HomeMy WebLinkAbout03.b. Review draft Position Paper to approve a new project; award a construction contract in the amount of $610,500 to Aztec Consultants, Inc., the lowest responsive bidder for the Sludge Blending Tank Repairs, District Project 6172; find that the Projec Page 1 of 6
Item 3.b.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: JUNE 4, 2019
SUBJECT: REVIEW DRAFT POSITION PAPER TO APPROVE A NEW PROJECT;
AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $610,500 TO
AZTEC CONSULTANTS, INC., THE LOWEST RESPONSIVE BIDDER FOR
THE SLUDGE BLENDING TANK REPAIRS, DISTRICT PROJECT
6172; FIND THAT THE PROJECT IS EXEMPT FROM THE CALIFORNIA
ENVIRONMENTAL QUALITYACT (CEQA); AND AUTHORIZE UP TO A 15-
PERCENT CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
CLINT SHI MA, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: NATHAN HODGES, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
The Board must award the contract or reject bids within 50 days of the bid opening. Board authorization is
required for the General Manager to establish a new capital project and transfer funds in an amount greater
than $200,000. Authorization is also required for the General Manager to execute the Contract
Documents subject to submittal requirements and include up to a 15-percent contingency.
BACKGROUND
The sludge blending tank (SBT) and lime tanks are critical assets used in the solids process at the
wastewater treatment plant. Lime is added to the sludge (primary and secondary mix)for dewatering and
incineration purposes and stored in the SBT. The SBT has an inner diameter and wall height of 60 feet
and 35 feet respectively, and a maximum capacity of 767,000 gallons. Over time, the lime infused sludge
builds up on the inner walls of the piping, valves, and other system components. Narrowing of the pipe
gradually obstructs the flow, which adversely affects the solids handling process. The Sludge Blending
Tank Repairs, District Project (DP) 6172 (Project)will restore the capacities for the sludge blending and
lime injection systems, replace several 12-inch plug valves with new pinch valves, rehabilitate piping, and
allow for inspection and condition assessment of the existing underground SBT piping for the Solids
Handling Facility Improvements, DP 7348 (Solids Project). The proposed plan under the Solids
Project will be to use the existing SBT as a storage tank during routine furnace burn outs and as an
June 4, 2019 EOPS Regular Committee Meeting Agenda Packet- Page 5 of 19
Page 2 of 6
emergency storage tank, which is not expected to happen until Fiscal Year(FY) 2022-23 or slightly later. A
map showing the location of the Project site is shown in Attachment 1.
Cleaning the sludge blending system is a five-year preventative maintenance (PM)task that is completed
by outside contractors. The last occurrence was in FY 2012-13, which was coordinated under a previous
capital project. Any PM work under the Project will be accounted for and charged to the Operating
budget. The capitalized portion such as the valve replacements, piping rehabilitation or similar work, and
inspection will be charged to the Solids Project. Combining the efforts between the Operations
Department and Capital Projects is more cost effective by reducing the time for equipment shutdown and
total work required to access these facilities.
Central San staff prepared the plans and specifications for the Project. The Engineer's estimate is
$525,000. This Project was advertised on May 7 and 14, 2019. One sealed bid for$610,500 was
received and publicly opened on May 28, 2019. The Capital Projects Division conducted a technical and
commercial review of the bids and determined that Aztec Consultants, Inc. (Aztec) is the lowest
responsive and responsible bidder. Upon review of the bid provided by Aztec, staff noted the increase
over the Engineer's estimate was due in part to the cleaning cost of the lime tanks and the associated
waste disposal. I n addition,Aztec is familiar with Central San's treatment plant and has successfully
completed other construction projects, including the SBT work completed in FY 2012-13. A summary of
the bid opening is shown in Attachment 2.
Central San will administer and manage the construction contract, provide contract administration,
inspection, office engineering, and submittal review.
CEQA
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15301, since it involves minor alterations to existing public facilities involving no expansion of use, and
CEQA Guidelines Section 15302, since it involves replacement of existing public facilities at the same
location and with the same purpose. Approval of this Project will establish the Board's independent finding
that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
The Board could provide alternate direction or reject all bids, which is not recommended.
