HomeMy WebLinkAbout10. Consider accepting Guiding Principles for future temporary diversion agreement with DERWA Page 1 of 32
Item 10.
CENTRALSAN
CENTRAL CONTRA COSTA SANITARY DISTRICT
August 16, 2018
TO: HONORABLE BOARD OF DIRECTORS
FROM: MELODY LABELLA, RESOURCE RECOVERY PROGRAM MANAGER
REVIEWED BY: DANEA GEMMELL, PLANNING AND DEVELOPMENT SERVICES DIVISION
MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
PHIL LEIBER, DIRECTOR OF FINANCE AND ADMINISTRATION
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: CONSIDER GUIDING PRINCIPLES FORA FUTURE TEMPORARY
DIVERSION AGREEMENT WITH DUBLIN SAN RAMON SERVICES
DISTRICT (DSRSD) EAST BAY MUNICIPAL UTILITY DISTRICT (EBMUD)
RECYCLED WATER AUTHORITY(DERWA)
In January2017, Central San received a written request from DERWA to develop a memorandum of
understanding to explore a pilot project to divert a portion of the raw wastewater from the San Ramon
Pump Station from May through September every year. The wastewater would be diverted through
DSRSD's existing collection system to DSRSD's treatment plant, for the purpose of producing and
distributing recycled water to meet DERWA's peak summer irrigation demand. DERWA is making this
request because it has a need for a temporary supplemental supply to help meet recycled water demands
in the EBMUD and IDS RSD service areas until wastewater flows increase with development and other
long-term supply options are identified.
Staff has prepared the attached presentation, which contain Guiding Principles for a future agreement with
DERWA regarding this requested diversion. Staff looks forward to receiving your direction on these
proposed principles at the August 16, 2018, Board meeting.
Strategic Plan Tie-In
GOAL ONE: Provide Exceptional Customer Service
Strategy 3- Maintain a strong reputation in the community
August 16, 2018 Regular Board Meeting Agenda Packet- Page 104 of 149
Page 2 of 32
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 1 - Manage assets optimally throughout their lifestyle
GOAL SIX: Embrace Technology, Innovation and Environmental Sustainability
Strategy 1 -Augment the region's water supply
ATTACHMENTS:
1. Presentation
August 16, 2018 Regular Board Meeting Agenda Packet- Page 105 of 149
I GUIDING PRINCIPLES FOR A
TEMPORARY DIVERSION
AGREEMENT WITH DERWA
Melody LaBella, P.E.
Resource Recovery Program Manager
Danea Gemmell, P.E.
Planning and Development Services Division Manager
- Board Meeting
CIA- August 16, 2018
August 16, 2 Board Me
PRESENTATION OVERVIEW
• Background
• Dublin San Ramon Services District (DSRSD) - East
Bay Municipal Utility District (EBMUD) Recycled Water
Authority (DERWA) Temporary Diversion Request
• DSRSD
• DERWA
• Central San's San Ramon Pump Station Sewershed
• Guiding Principles for an Agreement
• Staff Recommendation
, Questions & Board Input
&Jh2
DERWA's TEMPORARY DIVERSION REQUEST
• In January 2017, Central San received a written request
from DERWA to develop a memorandum of understanding to
explore a pilot project to divert a portion of the raw
wastewater from the San Ramon Pump Station from May
through September every year.
• The wastewater would be diverted through DSRSD's
existing collection system to DSRSD's treatment plant, for
the purpose of producing and distributing recycled water to
meet DERWA's peak summer irrigation demand .
• DERWA is now making this request, because it has a need
for a temporary supplemental supply to help meet recycled
water demands in the EBMUD and DSRSD service areas
until wastewater flows increase with development and other
long-term supply options are identified.
