,ejCENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: JUNE 20, 2019
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF$2,150,300 TO AUBURN
CONSTRUCTORS, LLC,THE LOWEST RESPONSIVE BIDDER FOR THE EMERGENCY SLUDGE
LOADOUT FACILITY UPGRADES, DISTRICT PROJECT 7348A; FIND THAT THE PROJECT IS EXEMPT
FROM THE CALIFORNIA ENVIRONMENTAL QUALITY ACT(CEQA);AMEND AN EXISTING
PROFESSIONAL ENGINEERING SERVICES AGREEMENT WITH BLACK&VEATCH CORPORATION
IN THE AMOUNT OF$220,000;AND AUTHORIZE UP TO A 15-PERCENT CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
MARK WENSLAWSKI,ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES-CAPITAL
PROJECTS
REVIEWED BY: NATHAN HODGES, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL SERVICES
Roger S. Bailey
General Manager
ISSUE
The Board must award the contract or reject bids within 50 days of the bid opening.Authorization is required for the General Manager
to execute the Contract Documents subject to submittal requirements and include up to a 15-percent contingency. Board
authorization is also required to execute an amendment to a professional engineering services agreement for an amount greater than
$200,000.
BACKGROUND
The Emergency Sludge Loadout Facility(ESLF)is located within the wastewater treatment plant in Martinez and is used for
emergency storage and truck loading of dewatered sludge in case the incinerators are unavailable.The ESLF Upgrades, District
Project(DP)7348A(ESLF Project)will install new isolation and modulating gates on the sludge silos, make improvements to other
mechanical and controls systems, and upgrade the odor control and ventilation systems.The work under this project will increase
operational reliability and flexibility for emergency solids handling.A map showing the location of the ESLF Project is included as
Attachment 1.
The ESLF Project is the first of three construction contracts as part of the Solids Handling Facility Improvements, DP 7348 (Solids
Project).These three separate contracts include the ESLF Project, the Sludge Blending Tank Repairs, DP 6172, and the Solids
Project.The Sludge Blending Tank Repairs and ESLF Project are being constructed ahead of the Solids Project to ensure that the
sludge bending tank and ESLF is fully functional and available for use during the construction of the Solids Project, which is
scheduled to begin around June of 2020.
The Engineer's estimate for construction of the ESLF Project was$2,300,000.This project was advertised on April 26 and May 1,
2019.Three sealed bids were received and publicly opened on May 30, 2019.The Engineering Department conducted a technical
and commercial review of the bids and determined that Auburn Constructors, LLC is the lowest responsive and responsible bidder
with a total bid amount of$2,150,300.A summary of bids received is shown in Attachment 2.
Black&Veatch Corporation (B&V)designed the ESLF Project as part of the larger Solids Project design effort. Staff recommends
amending the existing professional engineering services agreement with B&V to include design engineering support services during
the construction phase.The additional engineering services will include submittal review and design response services,field
verification, and asset management record documentation.A$220,000 cost ceiling has been negotiated with B&V to provide these
services, which includes a cost of$45,000 to update the record drawings and asset information for the entire facility.The asset and
drawing documentation will be incorporated in the Cityworks and GeoPortal systems(online database access for staff).
Central San staff will administer the construction contract and provide contract management and administration. Construction
inspection will be done by one of Central San's existing consultant inspection services agreements. In addition, staff will be
coordinating and managing the solids disposal under a separate contract with Lystek International Inc. (Lystek)as a pilot effort during
the commission of the ESLF Project. Lystek is a organic materials and recovery firm with experience working with wastewater municipalities
for solids waste process management in an environmentally safe manner and located at the Fairfield Suisun Sewer District.
CEQA
Staff has concluded that this project is exempt from CEQA under Central San's CEQA Guidelines Section 15301, since it involves
minor alterations to existing public facilities involving no expansion of use, and CEQA Guidelines Section 15302, since it involves
replacement of existing public facilities at the same location and with the same purpose.Approval of this project will establish the
Board's independent finding that this project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
The Solids Project is a two to three year construction effort and highly complex. Several critical equipment and processes will be
offline and coordinated for the construction of replacement systems including, but not limited to, the incinerator controls, air pollution
control equipment, dewatering equipment, and new electrical and controls infrastructure in the Solids Conditioning Building. Staff
recommends upgrading the ESLF before commencing the Solids Project to provide a loading system that can be used more on a
daily basis in case of issues that could arise during the Solids Project.
