Loading...
HomeMy WebLinkAbout03.b. Review draft Position Paper to authorize the General Manager to amend an existing agreement with V.W. Housen and Associates under the Pump Station Upgrades Project, District Project 8436, to include final design services for the Moraga, Orinda Cros Page 1 of 25 Item 3.b. CENTRAL SAN BOARD OF DIRECTORS ' POSITION PAPER DRAFT MEETING DATE: APRIL 25, 2018 SUBJECT: REVIEW DRAFT POSITION PAPER TO AUTHORIZE THE GENERAL MANAGER TO AMEND THE EXISTING AGREEMENT WITH V.W. HOUSEN AND ASSOCIATES UNDER THE PUMP STATION UPGRADES PROJECT, DISTRICT PROJECT 8436, TO INCLUDE FINAL DESIGN SERVICES FOR THE MORAGA, ORI NDA CROSSROADS, AND FLUSH KLEEN PUMP STATIONS ATA COST NOT TO EXCEED $2.2 MILLION. SUBMITTED BY: INITIATING DEPARTMENT: AMANDA SCHMIDT, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES- CAPITAL PROJECTS REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL SERVICES ISSUE Board of Directors' (Board) authorization is required for the General Manager to execute an amendment to a professional engineering services agreement for amounts greater than 15-percent of the original agreement amount. BACKGROUND In 2015, Capital Projects initiated an evaluation of the Moraga and Orinda Crossroads Pump Stations at the request of Operations due to several deficiencies with the standby power engine driven systems, electrical and instrumentation concerns, and other equipment identified for near term replacement. The most impactful item identified was replacement of the 1,000-horsepower Waukesha diesel engines (circa 1959) at both stations. The Comprehensive Wastewater Master Plan (CWMP) identified several structural, mechanical, electrical, and instrumentation improvements needed at the Martinez, Fairview, Maltby, and Flush Kleen Pump Stations. These stations have multiple concerns, including reliability of existing equipment and infrastructure, corrosion, are prone to flooding, and have some pumping capacity limitations. Central San staff decided to package these stations with Moraga and Orinda Crossroads to form one all-encompassing pumping station project, which has been included in the current Capital Improvement Budget (CI B)titled Pump Station Upgrades, District Project 8436 (Project). April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 19 of 72 Page 2 of 25 On July 20, 2017, the Board authorized the General Manager to execute an agreement with V.W. Housen and Associates (VW HA)for the predesign of the Project at a cost not to exceed $780,000. The predesign work consisted of numerous field investigations, workshops, meetings (with Operations, Maintenance, and Capital Projects staff), facility tours, and other important efforts to comprehensively evaluate and recommend solutions. The preliminary design included seven elements: Moraga and Orinda Crossroads "All Electric" Option Evaluation; Hydraulic Analysis; Electrical, Instrumentation & Controls (I&C)Assessment; Evaluation to Eliminate Fairview Pump Station; Corrosion Assessment; Heating, Ventilation and Air Conditioning (HVAC)Assessment; and Flood Risk Assessment. Project delivery options and construction sequencing were also included in the preliminary design. These elements form the basis of design for the Project. The following is a summary of the predesign work and the recommendations for final design. Moraga and Orinda Crossroads Pump Stations Moraga Pump Station, originally installed in 1959, is located in a residential area of Moraga. Orinda Crossroads Pump Station is located in downtown Orinda next to Theater Square. These stations were installed at the same time and are nearly identical in design and features. They have gone through several upgrades, with the most recent renovation in 2000. The stations consist of three dry weather electric pumps and two wet weather diesel engine driven pumps. Central San staff identified the need to replace the Waukesha diesel engine (circa 1959) and hired VW HA to assist in the project and prepare a basis of design report with options to replace the engine and other station improvements. During the Basis of Design phase, it was determined that an "all-electric" option