CENTRALSAN
' 3
PROPOSED DIVERSION
• Would divert ~ 1 .3 MGD of the ~2 .5 MGD
average dry weather wastewater flow through
the San Ramon Pump Station
• Would span up to 5 months of diversion to
coincide with DERWAs peak summer irrigation
demand
• Would use the existing gravity intertie between
Central San's and DSRSD's collection systems
' 4
NOW-
116- CENTRALSAN
Regional YrewlSe"ke Area Map
DSRSDi
CCCSD
S �°" CCCSD "a` "d
4 Torun d t)&AS['
00 San
areal Famcia I.)SRSII
HERTY VALLEY
Wastewater Service Area 1
ti
• 10. 19 million gallons
per day (mgd) annual SAN ON _
daily averagetA
A`
� W Paucs•
I FTA /-
• 9.7 mgd average dry
weather flow (ADWF)
• 12.3 mgd projected
w
ADWF at buildout
a �
T
(2035)
Water Service Area
• 30% population Map Legend
growth (2015-2035) OSRS1)flegonalWastewater Treatment Facility
0SRSID Winer Only Service Area !�
DSRSD Wastewater Only Service Area
051351)Wastewater Treatment Under Contract I jF—We
MRS Water&Wastewater Service Area
-- Alameda Contra Costa County Dividing Line
DSRSD Boundary
1v 5
CENTRALSAN
Map features
® Pump Station East Bay Dischargers Authority
Wastewater Treatment Plant Effluent Disposal System
Dechlorination Facility LAVWMA Export Pipeline
16-0 Diffuser "' Livermore Pipeline
�a5
San Leandro Plant
and Effluent Pump Station
Bay Outfall and LAVWMA Pump Station Livermore Wastewater
Diffuser Treament Plant
WTP Marina Dechlorination Facility
D n �,
WTDSRSD Wastewater
,. ^ Hayward Effluent Pump Station Treament Plant
Oro Loma-Castro Valley Plant
and Effluent Pump Station
WiP
Hav%t(a i lhusli Hayward Treatment Facility
Alvarado Treatment Facility
and Effluent Pump Station
WTP E
AS•7
?80�
0 1 2 4 Miles 6
DERWA
• DERWA created the San Ramon Valley
Recycled Water Program (SRVRWP) in 1995
and began delivering recycled water in 2006 .
• Being implemented in several phases within
DERWNs existing service areas
• Future phases will extend recycled water into
other parts of the San Ramon Valley, depending
on supply and demand and capital funding
needs and availability.
116- CENTRALSAN1
SRVRWP
• Designed to provide:
• Up to 3,696 acre-feet (> 1 billion gallons) per year
of recycled water to DSRSD's service area
• Up to 2,688 acre-feet (>875 million gallons) per
year of recycled water to EBMUD's service area
• It has been known since inception that DERWA
would face supply shortages
• DERWA first evaluated the concept of diverting
Central San's raw wastewater flow in 2004
DERWA San Ramon Valley
Recycled Water Program
Current racllltles
Location Map (April ZW6)
EBMUD
Service Area
7--7--- r.,m r,.yw.
