HomeMy WebLinkAbout03.b. Review proposed Fiscal Year 2018-19 Capital Improvement Budget (CIB) and Ten-Year Capital Improvement Plan (CIP) Page 1 of 14
Item 3.b.
Central Contra Costa Sanitary District
May 7, 2018
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: REVIEW PROPOSED FISCAL YEAR 2018-19 CAPITAL IMPROVEMENT
BUDGET (CIB) AND TEN-YEAR CAPITAL IMPROVEMENT PLAN (CIP)
Staff will present a summary of the proposed Fiscal Year 2018-19 CIB and 2018 Ten-Year CIP for review
and discussion.
New to the C I B:
• Operating impacts to project descriptions
• CIB changes from the previous year
• Included C I B/C I P process
• Funding sources for individual projects
ATTACHMENTS:
1. Presentation (Replaced by revised version)
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 10 of 51
Page 2 of 14
Item 3.b.
(Handout)
PROPOSED FISCAL YEAR (FY) 2018-19
CAPITAL IMPROVEMENT BUDGET
Engineering and Operations Committee
May 7, 2018
Presented by
Edgar J. Lopez, PE
Capital Projects Division Manager
CENTRALSAN
1
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 11 of 51
Page 3 of 14
FY 2017-18 MAJOR ACCOMPLISHMENTS
Completed construction of the Pleasant Hill-Grayson Creek Trunk Sewer
Project. Replaced and installed up to 10,000 feet of trunk sewers in
Pleasant Hill. Abandoned the deteriorated original trunk sewer along
Grayson Creek.
Replaced approximately five miles of sewers in the Collection System;
achieved 93% overall customer satisfaction rating on surveys received to
date this fiscal year.
Continuing construction of the Headworks Screening Upgrade Project;
installed two new bar screens and disposal facility, which allows the
screening materials to be removed from the wastewater.
Completed construction of the Pump and Blower Building Seismic Upgrade
Project.
Completed Pre-Design of the Solids Handling Facility Improvements,
including scrubber pilot and Pump Station Upgrades.
Started Pre-Design of the Filter Plant and Clearwell Improvements Project.
Started construction of the water upgrades under Piping Renovation —
., Phase 9.
2
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 12 of 51
Page 4 of 14
PROPOSED FY 2018-19
CAPITAL IMPROVEMENT BUDGET
UnderFuture FYs FY 2018-19 Active 2018-19 CIB Budget to FY 2018
Program
(2) Projects Comparison
Collection System $19,347,000 $109,085,540 $128,432,540 $308,958,000
Treatment Plant $16,865,000 $158,460,500 $175,325,500 $428,207,000
General Improvements $4,750,000 $11,418,800 $16,168,800 $25,432,000
Recycled Water $2,857,000 $20,387,500 $23,244,500 $23,675,000
Contingency $1,500,000 $8,000,000 $9,500,000 $19,500,000
Totals: $45,319,000* $307,352,340* $352,671,340 $805,772,000
*Approval of FY2018-19 projects may commit approximately
$31.2 million in the following fiscal years.
3
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 13 of 51
Page 5 of 14
FY 2018-19
COLLECTION SYSTEM (CS) PROGRAM
MAJOR PROJECTS FOCUS
Sewer Renovation:
Construction Lafayette, Ph. 12 includes 8,800 feet of sewers
Construction Walnut Creek, Ph. 12 includes 8,500 feet of sewers
Construction of Orinda projects includes 17,300 feet of sewers
Designs for Danville, Lafayette, Martinez, Orinda, Pleasant Hill,
Walnut Creek, and other communities in the Service Area
Pump Stations:
Final Design of Pump Stations Upgrades - Phase 1 for Moraga,
Orinda Crossroads, and Flush Kleen Pump Stations
No capacity driven projects (not including developer and CAD)
4
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 14 of 51
Page 6 of 14
FY 2018-19 CS PROGRAM
TOTAL ESTIMATED COSTS PER PROJECT
Project Project Budget-to- IFY 2018-19 IFY 2019-20 future Fys Total ProjectNumber Date
5991 Pleasant Hill Sewer Renovation-
Phase 2 $460,000 $0 $0 $0 $460,000
6602 South Jackson Contractual
As sessment District CAD $411,290 $0 $0 $0 $411,290
6603 North Jackson Contractual
Assessment District ICADI $400,000 $0 $0 $0 $400,000
8249 CSO Dump Pad Modifications $60000 $0 $0 $0 $60000
8419 Collection System Planning $870,000 $100,000 $206,000 $412,000 $1,588,000
8433 S.Orinda Sewer Renovation-Phase 6 $1,962,127 $2,758,873 $0 $0 $4,721,000
8435 Walnut Creek Sewer Renovation-
Phase 12 $1,450,000 $3,100,000 $0 $0 $4,550,000
8436 Pump Station Upgrades-Phasel $1,300,000 $2,697,000 $5,315,000 $17,868,000 $27,180,000
8441 CIPP Contract 2017-2020 $300,000 $100,000 $103,000 $0 $503,000
8442 Pump Station Equipment Piping
Replacement-Phasp 2 $36,000 $25,000 $103,000 $436,000 $600,000
8443 Large Diameter Pipeline Inspection
Program $200,000 $50,000 $515,000 $1,030,000 1 $1,795,000
8444 Force Main Inspection Program $75,000 $50,000 $0 $0 $125,000
