Loading...
HomeMy WebLinkAbout03.b. (Handout) Revised Presentation Item3.b. (Handout) M ECHANICALAND C ONCRETE R ENOVATIONS, D ISTRICT P ROJECT 7351 Engineering and Operations Committee November 5, 2018 Nancy Molina Capital Projects Associate Engineer Edgar J. Lopez Capital Projects Division Manager P ROJECT O VERVIEW Θ The Project focuses on the rehabilitation and replacement of concrete structures and mechanical equipment associated with preliminary and primary treatment process areas. Θ General Summary of Scope of Work: Θ Structure rehabilitation by concrete and epoxy coatings; Θ Replacement of flight rails and supports on the PSTs; Θ Gate and piping replacement; Θ Odor control tower rehabilitation; Θ Grout injection to eliminate leaks; Θ Safety improvements related to the structures and equipment replacement; and Θ Concord Main Metering Station upgrades. Ћ Њ L OCATIONOF P ROJECT E LEMENTS E VALUATED ATTHE T REATMENT P LANT Ќ L OCATIONOF C ONCORD M ETER S TATION Ѝ Ћ E NGINEER’S E STIMATE B ASEAND A DDITIVE B ID I TEMS Θ Base Bid$ 9,520,000 Θ Additive Bid Items Θ 1 -Concord Meter Station $ 850,000 Θ 2 -Other Structures$ 1,100,000 Total: $11,470,000 Ў B ID R ESULTS Џ Ќ C. O VERAA& C OMPANY B ID B ASEAND A DDITIVE B ID I TEMS Θ Base Bid$ 8,741,000 Θ Additive Bid Items: Θ 1 -Concord Meter Station $ 404,000 Θ 2 -Other Structures$ 919,000 Total Contract Amount: $10,064,000 А T OTAL E STIMATED P ROJECT B UDGET Ϋ Ϋ ЎЉі Ʒƚ ĬĻ ƩĻźƒĬǒƩƭĻķ ĬǤ ƷŷĻ /źƷǤ ƚŅ /ƚƓĭƚƩķ Б Ѝ F INANCIAL I MPACT *Includes past budgets В P ROJECT E LEMENTSFOR THE O DOR C ONTROL P ROJECT Θ Needed spring of 2019 prior to summer months ЊЉ Ў O UTFALL P H. 7 I MPROVEMENTS U PDATE Θ Project is needed for regulatory compliance. Θ Proceeding with both permits and design. Θ Construction of some of the structures under this Project. Θ Can not be constructed in FY 2019-2020 due to: Θ Influent structure gate replacements and repairs. Θ Primary Sedimentation Tank repairs and effluent channel work. Construction scheduled for FY 2020-21. Budget will be revised and no impacts to overall CIP budget anticipated. ЊЊ P ROJECT E LEMENTS I MPACTING O UTFALL P H. 7 I MPROVEMENTS P ROJECT Θ Needed prior to Outfall for Operations coordination ЊЋ Џ E LEMENTS I NCLUDEDFORTHIS T WO Y EAR C ONSTRUCTION P ROJECT Θ Not including Grit System –Future Project Θ Structure D has to be completed during Outfall Ph. 7 Project ЊЌ B OARD A CTIONSAND S TAFF R ECOMMENDATIONS Staff recommends the following: 1.Find that the Project is exempt from CEQA; 2.Award a construction contract in the amount of $10,064,000 for the construction of the Mechanical and Concrete Renovation, DP 7351, to C. Overaa & Company, the lowest responsive bidder; 3.Authorize the General Manager to execute Contract Documents subject to submittal requirements and include up to a ten-percent contract contingency; 4.Authorize the General Manager to amend an existing professional services agreement to increase the cost ceiling by $725,000 with Carollo for construction support services; and 5.Authorize the General Manager to consolidate and transfer the project budgets to fund the construction of the project. ЊЍ А Q UESTIONS? ЊЎ Б