Agenda Packet- Page 67 of 120 Page 6 of 14 All projects in the General Improvements Program are summarized; including all past, current, and planned budgets required to complete each project as shown on the following Table 4: CIB TABLE 4— FY 2019-20 General Improvements Program Budget/Project Summa Project Project Budget-to- FY 2019-20 Future FYs Total Project Number Date Cost 8207 General Security and Access $134,977 $150,000 $100,000 $384,977 8230 Capital Legal Services $178,665 $20,000 $40,000 $238,665 8236 District Easement Acquisition $258,047 $75,000 $150,000 $483,047 8240 IT Development $2,7938,794 $500,000 $1,260,000 $4,4598,794 8243 Server Room Relocation $2,000,000 $0 $0 $2,000,000 8249 Collection System Operations Dump $60,000 $0 $0 $60,000 Pad Modifications Enterprise Resource Planning $6§00000 $2088;09 500000 83,1 $4,G99;9985,2 8250* Replacement , 05,000 $1, , 05,000 8251* Capital Improvement Program and $0 $350,000 $950,000 $1,300,000 Budget Improvements 8516 Equipment Acquisition $876,000 $100,000 $1,000,000 $1,976,000 8517 Vehicle Replacement Program $1,849,000 $1,069,000 $5,400,000 $8,318,000 $23 pro n4� Total Program $8,695,483 $41,2641,000 $10,400,000 $24 '483 *New project in FY 2019-20 200 June 20, 2019 Regular Board Meeting Agenda Packet- Page 68 of 120 Page 7 of 14 Table 3 Ten-Year Program:General ImprovementsFiscal Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Project# Project Name 10 Year Total 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 8207 General Security and Access 250,000 150,000 100,000 0 0 0 0 0 0 0 0 8230 Capital Legal Services 200,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000 8236 District Easement Acquisition 750,000 75,000 75,000 75,000 75,000 75,000 75,000 75,000 75,000 75,000 75,000 8240 IT Development FY 2016-26 2,900,000 500,000 500,000 380,000 380,000 380,000 380,000 380,000 0 0 0 8250 ERP Replacement 4,605,000 3,105,000 1,200,000 300,000 0 0 0 0 0 0 0 8251 ICapital Improvement Plan&Budget 1,300,000 350,000 150,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 100,000 8516 Equipment Acquisition 850,000 100,000 250,000 250,000 250,000 0 0 0 0 0 0 8517 Vehicle Replacement Program FY 2016-26 6,469,000 1,069,000 900,000 900,000 900,000 900,000 900,000 900,000 0 0 0 TBD Document Management 1,272,000 0 212,000 530,000 530,000 0 0 0 0 0 0 TBD Security Improvements Study(10-Year) 600,000 0 0 0 0 100,000 100,000 100,000 100,000 100,000 100,000 TBD Security Improvements Study(5-Year) 212,000 0 0 106,000 106,000 0 0 0 0 0 0 TDB Equipment Acquisition FY 2023-33 1,500,000 0 0 0 0 250,000 250,000 250,000 250,000 250,000 250,000 TDB Future Property Repairs and Improvements 1,250,000 0 0 200,000 150,000 150,000 150,000 150,000 150,000 150,000 150,000 TDB IT Development FY 2026-36 1,140,000 0 0 0 0 0 0 0 380,000 380,000 380,000 TDB Vehicle Replacement Program FY 2026-36 2,700,000 0 0 0 0 0 0 0 900,000 900,000 900,000 General Improvements Total: $ 25,998,000 $ 5,369,000 $ 3,407,000 $ 2,861,000 $ 2,511,000 $ 1,975,000 $ 1,975,000 $ 1,975,000 $ 1,975,000 $ 1,975,000 $ 1,975,000 Table 4-Ten-Year Program:Recycled WaterFiscal Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Project# Project Name 10 Year Total 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 7306 Zone 1 Recycled Water 1,256,000 100,000 53,000 53,000 150,000 150,000 150,000 150,000 150,000 150,000 150,000 7361 Filter Plant and Clearwell Improvements-Phase 1A 30,463,000 3,452,000 8,000,000 10,000,000 7,100,000 1,911,000 0 0 0 0 0 7366 Recycled Water Distribution Systems Renovations Program 21300,000 500,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 200,000 7368 Water Exchange&Filter Plant and Clearwell