4 wmvuio.hr�jwee
o n —I,FMM
s�
P.M
x0, `
—I -
DSRSD r
y. J
Service Area r
� I
1MSA Fti
r j
tr
Pleasanton
f" Service Area
MMM 11h9L
IL
RACENTLSAN
DERWA PEAK DAY RECYCLED WATER
DEMAND VS , DSRSD WASTEWATER SUPPLY
Recycled Water Demand Versus Supply
Peak Demand
Peak Days Projected to
16.00 Exceed Supply b
pp Y Y
14.00 -5 MGD by 2022
20.00
5.00
6.00
1,ou
2.00
o.ao
7011 2018 2019 2020 2021 2022
N....nt- MUD �OSRSD —Sup*
Source: DSRSD
10
DERWA's RECYCLED WATER SUPPLY
SHORTFALL STRATEGIES
1 . Potable addition during peak demands (within
State guidelines during drought conditions)
2 . Demand management — voluntary or
mandatory cutbacks, timing shifts for big users,
pricing to reflect scarcity, switch users back to
potable
3. Connection moratorium
4. Central San diversion (temporary - a five-year
agreement to divert 1 . 3 MGD starting next
summer is currently being considered )
DERWA's RECYCLED WATER SUPPLY
SHORTFALL STRATEGIES (CONTINUED)
5. Livermore connection (temporary)
6 . Groundwater pumping (though this supply has
serious quality issues)
7 . Groundwater storage (long term)
8 . Other sources (such as East Bay Dischargers
Authority, though quite expensive)
N it -Z
F11
-{14 4 xl T, IJ
!' � 4�
' ` 10
5
PIS San Ram c)n Pump Statim Ce ntral San Bou-dary San Ramon Pump Station San Ram on City Limit r
_
DSRSE)Wastewater Only Service Area
- DSRSD Water Only Service Area
DSRSD
NTRALSAN San Ramon Pump Station Sewershed
Cen rRa,��;�r,rkr,ec}s a sar,�rwer oarrr�er
_..._..�.-----,------.�_......__......._ CENTRAL SAN
RESIDENTIAL UNIT EQUIVALENTS ( RUES
Service Sewershed
Area Area
Current
Residential 136,663 15,551
Non-residential 30,006 11604
Subtotal 166,669 173155
Projected additional RUEs ( 12 years) 51261
Total at Buildout 223416
Total Capacity Fees through 2030 $43)9001000
6 f
` 14
�;2ft R
CENTRALSAN
ANNUAL REVENUE
1=1 Service Area Sewershed
Area
Sewer Service Charge $ 9570007000 $ 977787210
Ad Valorem Tax $ 1678287591 $ 17732, 142
Capacity Fees $ 615007000 $ 37700,000
Misc. (Permits, inspections, etc.) $ 673587696 $ 6547491
. -
LIM
20`S R 15
NOW L CENTRALSAN
'. .
FIXED AND VARIABLE O&M COSTS
Sewershed
Service Are Area
Fixed O&M Cost (Annual ) $83,078,356
Variable O&M Cost $ 6,651 , 100
(Annual)
Variable O&M Cost
(5-month Diversion Period) � 243,348
"—""..�..
16
N��'s:2t�P& Regeiei seals u�eeniig r�geiiee i eei�e� i age rr i et lye _ '
Mme—'' CENTRALSAN
GUIDING PRINCIPLES FOR AN AGREEMENT
1 . No Adverse Financial Impact to Central San
2. No Adverse Financial Impact to Concord and Clayton
3. Consistency with Existing Bond Covenants
4. Consistency with Proposition 218
5. Community Support
6. Temporary Nature
7. Mitigation of Technical and Operational Impacts
8. Benefits to Central San Customers
9. Facilitate a Sustainable Solution to the Region's Water
,1\ Supply Shortage
GUIDING PRINCIPLE 1
NO ADVERSE FINANCIAL IMPACT TO CENTRAL SAN
• No additional operational cost to Central San
• Revenues (including Ad Valorem Tax, capacity
fees, sewer service charges) will not be shared
to the extent they are used to recover 100% of
Central San's systemwide fixed cost.
• Variable costs will be assessed and revenues
collected to cover these costs may be shared .
• Any fines from overflows caused by the
diversion will be reimbursed by DERWA.
� 18
GUIDING PRINCIPLE 2
NO ADVERSE FINANCIAL IMPACT
TO CONCORD AND CLAYTON
• The City of Concord and Town of Clayton provide
-$24M annually in revenue.
• Concord's annual bill is based on their proportional
share of flow at Central San's treatment plant.
• A diversion from Central San's collection system will
reduce Central San's flow to the treatment plant,
which causes an increase in Concord and Clayton's
proportional share.
• The requested wastewater flow equates to an
-$300 ,000 annual increase to Concord and
Clayton , if not adjusted .
