Strategic Plan Tie-In
GOAL ONE: Provide Exceptional Customer Service
Strategy 1 - Build external customer relationships and awareness
ATTACHMENTS:
1. General Manager Announcements
2. HR Report- Third Quarter 2018
November 1, 2018 Regular Board Meeting Agenda Packet- Page 455 of 499
Page 2 of 4
ATTACHMENT 1
Board Meeting of November 1 , 2018
General Manager Written Announcements
ENVIRONMENTAL COMPLIANCE
1) Industrial User Academy Hosted by Central San Staff
Environmental Compliance staff hosted an Industrial User (IU) Academy on October 25,
2018. Businesses issued a discharge permit were invited to attend the IU Academy to
learn how to comply with the conditions of the permit and Central San's Source Control
Ordinance. A full range of topics was covered including what to expect during inspections,
how to conduct sampling, reading lab reports, completing reports and more. The design
of this IU Academy was modified to provide pre-Academy modules for certain topics to
allow for just one day of sessions on site. The IU Academy included a plant tour which
has always been a popular feature. Twelve representatives from ten businesses attended
the event.
DEVELOPMENT SERVICES
2) Notices Sent to Reimbursement Account Holders
Central San provides a reimbursement program so that costs of mainline sewer
extensions can be shared among property owners. Each year, in accordance with District
Code, annual notices are mailed to the holders of reimbursement accounts (installers).
This year, a total of 81 annual notices were mailed on October 19, 2018.
Installers were reminded of the need to keep Central San informed of any change of
address. Installers were asked to update their information and return the notice to Central
San in the prepaid envelopes provided. Having current address information will enable
staff to notify Installers when reimbursement fees are collected on their behalf. Installers
were also informed of the expiration dates of their accounts. Staff will continue to make
reasonable efforts to locate installers.
CONTRACTS & AGREEMENTS — QUARTERLY UPDATE
3) General Manager Authorized Contracts, Agreements, Etc. - Third Quarter
2018
The Board has delegated various authorities to the General Manager via Board Policy No.
BP 037 — Delegation of Authority to General Manager, including the authority to enter into
certain agreements and contracts on behalf of the District. Additionally, the Board has
requested an announcement when construction projects have been accepted, which
occurs when the Notice of Completion is recorded with the County Recorder's Office.
Also, the Board has requested notification of certain legal claim settlements. Below is a
recap of each of these items for the period July 1 through September 30, 2018:
November 1, 2018 Regular Board Meeting Agenda Packet- Page 456 of 499
Page 3 of 4
Written Announcements
November 1, 2018
Page 2 of 2
Professional consul ting agreements*between $50,000 and$100,000
Agreement Amendment Company
Date No. (Y/N) Name Description Total
08/02/2018 041794 Y MCC Control Added $25,000/ $80,400
DBA Primex SCADA system
support
08/14/2018 046518 N Brown and Refinery exchange $95,000
Caldwell project
08/23/18 046459 N West Yost Recycled water system $92,900
Associates surge analysis
*All other contracts that are not`professional services"or"District Projects"such as maintenance services, equipment,
chemicals, and supplies, do not require Board approval regardless of dollar amount. The Board approves the annual
budget which includes the expenses that come from these contracts, so these contracts are not included in this report
as they have historically been within staff authority.
Construction contracts awarded under$175,000
Date Project Project Contractor Total
No.
None.
Construction projects accepted
Date I Project Project No. Contractor
8/2/18 Pump and Blower Building Seismic 7291 Manito Construction, Inc.
Upgrades
Legal claim settlements between $25,000 and$50,000
Date Type of Claim Claimant Description Total
None.
HUMAN RESOURCES— QUARTERLY UPDATE
4) Update on Personnel Actions — Third Quarter 2018
See Attachment 2 for the Human Resources report covering personnel actions for July
through September 2018.
November 1, 2018 Regular Board Meeting Agenda Packet- Page 457 of 499
ATTACHMENT 2
HUMAN RESOURCES QUARTERLY UPDATE
PERIOD:JULY-SEPTEMBER 2018
New Hires
Name Position Hire Date
Dmitry Abramov IT Analyst 1 07/02/18
Joel Rogge Construction Equip Operator 07/09/18
Benjamin Lavender Community Affairs Rep 09/17/18
Heather Ramamurthy Management Analyst 09/21/18
Promotions
Name Prior Position Current Position Date of Promotion
David Bagar Plant Operator Trainee Plant Operator 1 09/11/18
Sean Sullivan Electrical Technician Electrical Shop Supervisor 09/18/18
Personnel Advancements
Name Prior Position Current Position Date of Advancement
Katherine Grumbine Accounting Technician II Accounting Technician III 07/03/18
Imran Chaudhary IT Analyst I IT Analyst II 08/07/18
Loren Reimer Maintenance Crew Member I Maintenance Crew Member II 08/08/18
Jesse Rocha Maintenance Crew Member I Maintenance Crew Member II 08/08/18
Michael Cunningham Staff Engineer Assistant Engineer 08/21/18
Retirements
Name Position Length of Service Retirement Date
Tom Godsey Senior Engineer 30 years, 9 months 07/06/18
Thea Vassallo Finance Manager 21 years, 6 months 08/17/18
Jay Nightingale Construction Inspector 13 years, 10 months 08/30/18
Resignations
Name Position Length of Service Termination Date
Irina Kadantseva Management Analyst 10 months 08/17/18
Rohit Upadhya Assistant Engineer 3 years, 1 month 08/17/18
November 1, 2018 Regular Board Meeting Agenda Packet- Page 458 of 499