HomeMy WebLinkAbout13.a. Presentation on pre-selection process for key equipment re Solids Handling Facility Improvements Project, DP 7348 Page 1 of 7
Item 13.a.
CENTRALSAN
CENTRAL CONTRA COSTA SANITARY DISTRICT
July 5, 2018
TO: HONORABLE BOARD OF DIRECTORS
FROM: NATHAN HODGES, SENIOR ENGINEER
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING & TECHNICAL
SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE PRESENTATION ON PRE-SELECTION PROCESS FOR KEY
EQUIPMENT IN SUPPORT OF THE SOLIDS HANDLING FACILITY
IMPROVEMENTS PROJECT, DISTRICT PROJECT 7348
The Solids Handling Facility Improvements Project (Solids Project)will make improvements to nearly all
solids handling processes found in the Solids Conditioning Building (SCB). These processes include
sludge blending, dewatering, furnaces, and air pollution control equipment. Central San's design
consultant, Black& Veatch, recently completed the 10-percent Pre-design phase and one of the
outcomes of that effort was the recommendation to select critical equipment early in the Design phase.
The equipment to be pre-selected are the centrifuges, cake pumps, and wet scrubbers.
These specific pieces of equipment were identified in both the Comprehensive Wastewater Master Plan
and Black& Veatch's pre-design as nearing the end of their useful life and in need of replacement. Also, in
the case of the wet scrubber, the existing equipment will not meet upcoming regulations.
Black& Veatch's recommendation to pre-select equipment brings advantages to the project:
• Construction drawings and specifications will be based on the actual equipment
• Utilizing 3D model will detect conflicts, confirm access, and maintain operation during construction
• Improve cost estimates during design
• Reduce change orders
Black& Veatch and staff are finalizing the Basis of Design Memoranda and technical specifications for this
equipment. The memoranda summarize the design objectives and document the performance criteria that
will be used to select the equipment. The specifications will be included in the procurement documents.
Staff has met, and continues to meet, with Legal Counsel to review the pre-selection process and ensure
that selection complies with public procurement code. The centrifuges, cake pumps, and wet scrubber will
be selected using an open request for proposal (RFP)followed by low-bid selection. The RFP will be
July 5, 2018 Regular Board Meeting Agenda Packet- Page 151 of 195
Page 2 of 7
posted on Central San's website, proposals will be evaluated against pre-established criteria, and those
manufacturers that meet these criteria will move on to the final bid selection phase. Final selection of this
equipment will be based on the lowest, responsive bid. A purchase order (PO)will be issued to the
manufacturer only for the cost of up front engineering and shop drawings preparation. The equipment
manufacturing, delivery, and payment will be assigned to the General Contractor.
Coordination of the front end documents for equipment selection and construction is critical so that there
are no conflicts. Staff is working with Black& Veatch and Legal Counsel to ensure that Central San is
protected. Staff has hired a third party consultant with extensive experience in construction document
preparation to assist in the preparation of the front end documents.
Jean-Marc Petit, Director of Engineering and Technical Services, will present a summary of the Solids
Project Key Equipment Pre-Selection.