warranted consideration prior to committing to replacement of the Waukesha engine and engine controls, generator installation, and other capital improvements. The Preliminary Design Report (PDR), completed in February 2018, includes an "all-electric" evaluation that includes the following alternatives at both stations: Option 1: Keep Engines; Option 2:All-Electric; and Option 3:All-Electric Hybrid. The All-Electric Hybrid Option implements the "all-electric" option by installing one electric wet weather pump under the initial project but defers the replacement of the 20-year old Caterpillar diesel engine/pump with the second electric wet weather pump to a future project. Option 2 (All-Electric) is the preferred option at both stations for multiple reasons: it minimizes future requirements associated with escalating Bay Area Quality Management District (BAAQMD) regulations for diesel engines, it eliminates additional foreseeable wet weather pumping future upgrades and improves pumping transitions and low flow operations. The conversion to all electric pumping was implemented successfully at Lower Orinda Pump Station in 2003. To increase resiliency, the dry weather pumps will be replaced with drypit submersible pumps. Electrical improvements include a new generator sized to pump buildout peak wet weather flows (PW W F), new PG&E service, motor control center, configuration of breakers to allow for operator servicing, and implementing ArcFlash safety requirements.Additional surge protection is necessary and requires larger surge tanks and associated piping. HVAC needs will be addressed; there have been instances where electrical equipment has overheated. The corrosion assessment identified particular piping that needs to be rehabilitated or replaced within the station. In January 2018 at Moraga Pump Station, a leak was detected in a spool pipe between the wetwell and Caterpillar diesel wet weather pump.An immediate repair was completed as a change order on a capital project. At Moraga Pump Station, grinders will be installed to address the ongoing maintenance caused by rags. Flush Kleen Pump Station April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 20 of 72 Page 3 of 25 Flush Kleen Pump Station is one of Central San's oldest pump stations, originally built in 1950. Certain electrical, instrumentation and controls equipment are obsolete and replacement parts cannot be obtained from manufacturers. The Electrical, I&C assessment recommended replacing the standby power generator, automatic transfer switch, electrical service, and power distribution. It is recommended to install two new drypit submersible constant speed pumps. The new pumps will allow buildout PW W F to be pumped through a single forcemain and will allow for larger solids to be passed at low flows. Drypit submersible pumps will provide increased resiliency at the station. It is recommended to replace piping and valves located in the drywell. The corrosion assessment recommended replacing 6- inch discharge piping exiting the valve vault wall and investigating the extent of lead paint found on the wall of the drywell and within the station. Supervisory Control and Data Acquisition (SCADA)Architecture Assessment and Security Improvements A SCADA architecture assessment was a recommendation from the Preliminary Design Report and will be completed in the final design scope of work. The SCADA assessment includes an evaluation of the existing overall architecture including the pump station programmable logic controllers and their integration with the SCADA control system at the wastewater treatment plant. This assessment will be completed for all stations and recommendations will be implemented in the final design of Moraga, Orinda Crossroads, and Flush Kleen Pump Stations. Central San recently completed a security assessment of all facilities. Recommendations such as access control, intrusion detection, and surveillance will be included in the final design of Moraga, Orinda Crossroads, and Flush Kleen Pump Stations. Flood Protection Evaluation: Orinda Cross Road Pumping Station During the preliminary design phase of the Pump Station Upgrades