Item 11.
CENTRAL SAN BOARD OF DIRECTORS
' POSITION PAPER
MEETING DATE: MAY 3, 2018
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $748,008 TO
PLATINUM ROOFING, INC., THE LOWEST RESPONSIVE BIDDER FOR
THE SOLIDS CONDITIONING BUILDING ROOF REPLACEMENT,
DISTRICT PROJECT 7359; CONSIDER EXEMPTION FROM THE
CALIFORNIA ENVIRONMENTAL QUALITYACT (CEQA); AND AUTHORIZE
UP TO A 15-PERCENT CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
NATHAN HODGES, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Y.
,�_.
Roger S. Bailey
General Manager
ISSUE
On April 17, 2018, eight sealed bids were received and opened for the construction of the Solids
Conditioning Building Roof Replacement, District Project 7359 (Project). The Board of Directors (Board)
must award the contract or reject all bids within 50 days of the bid opening. Authorization is also required
for the General Manager to execute the Contract Documents subject to submittal requirements and
include up to a 15-percent contingency.
BACKGROUND
The Solids Conditioning Building (SCB) roof was constructed in the mid 1970's. During wet weather
May 3, 2018 Regular Board Meeting Agenda Packet- Page 80 of 225
Page 2 of 6
conditions, the SCB roof experiences significant leakage. Some of the leakage is overcritical electrical
equipment. Failure of this equipment could result in significant disruptions to operations as well as create
safety hazards. There are also several other critical assets in this building, including one of the two plant
control rooms. Over the last 10 years, several repairs have been made to repair significant leaks; however,
the entire roof is in poor condition and requires replacement. The roof is over 40 years old and the useful
life of a tar and gravel roof is in the order of 20 to 30 years. Temporary measures have been implemented
to protect the electrical equipment from water damage; however, a roof replacement is needed as the
long-term solution.
This Project will replace the existing built-up tar and gravel system with a membrane roofing system, install
new roof drains and piping for poor drainage locations, remove decommissioned exhaust stacks, and
replace flashing and sheet metal.
Additional scope of work items, including coating, relocation and installation of electrical and networking
conduits, installation of fall protection systems, modification to steam lines, and demolition of a natural gas
line, will be completed separate from the roofing work. These items are relatively minor and, if included in
the roofing scope of work, would require a general engineering contractor. In order to obtain the best cost
for roofing, staff has elected to complete the non-roofing scope items separately. Work will be coordinated
with the roof installation schedule.
Central San staff, along with Calpo, Hom, and Dong Architects, and TJ C and Associates Inc., prepared
the plans and specifications for the Project. The Engineers estimate for construction was $1,000,000.
This Project was advertised on March 30 and April 4, 2018. Eight sealed bids ranging from $748,008 to
$1,215,500 were received and publicly opened on April 17, 2018. The Capital Projects Division
conducted a technical and commercial review of the bids and determined that Platinum Roofing, Inc.
(Platinum) is the lowest responsive and responsible bidder.A summary of bids received is shown in
Attachment 2.
Central San will administer the construction contract and provide contract administration, inspection, office
engineering, and submittal review. Consultant inspection and engineering services will be used to
supplement staff as needed under existing Capital Projects As-Needed Agreements.
On April 23, 2018, the second lowest bidder, Exbon Development, Inc. (Exbon), submitted a timely
protest claiming the bid submitted by Platinum contained material defects. After staff's independent review
of the protest and the response provided by Platinum, it was determined that Platinum's bid was
responsive and did not contain any material defects.As of April 25, 2018, Exbon provided a verbal and
written notification that their protest has been withdrawn.
C Ems, A:
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15301, since it involves minor alterations to existing public facilities involving no expansion of use, and
CEQA Guidelines Section 15302, since it involves replacement of existing public facilities at the same
location and with the same purpose.Approval of this Project will establish the Board's independent finding
that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Roofing contractors are in very high demand and securing a contractor this dry weather season is
necessary. The existing S C B roof is past its useful life and is in need of replacement before the next wet
weather season.
FINANCIAL IMPACTS
May 3, 2018 Regular Board Meeting Agenda Packet- Page 81 of 225
Page 3 of 6
The total estimated cost for this Project is $1,300,000, which includes design, bid, contingency,
inspection, construction management, and other roof modifications. This Project is included in the Fiscal
Year(FY) 2017-18 Cl B on page 170 with a budget of$1,100,000.Additional funding will be included in
the FY 2018-2019 budget to cover the additional funds required to complete the project.