Improvements Phase A 100,000 100,000 0 0 0 0 0 0 0 0 0 TDB Filter Plant and Clearwell Improvements-Phase 113 21,000,000 0 0 0 0 1,600,000 2,400,000 6,000,000 5,500,000 5,500,000 0 Recycled Water Total: $ 55,119,000 $ 4,152,000 $ 8,253,000 $ 10,253,000 $ 7,450,000 $ 3,861,000 $ 2,750,000 $ 6,350,000 $ 5,850,000 $ 5,850,000 $ 350,000 Table 5 Ten-Year Program:Totals by ProgramFiscal Year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Programs 10 Year Total 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 Collection System 349,511,000 27,129,000 36,732,000 37,713,000 40,298,000 35,432,000 32,660,000 37,215,000 27,812,000 29,993,000 44,527,000 Treatment Plant 413,202,000 28,631,000 45,801,000 52,895,000 53,492,000 46,429,000 43,750,000 44,170,000 33,094,000 40,100,000 24,840,000 General Improvements 25,998,000 5,369,000 3,407,000 2,861,000 2,511,000 1,975,000 1,975,000 1,975,000 1,975,000 1,975,000 1,975,000 Recycled Water 55,119,000 4,152,000 8,253,000 10,253,000 7,450,000 3,861,000 2,750,000 6,350,000 5,850,000 5,850,000 350,000 Subtotal 843,830,000 65,281,000 94,193,000 103,722,000 103,751,000 87,697,000 81,135,000 89,710,000 68,731,000 77,918,000 71,692,000 Contingency 23,395,000 895,000 2,500,000 2,500,000 2,500,000 2,500,000 2,500,000 2,500,000 2,500,000 2,500,000 2,500,0001 Total with Contingency $ 867,225,000 $ 66,176,000 $ 96,693,000 $ 106,222,000 $ 106,251,000 $ 90,197,000 $ 83,635,000 $ 92,210,000 $ 71,231,000 $ 80,418,000 $ 74,192,000 (Note:All costs in 2019 dollars) 235 June 20, 2019 Regular Board Meeting Agenda Packet- Page 69 of 120 Page 8 of 14 Information Technolo Develo ment- District Project 8240 Program Phase Priority Rank Ranking Score General Improvements Construction Critical 70 Purpose: Project Drivers To replace and upgrade Information Technology (IT) infrastructure and software as needed. Aging Capacity Infrastructure Drivers: An IT Development Plan was developed to centralize efforts and Regulatory Sustainability funding in the development of computer and telecommunication technology within Central San. Central San budgets IT on an annual basis. The IT Master Plan was approved in 2015 and its implementation is within the Capital Improvement Program (CIP) and the Ten-Year Capital Improvement Plan. Description: This project is the implementation of the IT Master Plan which includes the following major elements: • Network infrastructure upgrades • Disaster recovery/business continuity • Cloud based technology improvements • Business application suite improvements • Increasing mobile presence • Desktop technology refreshment • Web redesign and enhancement • Cyber security Operating Department Impact and Funding Source: The impacts to the operating budgets have not yet been determined. Project expenditures are funded from Capital Revenues. Location(s): Central San-wide Project Budget Phase Budget-to-Date FY 2019-20 FY 2020-21 Future FYs Total Planning $0 $0 $0 $0 $0 Design $0 $0 $0 $0 $0 Construction $2,7938,794 $500,000 $500,000 $760,000 $4,4§98,794 FY Total $2,7838,794 $500,000 $500,000 $760,000 $4,43598,794 204 June 20, 2019 Regular Board Meeting Agenda Packet- Page 70 of 120 Page 9 of 14 Enterprise Resource Plannin Re lacement— District Project 8250 Program Phase Priority Rank Ranking Score General Improvements Construction Critical 65 Purpose: To replace our legacy Enterprise Resource Planning (ERP) system Project Drivers that manages Central San's finances, budget, human resources, procurement, payroll and other related resources. Aging Capacity Infrastructure Drivers: The existing SunGard ERP system uses outdated technology that Regulatory sustainability does not meet the current and future