Project, a flood risk assessment was performed for the six pump station sites included in the Project. The flood risk assessment includes information on the purpose and scope of the assessment, regulatory requirements, sea level rise estimates, findings, and flood protection and sea level rise protection recommendations for each station, where applicable. The assessment concluded that the Orinda Crossroads Pump Station is located within a 100-year flood area but is not tidally influenced or susceptible to sea level rise. The assessment indicates that the Orinda Crossroads Pump Station could experience flooding from San Pablo Creek. Just southeast of the pump station, the San Pablo Creek has been encroached by a concrete box culvert with inadequate capacity to convey the entire one-percent annual chance of flood.As a result, flood waters back up and begin to pond in the lowest area under the California State Route 24 overcrossing resulting in ponding at the pump station. A key subconsultant to VW HA, HDR, I nc. will be tasked to verify that the effective Federal Emergency Management Agency(FEMA) Flood Insurance Rate Map along San Pablo Creek in the vicinity of the Orinda Crossroads Pump Station is modeled appropriately and mapped accurately based upon the modeling results. The work performed will include data collection and hydraulic model/mapping review. The findings and recommended next steps will be presented and discussed at a future meeting. Recommended next steps may include guidance to proceed forward with flood protection; or recommended model revisions necessary to update the hydraulic model to revise mapping; or guidance to submit a Letter of Map Revision (LOMR)to FEMA for a proposed change. The predesign also evaluated the three pumps stations located in Martinez: Martinez, Fairview, and Maltby Pump Stations. Final design for these three pump stations will be started in two years. Martinez Pump Station is at the site of the former City of Martinez wastewater treatment plant. It is the first station that pumps in a chain (to Fairview and then to Maltby)to the Central San wastewater treatment plant. April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 21 of 72 Page 4 of 25 Some mechanical and electrical improvements are recommended at the Martinez Pump Station. However, the predesign recommends the construction of new pump stations for Fairview and Maltby. For the Fairview site, the new station would require the acquisition of a portion of a parcel owned by the City of Martinez (former right-of-way). These alternatives would increase reliability and improve resiliency and are more favorable for construction. Central San staff feels that land acquisition is critical to moving forward with an alternative and design work. For the Maltby site, the construction of a new pump station would require the acquisition of a portion of a parcel to the north, currently owned and occupied by Rethink Green. Central San believes the site may be contaminated since it was used in the past for storage of wood products. Properties on other sides of the station are less desirable due to previous use or topography. Central San staff feel that additional information about the availability and suitability of the Rethink Green property is needed before moving forward with design. The land acquisition presentation and discussion will be taken to the Real Estate, Environmental and Planning Committee. Concord Main Metering Station The existing venturi meter was installed in 2010 and measures 80-percent of the flow from the City of Concord (City). The City has at times expressed concerns about the accuracy of the meter. Staff initiated a study on the existing metering system and the analysis indicates that a new magnetic flowmeter would be more accurate and require less maintenance than the existing flowmeter. The sump pump discharge piping will also be relocated to a new tap location for better operations access. I ntrusion monitoring at the facility and a SCADA alarm will be updated to allow better communication with Central San operations staff. The City has agreed to reimburse half of the design costs and staff