HomeMy WebLinkAboutEngineering & Operations MINUTES 10-08-18 Page 2 of 8
E TRAL SAN
CENTRAL
CONTRA COSTA SANITARY
i ■ IMHOFF PLACE, MARTINEZ, i ■s 4 ■
REGULAR MEETING OF THE BOARD OF DIRECTORS:
JAMES A.NEJEDLY
CENTRAL CONTRA COSTA President
SANITARY DISTRICT DAVID R, WILLIAMS
President Pro Tern
ENGINEERING & OPERATIONS
PAUL H.CA USEY
COMMITTEE MICHAEL R.MCGILL
TAD J.PILECKI
MINUTES PHONE.: (925)228-9500
FAX (925)372-0192
www.centralsan.org
Monday, October 8, 2018
9:00 a.m.
2nd Floor Conference Room
5019 Imhoff Place
Martinez, California
Committee:
Chair Paul Causey
Member Mike McGill
Staff.
Roger S. Bailey, General Manager
Katie Young, Secretary of the District
Ann Sasaki, Deputy General Manager
Phil Leiber, Director of Finance and Administration
Jean-Marc Petit, Director of Engineering and Technical Services
Edgar Lopez, Capital Projects Division Manager
Dana Lawson, Senior Engineer (left after Item 4.a.)
Amelia Berumen, Senior Administrative Technician
1. Call Meeting to Order
Chair Causey called the meeting to order at 9:05 a.m.
2. Public Comments
None.
3. Items for Committee Recommendation to Board
a. Review draft Position Paper to authorize the General Manager to execute
professional engineering services agreements with TJC and Associates,
Inc. and ArcSine Engineering in an amount not to exceed $375,000 each
to provide as-needed electrical, instrumentation, and controls engineering
services
October 18, 2018 Regular Board Meeting Agenda Packet- Page 36 of 46
Page 3of8
Engineering & Operations Committee Minutes
October 8, 2018
Page 2
Mr. Lopez provided an overview of the draft Position Paper stating that the
use of as-needed contracts for various services has been occurring for
over ten years. With the number of upcoming projects in the adopted
Capital Improvement Budget (CIB), staff recommends using two
consultants to provide the needed services. TJC and Associates, Inc. and
ArcSine Engineering were chosen for their experience and proposed fees.
In addition to engineering services, ArcSine is also a construction
contractor adding a unique perspective for design needs. Staff
recommends a $375,000, three-year contract term to each consultant to
augment staff with in-house design and Operations and Maintenance
needs.
Chair Causey inquired how the work would be authorized amongst the two
consultants. Mr. Lopez responded that work is authorized on a task basis
after negotiating a project scope and fee, including availability;
additionally, contracts are tracked and balanced equally.
Member McGill noted that there were no alternatives listed for
consideration and justification in the draft Position Paper. Mr. Bailey said
staff will include them in the final Position Paper.
Chair Causey noted that there are several as-needed contracts and
requested staff provide a report that includes contract status and term
dates to show overlap and when contracts would be due. Mr. Lopez
answered that the term of contracts will be included in the next quarterly
report in the recently added as-needed contracts spreadsheet.
COMMITTEE ACTION: Recommended Board approval and requested
that staff augment the draft Position Paper before it is presented to
the full Board with respect to the Alternatives/Considerations section
regarding justification for the agreements.
4. Other Items
a. Asset Management Program Update
Mr. Petit announced that this would be the final Committee update from
Ms. Lawson as she accepted a lateral transfer to the Development
Services Division within the Engineering Department. He said her
replacement should be selected in the coming weeks.
Ms. Lawson provided a brief update on the program drawing attention to
the report provided in the agenda materials and answered questions from
the Committee, namely pertaining to development type projects that are
captured as capital and/or operations based.
October 18, 2018 Regular Board Meeting Agenda Packet- Page 37 of 46
Page 4 of 8
Engineering & Operations Committee Minutes
October 8, 2018
Page 3
The Program and Project Management Standards, Item No. 10 of the
report, was highlighted for this update and is currently in Phase 2. Beta
teams, comprised of District staff, are being used during the
implementation and have been useful in providing feedback for
adjustments needed to make the program more user and task friendly.
Upon completion of the software implementation, anticipated by July 2019,
all capital project information will be in one place, making project
information more accessible for the engineering management team
without searching through various individual reports.
