Item 5.a.
CENTRAL
07,Mkom MW.1 Z I I NOW1 Central Contra Costa Sanitary District
August 13, 2018
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY:
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY GENERAL MANAGER
SUBJECT: ANNOUNCE REQUEST FOR PROPOSAL (RFP) FOR DESIGN SERVICES
FOR THE INFLUENT PUMP ELECTRICAL IMPROVEMENTS, DISTRICT
P ROJ E CT 7328
The Influent Pump Electrical Improvements, District Project 7328, will renovate and improve the Influent
Pump Facility at the treatment plant. This facility is critical to operations and without the pumps, wastewater
cannot be treated or stored in the basins. The project will add a new pump for reliability and replace the
existing variable frequency drives which have reached the end of their useful life.Additional electrical and
control improvements will be addressed to correspond with the listed improvements needed in the facility
to maintain its reliability and resiliency.
The RFP for design services will be advertised on August 31, 2018, with proposals due September 21,
2018. The estimate for consultant services is approximately$500,000. More information will be presented
to the Board when the authorization for professional engineering services is presented in November.
August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 30 of 30