will be seeking a cost sharing agreement with the City for construction. Schedule Central San staff is recommending phasing the design and construction into two phases under two separate projects to accommodate Central San operations staffing, as well as much of the critical work at the station impacting operations will occur in the dry weather season. Moraga and Orinda Crossroads Pump Stations are in the greatest need of upgrade, are top priority, and will be done under Phase 1. Design for Moraga, Orinda Crossroads, and Flush Kleen Pump Stations is scheduled to be 12 months in duration, starting in July 2018. Also based on the similarities between the Moraga and Orinda Crossroads Pump Stations and locations of those stations, staff plan to construct the Moraga, Orinda Crossroads, and Flush Kleen Pump Stations under one project. Central San staff feels more information is needed to move forward with the final design at the Martinez, Fairview, and Maltby Pump Stations. Because the operation of Martinez Pump Station is so integral to those stations, staff plans to construct these pump stations together under Phase 2. This will allow time for land acquisition to determine the California Environmental Quality Act (CEQA) needs prior to the start of design. Staff plans to come back to the Board with a contract amendment with VW HA to design the Martinez, Fairview, and Maltby Pump Stations in 2019. CEQA: At its July 20, 2017 meeting, the Board independently found that the agreement with this vendor was exempt from CEQA under Central San's CEQA Guidelines Section 15262, since it allowed for further planning and feasibility studies for possible future actions which Central San has not approved, adopted, or funded, and the outcome of these tasks will not have a legally binding effect on later activities. Central San will conduct an environmental evaluation of any capital project that is proposed in the future as a result of the tasks authorized herein to determine the need for any additional CEQA documentation. April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 22 of 72 Page 5 of 25 ALTERNATIVES/CONSIDERATIONS An alternative would be to postpone the design or design each station improvement as separate projects, which is not recommended due to the project drivers and design complications previously noted above, and the associated increase in overall project costs in implementing multiple projects over a long period of time. Although the proposed CI B and current budget have adequate cash funding for the final design, it is anticipated that Central San will most likely request bond financing to construct these improvements. This decision will be presented at a future Board Meeting and no action is required at this time. FINANCIAL IMPACTS The VW HA final design services for the Project Phase 1 is estimated at$2.2 million. The total VW HA agreement cost ceiling is estimated at$2.98 million ($780,000 for pre-design, and $2.2 million for final design), which is approximately 11-percent of the $27.2 million total estimated project cost for Project Phase 1 and the Concord Metering, as detailed in Attachment 1. The Project is listed in the Fiscal Year(FY) 2017-18 CI B on page 131 with an estimated budget of $450,000 for planning, $2,596,000 for design, and $30,389,000 in construction. The final design will span this fiscal year and next fiscal year. The Project Phase 1 and Phase 2 will be detailed, updated, and included in the FY 2018-19 Cl B. The Financial I mpact Table was not included since no budget transfer is required to fund this Project. There are adequate funds within the current and following year Cl B for the design of the Phase 1 Project. COMMITTEE RECOMMENDATION The Engineering and Operations Committee reviewed this agreement amendment at the April 25, 2018 meeting and recommended approval to include final design services for the Pump Station Upgrades Project. RECOMMENDED BOARD ACTION Authorize the General Manager to amend the existing V.W. Housen and Associates Agreement, Agreement 045460, in an amount not to exceed $2.2 million for the Pump Stations Upgrades Project, District Project 8436, Phase 