FINANCIAL IMPACTS
The total estimated cost for this Project is approximately$776,000, which includes design, bid,
contingency, inspection, and construction management as shown in Attachment 3. Staff anticipates that
the costs associated with the Operations budget to be $300,000. The capital cost related to the Project is
estimated at$476,000 and will be charged under the Solids Project under a new project number, DP
6172. Upon approval of the Project and construction contract, the General Manager will transfer the
required capital funds from the Solids Project. There is adequate funding for this work in the Operating
and Solids Project budgets. The transfer will be categorized as "A. Bundling/Unbundling" in the ongoing
analysis of C I B transfers presented quarterly.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the June 4, 2019 meeting
and recommended
June 4, 2019 EOPS Regular Committee Meeting Agenda Packet- Page 6 of 19
Page 3 of 6
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Approve a new project in the amount of$776,000 entitled Sludge Blending Tank Repairs, District
Project 6172;
2. Find that the Project is exempt from CEQA;
3. Award a construction contract in the amount of $610,500 for the construction of the Sludge
Blending Tank Repairs, District Project 6172, to Aztec Consultants, I nc. the lowest responsive
bidder; and
4. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements and include up to a 15-percent contingency.
Strategic Plan re-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL THREE: Be a Fiscally Sound and Effective Water Sector Utility
Strategy 2- Manage costs
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post Bid/P reconstruction Estimate
June 4, 2019 EOPS Regular Committee Meeting Agenda Packet- Page 7 of 19
Page 4 of 6
Di
0 200 400
FEET
Basin A South
°
CONSTRUCTION
STAGING AREA —
® SOLIDS
NDITIONI
BUILDIN
PROJECT AREA It
0 SLUDGE BLENDING TANKS
a i
0
Aeration CLA IERS
Tanks (SOUT UAD)
I
o PRIMARY I
S DIMENTATI N i
TANKS i
zc
I
❑
El0 �i I
❑ PUMP AND BLOWER
BUILDING
POD HOB
P�-PG IMHOFF PLACE
f
Central Contra Costa Attachment
Y sanitary District SLUDGE BLENDING TANK REPAIRS
DISTRICT PROJECT 6172 1
LOCATION MAP
N ar Committee Meeting Agenda Packet- Page 8 of 19
Page 5 of 6
ATTACHMENT 2
SLUDGE BLENDING TANK REPAIRS
DISTRICT PROJECT 6172
SUMMARY OF BIDS
PROJECT NO.: 6172 NO. OF ADDENDA: 1 DATE/TIME: MAY 28, 2019/2:00 PM
PROJECT NAME: SLUDGE BLENDING TANK REPAIRS
PROJECT MANAGER: MARK CAVALLERO
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $525,000
NO. BIDDER BID PRICE
1 Aztec Consultants, Inc. $610,500
San Ramon, California
BIDS OPENED BY /s/Katie Young DATE: May 28, 2019
June 4, 2019 EOPS Regular Committee Meeting Agenda Packet- Page 9 of 19
Page 6 of 6
ATTACHMENT 3
SLUDGE BLENDING TANK REPAIRS
DISTRICT PROJECT 6172
POST-BID / PRECONSTRUCTION ESTIMATE
% of
No. Item Description Amounts Construction
Cost
1. CONSTRUCTION
a. Construction Contract $610,500
b. Contingency at 15% $90,500
SUBTOTAL — CONSTRUCTION COST $701,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management, Engineering, $30,000
Inspection, As-Builts
- Plant Operation Division (POD) Coordination $5,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $35,000 5%
3. PREBID EXPENDITURES
a. Engineering (Planning, Design, Drafting, POD
Coordination) $40,000
SUBTOTAL - PREBID EXPENDITURES $40,000 6%
4. TOTAL ESTIMATED PROJECT COST $776,000
June 4, 2019 EOPS Regular Committee Meeting Agenda Packet- Page 10 of 19