HomeMy WebLinkAbout04.b. Receive report on Fiscal Year 2017-18 Closeout of Capital Improvement Projects Page 1 of 13 Item 4.b. CENTRAL 07,Mkom MW.1 z I I Nowl Central Contra Costa Sanitary District August 13, 2018 TO: ENGINEERING AND OPERATIONS COMMITTEE FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER REVIEWED BY: THEA VASSALLO, FINANCE MANAGER JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL SERVICES SUBJECT: RECEIVE REPORT ON FISCAL YEAR 2017-18 CLOSEOUT OF CAPITAL IMPROVEMENT PROJECTS Eleven (11)capital improvement projects have been closed in Fiscal Year 2017-18.Attachment 1 lists the expenditures and budget underrun or overrun for each project.All expenditures are based on the pre-audit financial reports ending June 30, 2018.Attachment 2 contains a brief summary of the work completed under each project. For project budget details, please reference the information provided under the Financial Statements. ATTACHMENTS: 1. Expenditure Summary 2. Project Descriptions 3. Presentation August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 7 of 30 Page 2 of 13 Attachment 1 Expenditure Summary Fiscal Year 2017-18 Closed Projects TREATMENT PLANT (TP) PROGRAM DISTRICT PROJECT TITLE EXPENDITURES UNDERRUN PROJECT NO. AS OF 6/30/18 (OVERRUN) 7311 TP Safety Enhancement Phase 4 Rev 3391072 928 7314 TP Urgent Repairs 71421 71579 7319 Laboratory Upgrades and Repair 1,235,462 61041 Program Totals $1,581,955 $14,548 COLLECTION SYSTEM (CS) PROGRAM DISTRICT EXPENDITURES UNDERRUN PROJECT NO. PROJECT TITLE AS OF 6/30/18OVERRUN ( ) 5941 PS Equipment and Piping Replacement 905,050 41951 8417 Survey Monument Install 2491964 39 8420 Development Sewerage 413381840 321269 8422 Walnut Creek Sewer Renovation, Phase 11 317431931 61065 8434 CS Urgent Repairs 3461814 (50,700) 8437 Martinez Sewer Renovation, Phase 5 411541705 293 8439 Miner Road Sewer Repairs 1011169 (61170) Program Totals $13,840,473 ($13,253) GENERAL IMPROVEMENTS PROGRAM DISTRICT PROJECT TITLE EXPENDITURES UNDERRUN PROJECT NO. AS OF 6/30/18 (OVERRUN) 8227 Geographic Data Integration (GDI) Treatment Plant 4321356 (71354) Program Totals $432,356 ($7,354) RECYCLED WATER PROGRAM There were no projects closed in Fiscal Year 2017-18. Page 1 of 1 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 8 of 30 Page 3 of 13 Attachment 2 Project Descriptions Fiscal Year 2017-18 Closeouts TREATMENT PLANT PROGRAM Project No. Project Title 7311 Treatment Plant Safety Enhancements Phase 4 Revised Central San has very proactive safety programs administered by separate committees responsible for addressing safety concerns identified by the craftsmen, safety modifications, identified repairs, or in response to ever-changing regulatory requirements. This phase included hazardous waste facility improvements and other safety related items within the treatment plant facilities. 7314 Treatment Plant Urgent Repairs Urgent treatment plant work which requires immediate repairs arise at any time, some cannot be completed by maintenance staff or wait for incorporation into a capital improvement project. This project encompassed miscellaneous areas around the plant and were triggered by equipment or process piping failures; compliance with regulatory or code issues; and/or safety or unexpected damage due to excessive or unexpected hazards. Staff intended to procure a standby contractor to perform such activities; however, due to the lack of outside interest and the current bid environment staff decided to assign this scope of work to the Treatment Plant Piping Renovations Project-Phase 9 and other projects within the Treatment Plant Program. 