Central San business needs. The latest generation of ERP systems have been developed to implement modern best-practice processes that will help Central San to streamline and optimize many business processes. This project will eliminate the need for staff to use many manual processes and workarounds that are currently in use to accomplish work. It will enable more organizational transparency by providing visibility into our financial and business data in ways that are not currently possible and will provide the latest generation of technology to ensure full integration with future business applications. Description: The following are major elements included in the project: • Conversion of data from SunGard system to new ERP system • Implementation of Human Resources, Finance, Payroll, and related systems • Staff training • Integration with related Central San systems A replacement of Central San's permitting software functionality, currently provided by the SunGard system, is not included in these costs but may be funded from IT Development or other project sources. Operating Department Impact and Funding Source: This project is expected to have an annual ongoing impact of approximately $200,000 on the Operating Budget. Other operating efficiencies may offset, in part, some of these direct costs. Project expenditures are funded from Capital Revenues. Location(s): Martinez and Walnut Creek Campuses and Cloud Project Budget Phase Budget-to-Date FY 2019-20 FY 2020-21 Future FYs Total Planning $100,000 $0 $0 $0 $100,000 Design $200,000 $0 $0 $0 $200,000 $2 nnn nnn $3,700,000 Construction $3-200,000 3'100 $1,200,000 $300,000 49 00 FY Total $6-500,000 $ n�AA $1,200,000 $300,000 $3,105,000 $5,205,000 207 June 20, 2019 Regular Board Meeting Agenda Packet- Page 71 of 120 Attachment 2 ERP CONTRACT APPROVA UPDATE AND FY 2019 =20 BUDGET AMENDMENT Phil Leiber Director of Finance & Administration Board Meeting ' June 20, 2019 r3 =F �n - June 20, 2019 oard Mee . �. CENTRALSAN BACKGROUND 1 . Enterprise Resource Planning (ERP) related contracts under District Project (DP) 8250 approved 6/6/2019 2 . FY 2019-20 Budget approved 6/6/2019 3 . Discrepancy between #1 , and #2 : • Need to update Capital Improvement Budget to reflect approved ERP project funding level 4 . Also now need to update DP 8250 funding level by $80 ,000 CENTRALSAN2 BACKGROUND • Final contract payment schedule differed by $80,000 from the amount used in the budget analysis presented in recent months • Relates to Central San 's request to phase the project to reduce risk • Staff agrees the $80 ,000 is necessary and appropriate 3 ' RECOMMENDATIONS AND Recommendations: ERP BUDGET AS AMENDFr) • Authorize an $80,000 increase to the Emtec Consulting Services LLC professional consulting services agreement approved at the June 6, 2019 Board meeting, for a new cost ceiling of $2,365,000; • Authorize a concurrent $80,000 increase in the total cost for the ERP Replacement, District Project 8250, approved at the June 6, 2019 Board meeting, bringing the Project total to $5,205,000; and • Authorize amendments to the Fiscal Year 2019-20 District Budget adopted on June 6, 2019 to incorporate changes associated with funding for the ERP Replacement, District Project 8250. Proiect As Amended: ' • - 1 • 1 . 1 MIEMFY 1 • . DP 8250 ERP $600,000* $3,105,000** $1 ,200,000 $300,000 $5,205,000 * Source of funding is District Project 8240 (IT Development) which has been unbundled to separately show DP 8250. Includes the $500,000 presented in the draft budget book as of 5/2/2019. ** Includes use of$1 ,105,000 from CIB Contingency ($1,025,000 previously, and $80,000 now). Vii. i CENTRALSAN QUESTIONS ? J►Y d 5