Ms. Lawson responded to various questions pertaining to uses of the E-
Builder(program management information software) and how it will
coordinate with the new Enterprise Resource Planning (ERP) program. As
the new ERP is in place, the operations and capital project components
will be reviewed, and staff will find the right balance to ensure the
information is accessible. Mr. Bailey added that the goal of each
program's function is what will be looked at, but the important takeaway is
that the information will be available. Chair Causey indicated that he does
not want to see so many different programs added in the future, preferring
instead to limit it to one or two.
Mr. Petit explained that E-Builder will have all the capital project
components, which includes all projects adopted in the CIB and the Ten-
Year Capital Improvement Plan, design and construction modules, and all
capital financial commitments.
Chair Causey inquired about Item No. 6d of the report, regarding the
consolidation of CCTV(closed circuit television) inspection databases,
and if the proper format was not being received. Ms. Lawson responded
that the current CCTV contract has a three-year term that expires June
2019. That contract specified the CCTV format of the software the District
used at that time (WinCan). As part of the CCTV software replacement,
the new software vendor(IT Pipes) was contracted to migrate the legacy
data into the new software format and budget was included to convert the
remainder of data until the new CCTV contract is issued requiring the
software next year. The next solicited contract will require that the
selected contractor have and use the IT Pipes platform for their sewer
inspection deliverables.
Lastly, regarding Item No. 13 on the report, Capital Improvement Program
Business Case Evaluations, Chair Causey stated he would like to review
the business case and requested staff bring it to the Committee for review.
COMMITTEE ACTION: Received the update.
October 18, 2018 Regular Board Meeting Agenda Packet- Page 38 of 46
Page 5of8
Engineering & Operations Committee Minutes
October 8, 2018
Page 4
b. Receive a project update of the Mechanical and Concrete Renovations,
District Project 7351
Mr. Lopez presented the material included in the agenda packet providing
the Committee with a project and budget status, and a brief overview of
some of the condition assessments conducted. He further indicated that
the last time this project was brought before the Committee, the
discussion focused on the history rather than the project components.
The project focuses on the primary treatment process area and has been
designed in coordination with the consultant team led by Carollo
Engineers, Inc. The consultant conducted an extensive amount of
condition assessments in spring and summer 2018, confirming the
complexity of the project scope. A significant amount of the work will be in
concrete repairs, but also includes 40 gate replacements, Odor Control
Unit (OCU) Towers rehabilitation, and repairs to 60-inch diameter primary
effluent pipeline. Staff would like to rehabilitate the critical OCU Towers in
the spring.
Upon reviewing photographs included in the presentation that depicted a
lot of corrosion, Chair Causey inquired as to what lessons were learned
and maintenance that should be performed. Mr. Lopez replied that staff
does shut down portions of the primary process area for maintenance;
however, some areas do not, or cannot be, shut down for work without a
major coordination effort. During the Master Plan, staff began looking
deeper into maintenance and inspections needs and will be incorporating
into projects. Mr. Petit further added that some processes cannot be - or
are very challenging to be - bypassed, and distribution channels cannot be
shut down, which makes it very difficult. One lesson learned is that a valve
and gate exercising program is needed, as staff encountered when
headworks gates were found to be inoperable. Operations has learned
more about the existing condition of the primary structures and practices
to bypass or shut downs required for inspection and emergency situations.
Mr. Lopez said that the Concord Main Flowmeter is currently a venturi
meter that will be replaced with a magnetic flow meter, staying within the
current configuration. In response to a question from Chair Causey, Mr.
Petit said the City of Concord has agreed to pay half the cost of the new
meter.
There was an extensive discussion on gate replacements, including the
proposed project amount or phasing over time, whether pump station
gates should be added to the project, pre-purchasing and storing gates,
potential challenges, cost implications, coordination efforts and timing, and
various complications. Mr. Lopez stated there would be no cost saving to
postponing gate replacements since this work requires expensive bypass
pumping to do the replacement.
October 18, 2018 Regular Board Meeting Agenda Packet- Page 39 of 46
Page 6 of 8
Engineering & Operations Committee Minutes
October 8, 2018
Page 5
Mr. Petit reminded the Committee that the project was out to bid as of this
morning. He added that essentially, the area of the project needs to be
fixed and this project will assist in the prevention of possible emergency
failures that could occur if not handled, as well as addressing odor control.
The project has become larger than originally anticipated, is complex,
labor intensive, and will also require nightwork to complete some work
during lower incoming flows. Projects in the CIB have been evaluated and
will be rescheduled for budget purposes, such as the Outfall
Improvements- Phase 7, to fund this project.
Member McGill pointed out the Outfall Improvements-Phase 7 project has
been postponed before. Mr. Lopez stated that though the improvements
have been postponed two years, staff plans to complete the project in the
year 2020, prior to the year 2021 permit requirement. More information will
be provided on this subject at award.