8445 North OrindaSewer Renovation-
Phase 7 $636,000 $3,731,000 $0 $0 $4,367,000
8446 Lafayette Sewer Renovation-Phase
12 $636,000 $3,397,600 $0 $0 $4,033,600
9M7 Pump Station Security Improvements $131,000 $25,000 $51,500 $360,500 $568,000
8448 Manhole Modifications $400000 $300,000 $309,000 $1,236,000 $2,245,000
8M9 Collection System Modeling Support $100,000 $100,000 $103,000 $206,000 $509,000
8450 Development Sewerage Support $400000 $250000 $309,000 $1,236,000 $2,195,000
8451 Collection System Sewer Renovation
Phase 1 $50,000 $2,612,527 $18,181,540 $35,535,000 $56,379,067
TBD Pump Stations Upgrades-Phasel $0 $50,000 $907,000 $24,663,000 $25,620,000
Total Program $9,877,417 $19,347,000 $26,103,040 $82,982,500 $138,309,957
s -
5
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 15 of 51
Page 7 of 14
FY 2018-19
TREATMENT PLANT (TP) PROGRAM
MAJOR PROJECTS FOCUS
Rehabilitation and Replacement:
• Headworks Screenings Upgrade (Construction)
• Piping Renovation - Phase 9 (Construction)
• Equipment Replacement (Construction)
• Solids Conditioning Bldg. Roof Replacement (Construction)
• Plant Operations Building Seismic Upgrade (Construction)
• Plant Control System 1/0 Replacement (Construction)
• Mechanical & Concrete Renovations (Design and Construction)
• Solids Handling Facility Improvements (Final Design)
• Energy Recovery and Blower Replacement (Planning and
Pre-Design); retitled from Aeration and Energy Upgrades
Ultraviolet Disinfection Repairs
., No new projects
6
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 16 of 51
Page 8 of 14
FY 2018-19 TP PROGRAM
TOTAL ESTIMATED COSTS PER PROJECT
FY 2018 19 FY 2019 20 Future FY Total'-"dPump 9,Blower Building Seismic
7291 U rade $6,582,000 $0 $0 $0 $6,582,000
7292 Switch ear Refurbishment-Phase2 $770,000 $200,000 $226,600 $0 $1,196,600
7304 PLCs s[emsU rades $575,000 $110,000 $113,300 $226,600 $1,024,900
Ti15 A lied Research&Innovations $557,274 $3W,000 $515,000 $1,000,000 $2,402,274
Plan[Co.
[rol System Network
M7 U rades $330,000 $100,000 $0 $0 $430,000
7320 Plant Energy0 timiaation COGen $1,094,000 $0 $0 $0 $1,094,000
7322 Fire ProtectionSystem-Phase2 $1,406,000 $0 $0 $0 $1,406,000
7326 E ui ment Replacement $1,166,000 $250,000 $0 $0 $1,416,000
7327 Headworks Screenin sU rade $8,144,000 $76,000 $0 50 $8,220,000
Influent Pump Electrical
7328 Im rove mens $100,000 $510,000 $1,380,000 $2,758,000 $4,748,000
7329 1 Furnace Burner Upgrades $220,000 $0 $0 $0 $220,000
7330 Pi in Renovation-Phase9 $2,566,000 $614,000 $0 $0 $3,180,000
Plant Control System I/O
7339 Replacement $470,000 $900,000 $1,133,000 $1,839,000 $4,342,000
Walnut Creek/Grayson Creek Levee
7341 Rehab $100,000 $0 $515,000 $515,000 $1,130,000
Solids Handling Fadlity
7348 Improvements $4,975,000 $5,715,000 $11,130,000 $60,280,000 $82,100,000
Energy Recovery and Blower
7349 Replacement $300,000 $1,200,000 $3,713,000 $54,937,000 $60,150,000
7351 Nlechaniral and Concrete Renovations $1,300,000 $3,000,000 $3,OO,. $0 $7,3W,000
7352 WDisinfeRionU rades $0 $SW,OW $300,000 $300,000 $1,100,000
n53 Outfalllm rovements-Phase 7 $0 $400,000 $2,240,000 $1,812,000 $4,452,000
Treatment Plant Security
n3 Im ravements $87,000 $00,000 $788,000 $915,000 $1,840,000
n55 Odor Cont.IU rades-Phasel $44,000 $2W,OW $824,000 $2,935,000 $4,W3,000
7357 Plant-Wide Instmmentation Upgrades $100,000 $190,030 $515,000 $1,236,000 $2,041,000
7358 Innovative Renewable Energy Project $300,000 $0 $100,000 $20),000 $600,000
Solids Conditioning Building Roof
7359 Replacement $500,000 $800,030 $0 $0 $1,300,000
7360 Existin Plant Faci lubes As-ISDrawin s $100,000 $100,0`0 $103,000 $51,500 $354,500
Plant Operations Building(POB)
7362 Seismic Upgrades $400,000 $1,100,000 $1,030,000 $0 $2,530,000
7363 Treatment Plant Planning $450,000 $450,030 $566,500 $1,133,000 $2,599,500
Treatment Plant Safety Enhancement
ases $0 $100,000 $100,000 $0
7364 Ph $200,000
Total Program $32,636,274 $16,865,000 $28,292,400 $130,168,100 $207,961,774 -
7
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 17 of 51
Page 9 of 14
FY 2018-19
GENERAL IMPROVEMENT (GI) PROGRAM
MAJOR PROJECTS FOCUS
Asset Management Program:
Continue Program Management Information System (PMIS)
Implementation
IT Development:
Enterprise Resource Planning (ERP) Improvements
Infrastructure Improvements
Cyber Security
Building Improvements:
Server Room Relocation (Construction)
Security and Public Facilities Improvements (Design)
s
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 18 of 51
Page 10 of 14
FY 2018-19 GI PROGRAM
TOTAL ESTIMATED COSTS PER PROJECT
TotalProject Project Jget-to- FY 2018-19 FY 2019-20 Future FYs .