1 Scope of Work. GOAL TWO: Strive to Meet Regulatory Requirements Strategy 1 - Strive to Achieve 100% Permit Compliance in Air, Water, Land and Other Regulations, Strategy 2- Strive to Minimize the Number of Sanitary Sewer Overflows GOAL FIVE: Maintain a Reliable Infrastructure Strategy 2- Facilitate Long-term Capital Renewal and Replacement, Strategy 3- Protect District Personnel and Assets from Threats and Emergencies ATTACHMENTS: 1. Estimated Capital Costs April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 23 of 72 Page 6 of 25 2. Presentation (replaced with revised version) April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 24 of 72 Page 7 of 25 Attachment 1 Pump Stations Upgrades Project - Phase 1 District Project 8436 Estimated Capital Costs of Recommended Improvements Estimated Estimated Total Pump Stations Construction Cost Project Cost Flush Kleen Pump Station $1,292,000 $1,816,000 Moraga Pump Station $9,023,000 $12,684,000 Orinda Cross Road Pump Station $7,997,000 $11,240,000 Concord Main Metering Vault Improvements (*) $720,000 $950,000 Total Project Cost $19,032,000 $26,690,000 Security Improvements $150,000 $210,000 Pump Stations SCADA Architecture Improvements $200,000 $280,000 Total Project Cost $19,382,000 $27,180,000 (*) Cost to be shared 50-percent with City Concord per Agreement April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 25 of 72 Page 8 of 25 Item 3.b. (Handout) PUMP STATION UPGRADES Engineering and Operations Committee April 25, 2018 Jean-Marc Petit,Director of Engineering and Technical Services Edgar Lopez,Division Manager,Capital Projects _ •- Amanda Schmidt,Associate Engineer Capital Projects Division Presentation Agenda n� Drivers rymPSHWn \ „ Preliminary Design Fi� Project Scope and Approach J Project Phasing and Schedule Project Budget j Recommendations 1 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 26 of 72 Page 9 of 25 1 . PROJECT BACKGROUND AND DRIVERS ee�m,a irl--1 Hill M,rtme: ■ 8 n�dttl e�l, COLLECTION SYSTEM loll o ■W ,3 Berk ay PUMPING STATIONS �a,,,,d, ° FT ri-.H. (PS) Oa klpntl O,mww � Ny I Treatrnem rwatana rvxwcws c u'woe Fsiiiry ff1 Pmafety Oxnetl wmpiop Smoon l re GCGSp Punpinp Stations mmem Iseneremeinlmmaialm� vu nd A yyy, W muenwn rot 3]9, d a� 3oom arami by HHI.- w a ry 2 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 27 of 72 Page 10 of 25 PROJECT BACKGROUND � o flu hanan Clyde Concord � tyres, lndus[r,a! &uhanin Falmiew a 0 saurh Maltby o _Q a Rop, l'� Mar[in•z rrea*mrn�Plank Moray 5 Bates Q D San Raman 0—da. O Crossroads p o 41inda Acacia sleepy Hollow � O Wagner Flush RAnch . lee ORINDA CROSSROADS PUMP STATION • Largest Pump Station for Central San I r • Major Concerns: • Very tight site • Located in very busy downtown commercial area in Orinda • Diesel Engines on wet weather pumps �,► • Consider wet weather pump r- replacement? _. Electrical, instrumentation and controls improvements and upgrades • Existing electrical equipment issues (overheating) • Evaluate back-up power I � • Evaluate adequacy of surge protection ; kA .� 3 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 28 of 72 Page 11 of 25 MORAGA PUMP STATION • Major Pump Station: Second largest PS for Central San • Major Concerns: • Located in residential neighborhood t:r - near a school and creek • Diesel engines on wet weather - - pumps • Consider wet weather pump 1 �' replacement? ' ' • Electrical, instrumentation and r controls improvements and upgrades • Existing electrical equipment issues • Evaluate back-up power • Evaluate adequacy of surge protection • Evaluate installation of mechanized grinders (currently manual cleaning) - PRELIMINARY DESIGN FOR FAIRVIEW AND MALTBY • All pumps reported in operation at Maltby and Fairview Pump Stations during 2016/2017 wet weather Martinez PS Fairview PS Maltby PS • Master Plan reduced buildout PWWF by 17% • 2016/2017 worst case storm < 10-year, 24-hour storm 201601 7 Worst Case 24 • Hydraulic analysis will determine == 'A"M1=3.06 inches {� required upgrades to meet reliable firm capacity for buildout PWWFs - Mote:14year,24-hour storm=3.51 inches at Martinez VWVM I 4 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 29 of 72 Page 12 of 25 2. PRELIMINARY DESIGN FINDINGS T � DESIGN SERVICES ox� FOR PUMP STATION District Project 8436 .:P• n UPGRADES unp wem r 3� Draft Preliminary Design Report Review Meeting �mpsW on Warr • V.W.HOVSEN L 1rCSi ne engi veering January 24,2018 �jC •^�Imo' I 5 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 30 of 72 Page 13 of 25 PUMP STATION UPGRADES PROJECT PDR OVERVIEW—TABLE OF CONTENTS Draft Preliminary Design Report Executive Summary Introduction .