A lengthy discussion regarding the budgetary components of the project
followed. Member McGill asked what contingency amount was being
carried, Mr. Lopez replied 10% for contract contingency; 15% has been
included in the engineer's estimate. Mr. Petit added that consultants have
been adding a 10% bid market allowance to reflect that the market is
getting more expensive due to higher labor demands and other economic
factors. Chair Causey indicated he does not see a low contingency
amount for this project.
Chair Causey noted that the project estimate is X2.5 million over original
estimate. He asked if staff tried to stay within budget or considered
changing the project scope, adding that the bid climate is not good at this
time. Mr. Lopez replied that as the project condition assessments
progressed the project became larger; some scope has been postponed.
There are several additive bid items in the project. Staff has evaluated and
prioritized the additive bid items. It has been a difficult project to estimate.
Member McGill shared that he does not like trying to force a project into a
budget, not doing a project because of budget, or using a low contingency
to meet a budget figure.
Mr. Petit expressed that although the project budget is higher than
originally planned due to issues that have been encountered and the
scope has grown, staff is not asking for more money but will be
transferring budget from other projects that are not as far along this or
next fiscal year. Chair Causey inquired why not increase the CIB. Mr.
Bailey replied that the CIB will be reconciled at the end of the year in the
standard process, staff will manage this approved CIB and move funds
accordingly.
October 18, 2018 Regular Board Meeting Agenda Packet- Page 40 of 46
Page 7of8
Engineering & Operations Committee Minutes
October 8, 2018
Page 6
Chair Causey expressed that this was a good discussion, that there is
more scope than anticipated, and the exceeded budget needs to be
explained to the Board. Member McGill suggested that staff work on their
explanation and project justification when the item is brought to the Board.
COMMITTEE ACTION: Received the update.
C. Receive a project update of the South Orinda Sewer Renovations, Phase
6, District Project 8433
Mr. Lopez provided the Committee with an informational overview of an
urgent, necessary pipe replacement in the Camino Pablo vicinity in
Orinda. The structural integrity of the sewer line was deemed an urgency
to replace, especially with upcoming wet weather.
This work was authorized under the recently adopted General Manager
Authority, as the work was within the change order threshold amount.
Sufficient contingency remained in the South Orinda Sewer Renovations,
Phase 6 construction contract. Proper notifications were provided to the
City of Orinda and the public. The work was completed by the contractor
expeditiously, and punch list items are underway. Only a few traffic
complaints were received as the work was located near a school. The
contractor accommodated to their best ability but some impacts to student
drop-offs were experienced.
COMMITTEE ACTION: Received the update.
d. Receive list of future agenda items
The Committee and staff reviewed the future list of agenda items.
Chair Causey inquired whether District Project 7349 (Energy Recovery
and Blower Replacement Project) will include a solar alternative. Mr. Petit
replied that it does not; however, a solar update item was planned for an
upcoming Real Estate, Environmental, and Planning Committee meeting.
Mr. Lopez stated he will provide an update at the November Committee
meeting on the bar screen equipment of the Headworks Screening
Upgrade project and will soon provide an update on the final billing of the
Pleasant Hill-Grayson Creek Sewer Replacement project.
COMMITTEE ACTION: Received and provided input to staff.
October 18, 2018 Regular Board Meeting Agenda Packet- Page 41 of 46
Page 8of8
Engineering & Operations Committee Minutes
October 8, 2018
Page 7
5. Announcements
a. Mr. Petit and Mr. Lopez provided the Committee with an informational
update of a challenging sewer replacement on Austin Lane, a private road
in Alamo, where a heritage oak tree was directly above the sewer. This
endeavor required complex coordination due to the tree location and its
roots, right-of-way challenges, and legal involvement. Staff coordinated
with the County and all permits were obtained. The contractor successfully
completed the sewer replacement and was very detailed on the work
performed, documenting with photographs along the way. The pipe is in
place and the contractor is currently in the restoration phase.
6. Future Scheduled Meetings
a. Monday, November 5, 2018 at 9:00 a.m.
Monday, December 10, 2018 at 9:00 a.m.
7. Suggestions for Future Agenda Items
a. Chair Causey requested staff bring the Capital Improvement Business
Case Evaluations (as noted in the Asset Management Program Update
attachment, Item No. 10) for review.
8. Adjournment— at 10:41 a.m.
October 18, 2018 Regular Board Meeting Agenda Packet- Page 42 of 46