HomeMy WebLinkAbout04. Authorize pre-selection of supliers for Solids Handling Facility Improvements, DP 7348, and authorize contracts for specialty services Page 1 of 6
Item 4.
CENTRAL SAN CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: DECEMBER 20, 2018
SUBJECT: AUTHORIZE THE PRE-SELECTION OF THE FOLLOWING SUPPLIERS
FOR THE SOLIDS HANDLING FACILITY IMPROVEMENTS, DISTRICT
PROJECT7348: (1)ANDRITZ SEPARATION TECHNOLOGIES, INC. FOR
THE DEWATERING CENTRIFUGE SYSTEM EQUIPMENT IN THE BASE
AMOUNT OF $1,968,858; AND (2) SCHWING BIOSET FOR THE CAKE
PUMPS EQUIPMENT IN THE BASE AMOUNT OF $1,973,350; AND
AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACTS
TOTALING $210,771 WITH ANDRITZ SEPARATION TECHNOLOGIES, INC.
($60,771)AND SCHWING BIOSET ($150,000) FOR SPECIALTY SERVICES
RELATED TO FUTURE EQUIPMENT INSTALLATION FOR THE PROJECT
SUBMITTED BY: INITIATING DEPARTMENT:
NATHAN HODGES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
tar_,
Roger S. Bailey Kenton L. Alm
General Manager District Counsel
ISSUE
Board of Directors (Board) authorization is required for the General Manager to enter into a project
contract in an amount that exceeds $175,000.
December 20, 2018 Regular Board Meeting Agenda Packet- Page 28 of 168
Page 2 of 6
BACKGROUND
I n 2016, staff initiated the Solids Handling Facility Improvements, District Project 7348 (Project)to
address the immediate and near-term project needs and retained Black& Veatch (B&V), as authorized by
the Board on December 1, 2016, to provide evaluations of issues and pre-design work.Addressing
dewatering system deficiencies was identified as an immediate need. The dewatering centrifuges and
cake pumps were installed in 1988 and have been in operation for 30 years. These systems are beyond
their useful life and require frequent offsite major rebuilds with some components being no longer
available. As demonstrated by two centrifuge pilot testing, modern centrifuge technology can and will
provide improved performance, which in turn will optimize furnace operation, and reduce fuel (natural gas)
usage, greenhouse gases, and the risk of air permit violations. The objectives of the dewatering
improvements are to provide consistent cake solids with optimum characteristics for multiple hearth
furnace (MHF) operation and ensure reliable operation, while reducing equipment power and polymer
consumption.As part of the evaluation process, alternatives for the centrifuges and cake pumps were
developed.
The evaluation of alternatives included economic and non-economic criteria. Economic criteria included
capital, performance, and operating and maintenance costs, while non-economic criteria included reliability,
operability, maintainability, and environmental impacts. The alternative of four centrifuges/cake pumps was
recommended as the one best able to ensure adequate reliability of plant operations, to maximize use of
the existing building infrastructure, and to improve dewatering system performance, with resultant benefits
for MHF operation. Continued use of the existing centrifuges/cake pumps was determined to provide
inadequate plant reliability as the equipment is becoming increasingly obsolete and Central San will not
realize the benefits of modern technology for improved performance. New equipment will significantly
improve the following:
• The existing centrifuges require frequent offsite major rebuilds. This compromises the reliability of
the overall solids processing.
• The existing centrifuges and cake pumps are becoming increasingly obsolete with some
components no longer commercially available.
• New centrifuges have improved performance which will reduce power consumption, fuel use in the
multiple hearth furnaces, reduce polymer use, minimize upset furnace conditions, and risk of permit
violations.
Centrifuges and cake pumps available for the municipal market have different configuration, space, weight,
power and utility requirements, making it difficult to show specific installation requirements in the
construction bid documents for multiple potential suppliers. Selection of this equipment during detailed
design was recommended to facilitate the design process and provide specific installation requirements in
the construction bid documents, reducing the risk of change orders, as presented to the Board on July 5,
2018.
A questionnaire was sent to prospective centrifuge and cake pump manufacturers to obtain information on
performance capabilities of proposed equipment and qualifications of potential suppliers. Responses to
the questionnaire were then used to establish minimum equipment performance requirements for capacity,
cake solids concentration, to capture efficiency, power and polymer use, and to evaluate whether the
differences in size, weight, and utility requirements would be difficult to accommodate. The responses
were also used to establish minimum manufacturer qualifications related to experience providing
equipment for similar facilities and aftermarket service support. Performance requirements were set to
ensure optimum performance requirements and adequate manufacturer qualifications that would also
provide competitive bidding. Multiple manufacturers were identified for the centrifuges and cake pumps
that were able to meet acceptable equipment performance and supplier qualifications.
Selection documents, including bidding procedures, contract requirements, and technical specifications,
December 20, 2018 Regular Board Meeting Agenda Packet- Page 29 of 168
Page 3 of 6
were developed separately for both the centrifuges and cake pumps. The bid submittal packages included
two parts. Part 1 consisted of a Bidders Proposal that included supplier qualifications and supplementary
information to establish compliance with technical requirements. Part 2 consisted of the bid (purchase
price). Bidders Proposals were opened first, and only bids by respondents determined to meet the
minimum proposal qualifications were then opened after a period to allow for an appeal process. The
manufacturer's scope for the bid has two stages:
• Stage I - Supply equipment shop drawings and design coordination during development of the
Project bid documents, which will be performed under direct contract with Central San.
• Stage I I -After Board award of the Project construction contract, furnish equipment for installation
and provide associated services, such as commissioning, performance testing, and warranty. This
scope of Stage I I will be assigned to the general contractor to provide single source responsibility
for the installation, including equipment payments.