7319 Laboratory Upgrades and Repairs The laboratory is a critical component to regulatory reporting and operates several critical systems to maintain the facilities required to conduct testing. This project included work to address corroded hot water heat exchangers and tanks; obsolete and outdated HVAC control systems; replacement of a 150-ton roof chiller, including structural support modifications; and improved electrical and mechanical controls to the chiller and HVAC system COLLECTION SYSTEM PROGRAM Project No. Project Title 5941 Pump Stations Equipment and Piping Replacement The purpose of this project was to replace or recondition various failed and obsolete equipment, provide for proper emergency response at the pumping stations, and to meet new regulatory requirements. This project included the addition of appropriate control and isolation valves for shutdown and station protection; station and equipment flood protection; reconditioned major pieces of equipment to original factory specifications; purchased spare assemblies needed for pump station equipment; and investigated pump-around capabilities. 8417 Survey Monument Install The Survey Monument Installation project consisted of the installation/replacement of survey monuments which were removed during sewer renovations. This project provided staff with the contracted resources necessary to fulfill the professional and legal obligations that the survey monuments provide. 8420 Development Sewerage The purpose of this project was to provide for capitalization of labor for Central San forces and other expenses associated with developer installed sewer facilities. A portion of the revenue collected from these development projects is credited to the Sewer Construction fund to offset some of the expenditures made under this capital project. Page 1 of 2 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 9 of 30 Page 4 of 13 Attachment 2 Project Description Fiscal Year 2017-18 Closeouts 8422 Walnut Creek Sewer Renovations Phase 5 This project replaced and renovated 8,970 feet of small diameter sewer pipes and installed 23 manholes located in easements and public rights-of-way to prevent overflows, reduce maintenance requirements, lower system infiltration, and provide excellent customer service to the public. 8434 Collection Systems Urgent Repairs The purpose of this project is to restore and protect sewers that are discovered to be damaged or near failure during field maintenance or investigation. Sewer improvements that were identified to be completed under this repair program included sewers that were in poor condition and beyond repair that could not be incorporated into another capital project. This includes assessments made by failed sewers during routine cleaning, failed or damaged sewers by unexpected hazards or events, and safety or site hazards that posed a serious threat to the integrity of the collection system infrastructure. Staff intended to procure a standby contractor to perform such activities; however, due to the lack of outside interest and the current bid environment staff decided to assign this scope of work to other projects within the Collection System Program. 8437 Martinez Sewer Renovations Phase 5 This project replaced and renovated approximately 8,800 feet of existing sewers and infrastructure and 43 new or replaced manholes located in easements, public rights-of-way. Most of the sites were located south of Highway 24 in the Martinez area. 8439 Miner Road Sewer Repairs 2017 This emergency project was due to sewer failures caused by the significant rain events in February of 2017. A large sinkhole engulfed two sewers on Miner Road in Orinda. These sewers were repaired, and all work was coordinated with the City of Orinda and other agencies to restore the roadway. GENERAL IMPROVEMENTS PROGRAM Project No. Project Title 8227 Geographic Data Integration (GDI) Treatment Plant The GDI Treatment Plant project implemented a geographically based asset management system for the treatment plant. This tool will optimize the interface and functionality accessing the asset data. After successful implementation of the collection system GDI, the treatment plant GDI will provide efficient access to asset drawings and data. RECYCLED WATER PROGRAM Project No. Project Title There were no Recycled Water projects closed in Fiscal Year 2017-18. Page 2 of 2 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 10 of 30 Page 5 of 13 � FISCAL YEAR (FY) 2017-18 CLOSED PROJECTS r _ August 13, 2018 Meeting ;.