Financial Impact Table: Amount
El Funds budgeted for this project $1,100,000
❑ Funds taken from current FY 2017-18 Cl B contingency $ 0
Funds transferred from current FY 2017-18 projects:
❑ a. Updated forecast; estimated savings from project available $ 0
❑ b.Acceleration of funds for project that is budgeted in future year $ 0
0 c. Combined project scope for bidding purposes:
(District Project 7311, Safety-Phase 4) $150,000
d. Potential future year budget impact
0 (May be mitigated through (1) savings from close-outs of current year $50,000
projects; (2) reprioritizing future year projects; (3) cost savings on
future year projects)
Total Current Year Cost $1,300,000
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the meeting on April 25, 2018, and
recommended approval of this construction contract.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of$748,008 for the construction of the Solids Conditioning
Building Roof Replacement, District Project 7359 to Platinum Roofing, I nc., the lowest responsive and
responsible bidder; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal requirements
and include up to 15-percent contingency.
Strategic Plan Tie-In
GOAL FIVE:Maintain a Reliable Infrastructure
Strategy 2- Facilitate Long-term Capital Renewal and Replacement, Strategy 3- Protect District Personnel and
Assets from Threats and Emergencies
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post-Bid/P reconstruction Estimate
May 3, 2018 Regular Board Meeting Agenda Packet- Page 82 of 225
Page 4 of 6
O \ \
0 200 400 \ \ \ `'\•
FEET \ \ \•%
Basin A South
CONSTRUCTION — \
STAGING AREA = \\\
SOLIDS \�\
NDITIONI
BUILDIN D \\\
PROJECT AREA
SOLIDS CONDITIONING BUILDING i 1
❑ �� I I
o � Oo
Aeration CLA IERS
Tanks (SOUT UAD)
op PRIMARY
3 80 SEDIMENTATION
i
TANKS i
❑ PUMP AND BLOWER
BUILDING
——
o
POD HOB U
0
P�PGE IMHOFF PLACE
Central Contra Costa Solids Conditioning Building Attachment
Y Sanitary District Roof Replacement
A*Mk 1
District Project 7359
Location Map
May 3, 2018 Regular Board Meeting Agenda Packet- Page 83 of 225
Page 5 of 6
ATTACHMENT 2
SOLIDS CONDITIONING BUILDING ROOF REPLACEMENT
DISTRICT PROJECT 7359
SUMMARY OF BIDS
PROJECT NO.: 7359 NO. OF ADDENDA: 0 DATE/TIME: APRIL 17, 2018 /11AM
PROJECT NAME: SOLIDS CONDITIONING BUILDING ROOF REPLACEMENT
PROJECT MANAGER: NATHAN HODGES
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ
ENGINEER'S ESTIMATE: $1,000,000
NO. BIDDER BID PRICE
1 Platinum Roofing, Inc. $748008
San Jose, California '
2 Exbon Development, Inc. $850,000
Garden Grove, California
Roofing Constructors, Inc.
3 dba: Western Roofing Service $989,431
San Leandro, California
4 Southwest Construction and Property Management $1,005,300
San Bruno, California
5 Pioneer Contractors, Inc. $1,049,000
San Francisco, California
6 Andy's Roofing Co., Inc. $1,106,100
San Leandro, California
7 Stronger Building Services $1,196,500
San Leandro, California
8 Best Contracting Services, Inc. $1,215500
Gardena, California '
BIDS OPENED BY: /s/ Donna M. Anderson DATE: April 17, 2018
May 3, 2018 Regular Board Meeting Agenda Packet- Page 84 of 225
Page 6 of 6
ATTACHMENT 3
SOLIDS CONDITIONING BUILDING ROOF REPLACEMENT
DISTRICT PROJECT 7359
POST-BID / PRECONSTRUCTION ESTIMATE
No. Item Description Amounts % Construction
Cost
1. CONSTRUCTION
a. Construction Contract $748,008
b. Contingency at 15% $112,201
c. Electrical, Safety, and Miscellaneous Work $138,791
SUBTOTAL - CONSTRUCTION $999,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $55,000
- Inspection $51,000
- POD Coordination $5,000
b. Consultants
- Hazardous Material $20,000
- Architectural $5,000
- Structural $5,000
- Specialty Inspection $8,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $149,000 15%
3. PREBID EXPENDITURES
a. Engineering (Design, Drafting, POD
Coordination) $108,000
b. Consultant Fees (Structural, Architectural,
Hazardous Material Testing) $44,000
SUBTOTAL - PREBID EXPENDITURES $152,000 15%
4. TOTAL PROJECT COST $1,300,000