Pre-Selection and Bidding Process:
The cake pumps and centrifuges contract documents were publicly advertised. Each contract document
included two bid schedules: 1) a base bid schedule, which determines the basis of selection; and 2) an
additive bid schedule.
For the cake pumps, the contract documents were publicly advertised on September 24, 2018. On
October 26, 2018, one (1) sealed bid submittal package was received from Schwing Bioset, and the
proposal (Part 1)was opened. Engineering staff, with the assistance of B&V, conducted a review of Part 1
and determined that the bidder was responsive and met the minimum qualifications and experience. On
November 9, 2018, the bid (Part 2) of the package was publicly opened. The total lump sum of the base
bid schedule (Stages I and 11)was $1,973,350. Staff conducted a technical and commercial review of the
bid and determined that Schwing Bioset's bid was responsive and responsible.
The additive bid schedule for the cake pumps from Schwing Bioset included additional warranty, spare
parts, and service maintenance agreements. Staff recommends including the alternative bid item for a
spare pump assembly($97,300).
For the centrifuges, the contract documents were publicly advertised on September 24, 2018. On October
26, 2018, three (3) sealed bid submittal packages were received, and Part 1 of the packages were
opened. Engineering staff, with the assistance of B&V, conducted a review of the proposals and
determined that all the bidders were responsive and met the minimum qualifications and experience. On
November 28, 2018, Part 2 of the packages were publicly opened. The three (3) sealed base bids ranged
from $1,968,858.00 to $2,637,531.25. Staff conducted a technical and commercial review of the lowest
bid and determined that Andritz Separation Technologies, Inc. (Andritz) is the lowest responsive and
responsible bidder with a base bid schedule amount of$1,968,858.A summary of bids received is shown
in Attachment 1.
The additive bid schedule from Andritz included additional warranty, spare parts, and service maintenance
agreements. Staff recommends including the alternative bid items for an additional 3-year warranty period
($59,100) and a spare rotating element ($149,600).
ALTERNATIVES/CONSIDERATIONS
Several equipment alternatives were evaluated by B&V, as stated before, including continued use of the
existing system or partial replacement. It was determined by B&V and staff (Capital Projects and
Operations)that the best approach would be to replace the dewatering system as recommended. Other
alternatives that the Board could consider include the following:
December 20, 2018 Regular Board Meeting Agenda Packet- Page 30 of 168
Page 4 of 6
Alternative 1 - Reject the bids and continue the project design without equipment contracts. This is not
recommended due to the technical complexity and differences in the available dewatering equipment on
the market. Including the equipment contracts will help reduce the potential for change orders and
problems associated with substitutions, and simplify and cut the time required for equipment procurement
under the construction phase.
Alternative 2 - The contract includes provisions to allow Central San to purchase the equipment directly
from the manufacturers. This is not recommended at this time since the current plan is to continue final
design of the project and reassign the purchase of the equipment to the installing contractor. However, if
complications occur during the bid of the Project, staff will have the ability to purchase this equipment at
the specified costs and install under a separate contract.
FINANCIAL IMPACTS
The current contract commitment totals $210,771, which includes the specialty services for shop drawings,
design coordination, and engineering related to the installation of the equipment. The two contracts for the
selected centrifuges and cake pumps will be added to the Project contract documents for the Solids
Handling Facility Improvements and include the costs for the equipment, taxes, delivery, spare parts,
commissioning, testing, documents, and warranties that total an amount of approximately$4,040,000.
These costs will be reassigned to a general contractor upon successful award of the Project construction
contract at a later date.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at the meeting on December 10, 2018,
and recommended approval of the equipment contracts.
RECOMMENDED BOARD ACTION
Staff recommends the following for the Solids Handling Facility Improvements, District Project 7348:
1. Authorize the pre-selection of the following suppliers: (1)Andritz Separation Technologies, I nc. for
the dewatering centrifuge system equipment in the base amount of $1,968,858; and (2) Schwing
Bioset for the cake pumps equipment in the base amount of $1,973,350; and
2. Authorize the General Manager to execute contracts totaling $210,771 with And ritz Separation
Technologies, I nc. ($60,771) and Schwing Bioset ($150,000)for specialty services related to future
equipment installation.
Strategic Plan re-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL FOUR: Develop and retain a highly trained and innovative workforce
Strategy 3- Meet or exceed industry safety standards
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 1 - Manage assets optimally throughout their lifecycle, Strategy 2- Facilitate long-term capital renewal and
replacement
December 20, 2018 Regular Board Meeting Agenda Packet- Page 31 of 168
Page 5 of 6
ATTACHMENTS:
1. Summary of Bids
December 20, 2018 Regular Board Meeting Agenda Packet- Page 32 of 168
Page 6 of 6
ATTACHMENT 1
SOLIDS HANDLING FACILITY IMPROVEMENTS PROJECT DEWATERING
CENTRIFUGE SYSTEM EQUIPMENT SELECTION CONTRACT
DISTRICT PROJECT 7348
SUMMARY OF BIDS
PROJECT NO.: 7348 NO. OF ADDENDA: 2 DATE/TIME: NOVEMBER 28, 2018/3:00 PM
PROJECT NAME: SOLIDS HANDLING FACILITY IMPROVEMENTS PROJECT DEWATERING
CENTRIFUGE SYSTEM EQUIPMENT SELECTION CONTRACT
PROJECT MANAGER: NATHAN HODGES
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
NO. BIDDER BID PRICE
1 Andritz Separation $1,968,858.00
Technologies, Inc.
2 Alfa Laval, Inc. $2,026,480.00
3 GEA Mechanical Equipment $2,637,531.25
US, Inc.
BIDS OPENED BY /s/ Katie Young DATE: November 28, 2018
December 20, 2018 Regular Board Meeting Agenda Packet- Page 33 of 168