Strategic Plan re-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to achieve 100%permit compliance in air, water, land, and other regulations
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 2- Facilitate long-term capital renewal and replacement
ATTACHMENTS:
1. Presentation
July 5, 2018 Regular Board Meeting Agenda Packet- Page 152 of 195
Page 3 of 7
SOLIDS HANDLING FACILITY IMPROVEMENTS
PROJECT - DP 7348
KEY EQUIPMENT PRE-SELECTION
A'- Jean-Marc Petit
Director of Engineering & Technical Services
Board Meeting
July 5, 2018
4�
RECOMMENDED IMPROVEMENTS FROM PRE-
DESIGN EFFORT FOR SOLIDS HANDLING PROJECT
1 2 7 4 5 8 3 6
I
�y I
I � �
I
SLVOOEBLEXOIXL/SIOAALE LI NEAUOIiIOX CEIfIAIFULEOEWAiEAIN6 NVLLNLEHFARTH AIRAOLWIION SCB SEISNfL AAND AND ENEN6ENCY SLUUGE
SYSTEM FLMINACES [ONT0.0L ILLlA09T LOADOUT LOAOOUT
Elements to be Pre-Selected
z
CENTRALSAN
1
July 5, 2018 Regular Board Meeting Agenda Packet- Page 153 of 195
Page 4 of 7
KEY EQUIPMENT TO BE PRE-SELECTED
• Centrifuges
• Cake Pumps
• Air Pollution
Control
Equipment
-
Systems --- ------ -
CENTRALSAN
BACKGROUND
• Centrifuge and cake pump pre-selection
• Procurement of wet scrubber
• Combined RFQ-RFP document
• Equipment selection progress summary
Questionnaires sent to vendors and responses received Completed
Site visits and summary notes
Draft Basis of Design Memos(BDM),Draft front end documents Completed,in CS review
Draft technical Specifications(Division 1—16) Completed,in CS review
Finalize BDMs Late lune 2018
Front end document workshop Completed
Final equipment selection document Mid August 2018
Open SOQs and Bids October 2018
Award Contract to selected manufacturers December 2018
CENTRALSAN
2
July 5, 2018 Regular Board Meeting Agenda Packet- Page 154 of 195
Page 5 of 7
ANTICIPATED DESIGN AND CONSTRUCTION
SCHEDULE
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Equipment Procurement I�
RFP and Equipment Selection I�
Equipment Procurement
Shop Drawings
Final Design
(30%,60%,95%,100%)
Bidding _
Bid and Award
Construction
Installation and Commissioning
Procurement Phase: January 2018—August 2019
Design Phase: April 2018—October 2019
Bid &Construction Phase: October 2019— December 2022
5
CENTRALSAN
PRE-SELECTION OF EQUIPMENT IMPROVES
COLLABORATION AND DESIGN ACCURACY
• Customizes final drawings and specifications
based on actual equipment
• Drives high quality design -
• Interference detection and avoidance
• "Walk through"for Central San review of = -
operations access and maintenance space
and hoisting provisions
• High level coordination with Electrical,
Instrumentations,and Controls
• Leverage 3D model to develop construction
phasing and help maintain plant operations
• Facilitates cost estimating for final installation
• Reduces Change Orders
6
CENTRALSAN
3
July 5, 2018 Regular Board Meeting Agenda Packet- Page 155 of 195
Page 6 of 7
EQUIPMENT PROCUREMENT FOR
CENTRIFUGES, CAKE PUMPS, AND WET
SCRUBBERS
O 4 4 0 O
EL >
1. Issue SOQ and Bids for equipment
2. Open Bid for qualified equipment only
3. Award to most qualified and lowest responsible manufacturer for
centrifuges,cake pumps,and wet scrubber systems
4. Issue PO for shop drawings only and pay when completed
5. Actual equipment purchase will be assigned to General Contractor for
later manufacturing and delivery when needed based on bid price(*)
(*)adjusted for inflation
7
ESTIMATED CASH FLOW FOR EQUIPMENT
PRE-SELECTION
Procurement FY 2017- FY 2018-19 FY 2019-20 FY 2020-21 FY 2021-22 Subtotals
Centrifuges Procurement $ 285,000 1,282,500 $ 1,282,500 $ 2,850,000
Cake Pumps Procurement $ 180,000 $ 810,000 $ 810,000 $ 1,800,000
Wet Scrubbers Procurement $ 215,000 $ 967,500 $ 967,500 $ 2,150,000
Total $- $ 680,000 $ 3,060,000 $ 3,060,000 $- $ 6,800,000
Estimated Commitment
8 `
CENTRALSAN
4
July 5, 2018 Regular Board Meeting Agenda Packet- Page 156 of 195
Page 7 of 7
NEXT STEPS
• Advertise procurement documents
Bring Position Paper back to E&O Committee and Board of
Directors for approval to sign purchase orders
• Finalize Design of Solids Handling Facility Improvements Project:
April 2018—October 2019
9
CENTRALSAN
QUESTIONS?
10 `
CENTRALSAN5
July 5, 2018 Regular Board Meeting Agenda Packet- Page 157 of 195