6, Gve
1k*i— -
' 19
GUIDING PRINCIPLE 3
CONSISTENCY WITH EXISTING BOND COVENANTS
• Central San will not de-annex any portion of its
service area for the sake of implementing this
temporary diversion .
• Central San will not share any revenues associated
with the area served by the San Ramon Pump
Station , to the extent those revenues are used to
cover Central San's systemwide fixed costs.
Zro 112
GUIDING PRINCIPLE 4
CONSISTENCY WITH PROPOSITION 218
• There are concerns that the collection of revenues to
cover the transportation and treatment of wastewater
from customers within the subject area may be at
risk for a Prop 218 challenge, to the extent that
those customers do not benefit from Central San's
downstream conveyance and treatment facilities and
their associated cost.
• Any Prop 218 challenge will be grounds for
termination of agreement.
� 21
GUIDING PRINCIPLE 5
COMMUNITY SUPPORT
• Community support is essential for the successful
information of this project, including the following :
• Central San customers
• City of Concord and Town of Clayton
• The adjoining San Ramon Pump Station
neighborhood
• City of San Ramon
• San Ramon Valley Unified School District
• East Bay Regional Park District
GUIDING PRINCIPLE 6
TEMPORARY NATURE
• Central San is in the middle of a Memorandum of
Understanding with Contra Costa Water District and
Santa Clara Valley Water District regarding a
recycled water exchange project.
• To the extent this is proven viable, Central San may
need this wastewater supply to meet this and other
existing recycled water commitments, so Central
San retains the right to the requested wastewater
flow.
A&&2323
GUIDING PRINCIPLE 7
MITIGATION OF TECHNICAL AND
OPERATIONAL IMPACTS
• No damage to Central San's infrastructure during
the diversion
• Maintain minimum amount of wastewater flow to
prevent solids from settling in Central San's
collection system
• Mitigation of any significant increased potential for
odors or overflows
• Installation of an appropriate meter to measure
diverted flow, with frequent meter calibration
' 24
GUIDING PRINCIPLE 8
BENEFITS TO CENTRAL SAN CUSTOMERS
• The wastewater temporarily diverted from
Central San's service area will be available to
Central San's service area as recycled water.
ga�e uheeniiggeiiee i eeiei ege gee et iye _ ' 25
GUIDING PRINCIPLE 9
FACILITATE A SUSTAINABLE SOLUTION FOR THE
REGION 'S WATER SUPPLY SHORTAGE
• Central San understands the water supply
concerns/need within the Bay Area .
• Central San will work with agencies/stakeholders
within the region to:
• Facilitate the most optimal solution to collect and treat
wastewater within its service area
• Distribute such treated effluent for the benefit of its
customer base and the greater region
ik:� ZTV 112
GUIDING PRINCIPLE 9 (CONTINUED
FACILITATE A SUSTAINABLE SOLUTION FOR THE
REGION 'S WATER SUPPLY SHORTAGE
• There are several recycled water projects, which ,
collectively, may achieve this overarching goal :
• Zone 1
• Concord Community Reuse
• Diablo Country Club Satellite Water Recycling Facility
• Refinery Recycled Water Exchange Project
• The Exchange Project represents the potential
, for the most optimal regional solution .
&z7
CENTRAL SAN , CONTRA COSTA WATER DISTRICT &
SANTA CLARA VALLEY WATER DISTRICT
WATER EXCHANGE CONCEPT
Martinez ' I
Refineries
� u
u �•
iy
22 TAFY
Transfer-Bethany
AP Pipeline
22 TAFY 22 TAFY (proposed)
Santa Clara Valley
Water District
CCWD
*TAFY = thousand acre-feet per year Expanded
**CVP = Central Valley Project Los Vaqueros
` 28
CENT■
STAFF RECOMMENDATION
Accept these guiding principles or
provide additional direction to staff
f
29
NOW
CENTRALSAN
QUESTIONS
AND
BOARD INPUT