Number Date Cost
8207 General Security and Access $194,616 $500,000 $103,000 $103,000 $900,616
Geographic Data Integration(GDI)
8227 Treatment Plant $425,000 $0 $0 $0 $425,000
8230 Capital Legal Services $158,665 $20,000 $20,600 $41,200 $240,465
8236 District Easement Acquisition $208,047 $50,000 $51,500 $103,000 $412,547
Asset Management Program
8238 Development $2,969,185 $400,000 $0 $0 $3,369,185
Information Technology(IT)
8240 Development $2,148,794 $1,750,000 $2,420,500 $1,005,500 $7,324,794
8243 Server Room Relocation $955,430 $880,000 $0 $0 $1,835,430
8247 Property and Building Improvements $400,000 $300,000 $257,500 $1,030,000 $1,987,500
8248 Cyber Security $75,000 $0 $103,000 $309,000 $487,000
8516 Equipment Acquisition $676,000 $200,000 $206,000 $1,030,000 $2,112,000
8517 Vehicle Replacement Program $1,199,000 $650,000 $772,500 $3,862,500 $6,484,000
otal Program $9,409,737 $4,750,000 $3,934,600 7,484,200 25,578,537
9
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 19 of 51
Page 11 of 14
FY 2018-19
RECYCLED WATER (REW) PROGRAM
MAJOR PROJECTS FOCUS
Rehabilitation and Replacement:
Filter Plant and Clearwell Improvements (Pre-Design)
Planning:
• Zone 1 Recycled Water System (Ongoing program)
• ReW Distribution System Renovations (Planning)*
• Surge Tank (Pre-Design)
*New Project
10
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 20 of 51
Page 12 of 14
FY 2018-19 RECYCLED WATER (REW) PROGRAM
TOTAL ESTIMATED COSTS PER PROJECT
Total,Project . -
Number roject FY 2019-20 Future FYs Cost
7306 Zone 1 Recycled Water $497,894 t$35,000 $51,500 $103,000 $687,394
7346 Recycled Water Distribution SystemSurge Analysis $155,000 00 $0 $0 $205,000
7361 Filter Plant&Clearwell Improvements
$330,000 $2,457,000 $8,180,000 $11,393,000 $22,360,000
7365 ReW Clearwell Repairs $1,400,000 $300,000 $0 $0 $1,700,000
TBD* ReW Distribution System Renovations $0 $15,000 $60,000 $600,000 $675,000
Program
Total Program $2,382,894 $2,857,000 $8,291,500 $12,096,000 $25,627,394
* New Project
11
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 21 of 51
Page 13 of 14
TEN-YEAR CAPITAL IMPROVEMENT PLAN (2018-2028)
$806 MILLION (M) TOTAL
Treatment Plant ($428 M)
• Liquid Treatment Process $ 185 M
• Solids Handling Process Treatment $ 97 M
• General Projects/ Safety/ Regulatory $ 146 M
Collection System ($309 M)
• Replacement and Rehabilitation $ 210 M
• Pumping Stations $ 60 M
• Regulatory Compliance $ 36 M
• CAD's and Developer Sewers $ 3 M
General Improvements ($25 M)
• IT Development $ 11 M
• Vehicles and Equipment $ 9 M
• Buildings/ Properties/ Others $ 5 M
Recycled Water($24 M)
• Filter Plant and Clearwell $ 23 M
Distribution and Zone 1 $ 1 M
CIP Contingency ($20 M)
12
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 22 of 51
Page 14 of 14
QUESTIONS
41.
CENTRALSAN
..._,, ,.
----
13
May 7, 2018 Special EOPS Committee Meeting Agenda Packet- Page 23 of 51