� aDESIGN SERVICES Reliability and Redundancy Critena -- "+ ° .—.,- 46 Facilities -" FOR PUMP Martinez Pump Station .µ STATION D,-ict P+oj,CI 5d 35 Fairview Pump Station UPGRADES Maltby Pump Station o�� araR Preliminary Design Report Reriew Meelirtg Flush-Kleen Pump Station Concord Main(South)Metering Stationnuary 2e,201E .x- �-- r Momga Pump Station Dnnda Crossmads Pump Station Pmject Implementation Strategy Pmject Design and Construction Schedule _ 'I FLOOD PROTECTION/ SEA LEVEL RISE V- _m __ Pump Flooding Potential at Site Sea Level Rise Station (Proleded Water Surraoe Elevation NAVD , FEMA FEMA Notes +30 +50 +100 Flood years years years Hazard Zone Maflree PE Whn100ymfloodplan(l%vd)ablityd0opfrgeayy�,, 115 126 16.6 Zane AE=HJrnskv Nati re Flood ligfxrs Rogan) Mflbj A Wfl1n10Dyeaflaodplan(1%vc litydflo irgaayy • 11.5 12.6 16.6 Zore A=H�nskrrtla Nar'ma Fbo]I�.rxxx Ragan) _– – FarAev X hyace W10D1fl O edoain(l%polaltiliyorfloodrge y 115 126 16.6 – – ----- yea•ZaneAE=HJinskala Ns ptnl FkodIrs—e Ro3an) _ RSA X Msded FQvWflaotl haavd rune - - - _ _ f• ween – — Maaga X AdlaedW 100y,sfl-I0an(1%pdbs!i1ityoffloadrgee, - - - y ,Z—ne Hfr n*a Na"Flood Ins—e Rwm) CnMa AH Wnnloly fi-pan(1%pd lily'dfl gea yea. Oosced wlh9-Abvflaair9lPnndn3)kith depOsdl-3fe3dd'{N) I 6 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 31 of 72 Page 14 of 25 3. PROJECT SCOPE AND APPROACH w 3. Project Scope and Recommendations A. MORAGA AND ORINDA PUMP STATIONS 7 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 32 of 72 Page 15 of 25 MORAGA AND ORINDA CROSSROADS PS EVALUATED ENGINE VS. ALL ELECTRIC OPTIONS • Recommending All Electric: • New PG&E service • VFDs for wet weather pumps • Larger standby generators oil • Reliability „ • Redundancy • ResiliencyI � 1 "ALL ELECTRIC" WET WEATHER PUMP ALTERNATIVES AT ORINDA CROSSROADS AND MORAGA PS INCLUDE: Reuse of Existing Morris IIS fl► 1k AA Am-do Pump Casings with Smaller Impellers and New 700 HP ' Horizontal Electric Motors Least Cost Alternative •�f'� 1 f � Y ® 16 Install New Dry Pit } � Submersible Electric Pumps Provides Increased Resiliency Moraga Pump Station 3D Visualization 8 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 33 of 72 Page 16 of 25 4. PROJECT PHASING AND SCHEDULE PHASING OF RECOMMENDATIONS • Phase 1: • Orinda Crossroads PS • Moraga PS • Flush Kleen PS • Concord Metering Vault Improvements • Phase 2: • Martinez PS • CEQA on Fairview and Maltby PS 9 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 34 of 72 Page 17 of 25 PHASING OF RECOMMENDATIONS • Phase 1: • Orinda Crossroads PS • Moraga PS • Flush Kleen PS • Concord Metering Vault Improvements • Phase 2: • Martinez PS • CEQA on Fairview and Maltby PS - -0, MORAGA-ORINDA PUMP STATIONS • Facilities deliver majority of wastewater flows from Orinda and Moraga and are critical facilities (daisy chain for Orinda Flush Kleen Crossroads) ` • Moraga and Orinda Crossroads �rinda , PS need the following upgrades: crossroads • Electrical upgrades Moraga • Instrumentations and controls • Standby power • Wet weather pumps: • Pumping capacity • Conversion to electric driven pumps - 10 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 35 of 72 Page 18 of 25 PHASING OF RECOMMENDATIONS • Phase 1: • Orinda Crossroads PS • Moraga PS • Flush Kleen PS • Concord Metering Vault Improvements Phase 2: • Martinez PS • CEQA on Fairview and Maltby PS MARTINEZ AREA PUMP STATIONS • Facilities deliver all wastewater flow from Martinez and are critical ,�y facilities (daisy chain) • Maltby and Fairview PS need work: • O&M access 'Martinez • Drywell show signs of F•[Mew corrosion • Potential wet weather Treatment Plant capacity issues 