The Board may elect to reject all bids and provide another alternative.
FINANCIAL IMPACTS
The total estimated costs for constructing this project is$3,548,000,which includes planning, design, construction contract,
contingency, and construction management costs as shown in Attachment 3.
The ESLF Project is being funded by the Solids Project under a sub-account,which has adequate budget for the ESLF Project
construction phase. No transfer of funds will be required.The Solids Project is listed under the Fiscal Year(FY)2019-20 Budget on
page 182 with a FY 2019-20 project budget of$6,550,000.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the June 4, 2019 meeting and recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2.Award a construction contract in the amount of$2,150,300 for the construction of the Emergency Sludge Loadout
Facility Upgrades, District Project 7348A,to Auburn Constructors, LLC, the lowest responsive bidder;
3.Authorize the General Manager to amend the existing professional engineering services agreement with Black&Veatch
Corporation to include construction services in the amount of$220,000; and
4.Authorize the General Manager to execute the Contract Documents subject to submittal requirements and include up to a 15-
percent contingency.
Strategic Plan Tie-In
GOAL TWO:Strive to Meet Regulatory Requirements
Strategy 1-Strive to achieve 100%permit compliance in air, water,land, and other regulations
GOAL FOUR:Develop and retain a highly trained and innovative workforce
Strategy 3-Meet or exceed industry safety standards
GOAL FIVE:Maintain a Reliable Infrastructure
Strategy 3-Protect District personnel and assets from threats and emergencies
ATTACHMENTS:
Description
1. Project Location Map
2. Summary of Bids
3. Post Bid/Preconstruction Estimate
N
o
d 0 250
FEET
South
Clarifiers
o Emergency
Sludge Loadout
Facility
0 0
�0
POD
❑ 000 Solids
0 Conditioning
ED Building
��71
Sludgee
Control
Bldg
HOB
p d
Do Primary 0 Influent
Sedimentation Structure
a Tanks Headworks
a El O
d
----------------------------------------------------------
24
0
Q
0
PROJECT SITE r
a
L - - J
0
Attachment
Y CENTRAL SAN EMERGENCY SLUDGE LOADOUT FACILITY
' UPGRADES 1
DISTRICT PROJECT 7348A
ATTACHMENT 2
EMERGENCY SLUDGE LOADOUT FACILITY UPGRADES
DISTRICT PROJECT 7348A
SUMMARY OF BIDS
PROJECT NO.: 7348A NO. OF ADDENDA: 1 DATE/TIME: MAY 30, 2019/2:00 PM
PROJECT NAME: EMERGENCY SLUDGE LOADOUT FACILITY UPGRADES
PROJECT MANAGER: MARK WENSLAWSKI
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $2,300,000
NO. BIDDER BID PRICE
1 Auburn Constructors, LLC $2,150,300
Sacramento, California
2 D.W. Nicholson Corporation $2,252'600
Hayward, California
3 Sonnikson and Stordahl Construction, Inc. $2,680,000
Martinez, California
BIDS OPENED BY /s/ Katie Young DATE: May 30, 2019
ATTACHMENT 3
EMERGENCY SLUDGE LOADOUT FACILITY UPGRADES
DISTRICT PROJECT 7348A
POST-BID/PRECONSTRUCTION ESTIMATE
No. Item Description Amounts Construction
Cost
1 CONSTRUCTION
a. Construction Contract $2,150,300
b. Contingency at 15% $322,700
c. Permitting (BAAQMD) $20,000
d. Lystek Pilot (Solids Handling) $65,000
SUBTOTAL - CONSTRUCTION COST $2,558,000 100%
2 CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $130,000
- Operations Support $40,000
b. Outside Services
- B&V (Consultant) $220,000
- Inspection (Consultant) $100,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $490,000 19%
3 DESIGN (PREBID ESTIMATE)
a. District Staff and B&V Design $500,000
SUBTOTAL - DESIGN $500,000 20%
4 TOTAL ESTIMATED CONSTRUCTION COST $3,548,000