�.. . Engineering and Operations Committee Edgar J. Lopez, PE y_ Capital Projects Division Manager TOTAL EXPENDITURES BY CAPITAL PROGRAM Program Total Expenditures Treatment Plant (TP) $1,581,955 Collection System (CS) $13,840,473 General Improvements (GI) $432,356 Recycled Water (ReW) $0 Total $15,854,784 1 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 11 of 30 Page 6 of 13 TREATMENT PLANT PROGRAM CLOSED PROJECTS > $1 MILLION Project project Title Total Number Expenditures 7319 Laboratory Upgrades and $1,235,462 Repair how.- CENTRALSAN LABORATORY UPGRADES AND REPAIR, DISTRICT PROJECT (DP) 7319 Purpose: Replace, repair, and/or upgrade the existing equipment at the treatment plant laboratory Work completed: Chiller rental Replaced the 150-ton roof chiller, included structural support modifications Improved the controls to the chiller and system Additional electrical and mechanical to improve the efficiency of system CENTRALSAN 2 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 12 of 30 Page 7 of 13 I Structural Steel Modifications i Lifting new chiller onto roof V 5 CENTRALSAN M�. 1 I� YYS 4 e 1 :1 p New Industrial 150-ton Chiller 4 _ CENTRALSAN k'i M1, 3 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 13 of 30 Page 8 of 13 COLLECTION SYSTEM PROGRAM CLOSED PROJECTS > $1 MILLION Project project Title Total Number Expenditures 8420 Development Sewerage $4,338,840 $422 Walnut Creek Sewer $3,743,931 Renovation, Phase 11 8437 Martinez Sewer Renovation, $4,154,705 Phase 5 '04 NON, CENTRALSAN DEVELOPMENT SEWERAGE, DP 8420 Purpose: Provide for capitalization of Central San force account labor and other expenses for developer installed sewer facilities Project opened in FY 2013-14 In FY 2017-18 capitalization was captured under Operating budget, contributed assets; approximately $440k CENTRALSAN 4 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 14 of 30 Page 9 of 13 WALNUT CREEK SEWER RENOVATION PHASE 11 DP 8422 Purpose: Replace/renovate deteriorating and high maintenance sewers Work completed: Installed/replaced total of 8,970 feet of sewer mains by open-cut, pipe-bursting, and Cured-in-Place Pipe (CIPP) Installed 23 manholes (new or replaced) CENTRALSAN Prollga Arigas •t tiv_ r K � CEA Ry qD i t ` � x r _ + ' e 1 u Walnut Creek Renovation, Phase 11 74 r Location Map a .} !~t itn, t f WWa Inu t CF010 r$ewer Re npw�fign Pha��11 A1tadin er7121 ti)O �+�**i M Dis trial Projec t 8422 = Pmjeo Lori#ion CENTRALSAN 5 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 15 of 30 �40 1 • 16°. - 6 '- f■m ; J 7F 4 4 iY_ r Ah Ah r� °_"...• V i-,. �_�+'°° '� I Al .14 k L AF •; - CENTRALSAN r Mff PQI -� f r • k t rry •� - y ` 4 - ,, r CENTRALSAN • Page 11 of 13 MARTINEZ SEWER RENOVATION PHASE 5 DP 8437 Purpose: Replace/renovate deteriorating and high maintenance sewers Work completed: Installed/replaced total of 8,800 feet of sewer mains (open-cut and pipe-bursting) Installed 43 manholes (new or replaced) Located in easements and public rights-of-way c - 113 CENTROS:, ■ 9 01" 1 Tr_ C Martinez Renovation, F* - Phase 5 Location Map v. ' s r �4 fJ FOM x w [st Rrt e7 1 = 14 _gR 7 August 13, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 17 of 30 •- • +. s �T T � � j 40 t -09". v SIF r ¢ AT. a r - zd � Fit 17 r CENTRALSAN p y .. _ i7 k �r nr ft CENTRALSAN • • •— • �0- �_�,•-• .a a ,�- � ':r�fid'�',� •.`.'}��' .'.. i f F-rs�� �� `� Fes' - ^�' "_ �e r<w � .f y1i r �1. .f f •, �• r r'f r 15 I 40 46 r F ait MP � I I 1 } 41 r .'. IL pr CENTRAL SAN Questions? I F � � • CENTRAL SAN •