11 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 36 of 72 Page 19 of 25 MARTINEZ PUMP STATION ALTERNATIVE RECOMMENDATION Implementation of Alternative 2 — New Drywell Submersible Wet Weather Pumps Include in Phase 2 to coincide with Fairview and Maltby PS upgrades 0010L FAIRVIEW AND MALTBY PUMP STATIONS Hydraulic Analysis Corrosion Assessment Flood Risk Assessment Pump Station Alternatives Alt 1 - Rehabilitate Existing Pump Station Alt 2 - Construct New Drywell/Wetwell Pump Station Alt 3 - Construct New Submersible Pump Station 12 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 37 of 72 Page 20 of 25 FAIRVIEW PUMP STATION IMPROVEMENTS Major Improvements: Replace Pump Station Electrical, instrumentation and controls improvements and upgrades - Redundancy: All three pumps operating during winter 2017 wet weather Considered elimination but not _ recommending that alternative F FAIRVIEW PUMP STATION ALTERNATIVE RECOMMENDATION Include in Phase 2 since existing pumps were rebuilt in 2016 and need to evaluate CEQA process Prior to the design phase of the project, a portion of the parcel to the north of the existing site currently owned by City of Martinez shall be evaluated and obtained by Central San for the Fairview Pump Station Proceed with CEQA I. 13 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 38 of 72 Page 21 of 25 MALTBY PUMP STATION I • Largest of the three Martinez stations • Major concerns: • Very tight site • Electrical, instrumentation and - controls improvements and upgrades • Replace pumping station • Outdated electrical systems • Corrosion issues of metal cans • Difficult access i • Redundancy:All three pumps :Ir operating during winter 2017 wet weather MALTBY PUMP STATION ALTERNATIVE RECOMMENDATION • Include in Phase 2 since existing pumps were rebuilt in 2016 and need to evaluate CEQA process • Prior to the design phase of the project, a portion of the parcel to the north of the existing site currently owned by Rethink Green shall be evaluated for potential contamination and obtained by Central San for the Maltby Pump Station • Proceed with CEQA 14 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 39 of 72 Page 22 of 25 CONCORD METERING VAULT • This flow meter measures ' 80% of City of Concord flows • Recent meter study recommended replacement to improve accuracy �v • Corrosion 1 pw PUMP STATION UPGRADES PROJECT PROJECT DESIGN, BID,AND CONSTRUCTION SCHEDULE ANY �4� �M G�ww Np4 Ynn•r�Yn W/yp FI�pYCq� 1b fin• - F� •ucnm Fx•� �l II�W� WYfat+�n4 erq^Fw� - M•nM1q EZ nFiwf viwq Pn�lF�vbk.�wmr aprr�ry 15 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 40 of 72 Page 23 of 25 5. PROJECT BUDGET PUMP STATION UPGRADES PROJECT PHASE 1 PRELIMINARY CONSTRUCTION COST ESTIMATES Pump Stations Upgrades Phase 1 Estimated �Estimated Project Cost Construction Cost Flush Kleen Pump Station $1,292,000 $1,816,000 Moraga Pump Station $9,023,000 $12,684,000 Orinda Cross Road Pump Station $7,997,000 $11,240,000 Concord Main Metering Vault(*) $720,000 $950,000 Total Project Cost $19,032,000 $26,690,000 Security Improvements $150,000 $210,000 PS SCADA Architecture Improvements $200,000 $280,000 Total Project Cost $19,382,000 $27,180,000 (')50-percent cost share with City of Concord per Agreement—In progress In 2018 Dollars 16 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 41 of 72 Page 24 of 25 DESIGN BUDGET FOR PHASE 1 DISTRICT PROJECT 8436 Consultant (VWHA and Others) • Preliminary Design Services: $780,000 • Final Design Phase 1: $2,200,000 Staff and Operations (Planning and Design) • Coordination, Project Management, Bidding, etc.: $720,000 Construction • Contractor, Construction Management, Contingency: $23,480,000 6. RECOMMENDATIONS 17 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 42 of 72 Page 25 of 25 RECOMMENDED BOARD ACTIONS • Staff recommends that the Board authorize the General Manager to include final design services with V.W. Housen and Associates in an amount not to exceed $2.2 million for the Pump Station Upgrades Project- Phase 1, District Project 8436 00elo I�11*1114 ' QUESTIONS -1: 18 April 25, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 43 of 72