HomeMy WebLinkAbout10. Award contract to Cratus for Orinda Sewer Renovations, Phase 7, DP 8445 Page 1 of 6 Item 10. CENTRAL SAN BOARD OF DIRECTORS ' POSITION PAPER MEETING DATE: MAY 3, 2018 SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $3,306,370 TO CRATUS, INC., THE LOWEST RESPONSIVE BIDDER FOR THE NORTH ORINDA SEWER RENOVATIONS, PHASE 7, DISTRICT PROJECT 8445; CONSIDER EXEMPTION FROM THE CALIFORNIA ENVIRONMENTAL QUALITYACT (CEQA); AND AUTHORIZE UP TO A FIVE-PERCENT CONTINGENCY SUBMITTED BY: INITIATING DEPARTMENT: MARK WENSLAWSKI, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES- ENGINEER CAPITAL PROJECTS REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL SERVICES Roger S. Bailey General Manager ISSUE On April 12, 2018, two bids were received for the construction of the North Orinda Sewer Renovations, Phase 7, District Project 8445 (Project). The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening. BACKGROUND The Project is part of the ongoing sewer renovation within the Collection System Program of the Capital Improvement Budget (CI B)to replace or rehabilitate deteriorated sewer infrastructure that is in poor May 3, 2018 Regular Board Meeting Agenda Packet- Page 74 of 225 Page 2 of 6 condition. This work is coordinated with local jurisdictions, cities, utilities, and private property owners and tenants. The Project consists of approximately 8,500 feet of sewer replacement using open-trench construction, pipe-bursting, pipe reaming, and cured-in-place pipe methods. Two sewer creek crossings will be repaired, sewer pipelines replaced, and work coordinated with the Department of Fish and Wildlife requirements. The Project is located within the City of Orinda in various neighborhoods north of Highway 24, as shown in Attachment 1. Central San staff prepared the plans and specifications for the Project. The Engineer's estimate for construction was $3,200,000. This Project was advertised on March 19 and 23, 2018. Two sealed bids ranging from $3,306,370 to $3,388,000 were received and publicly opened on April 12, 2018. The Engineering and Technical Services Department conducted a technical and commercial review of the bids and determined that Cratus, Inc. is the lowest responsive and responsible bidder. References were provided for Cratus, I nc. and staff received satisfactory feedback. A summary of bids received is shown in Attachment 2. Central San will administer the construction contract and provide construction management, resident engineering, inspection, survey, administration and submittal review. Consultant inspection will be used to supplement staff on an as-needed basis. CEQA: Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section 15302, because it involves replacement of existing facilities at substantially the same locations and with the same purpose and level of activity as the facilities being replaced.Any capacity increases are for non- growth inducing, wet weather purposes. The Project also is exempt under Central San CEQA Guidelines Section 15061(b)(3), since it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment. This certainty is based on Central San's experience with numerous sewer construction projects of this nature, the relatively short distance involved, and Central San's mitigating construction specifications. These specifications are standardized general and special conditions that are made part of the Project bid documents to address environmental considerations, such as protecting trees and riparian areas, as well as compliance with applicable federal, state, county, district, municipal and local laws, ordinances, orders, and regulations.Approval of this Project will establish the Board's independent finding that this Project is exempt from CEQA. ALTERNATIVES/CONSIDERATIONS Delaying or postponing the sewer replacement work is not recommended since several sites have been coordinated with the public and the City of Orinda's upcoming paving plan. Another alternative would be to reject all bids, which is not recommended. FINANCIAL IMPACTS The total estimated Project cost is $4,367,000, including planning, design, bid price, contingency, construction management, and consultant costs as detailed in Attachment 3. This Project is included in Fiscal Year(FY) 2017-2018 Cl B on page 138 with a total estimated project budget of$4,061,000. Financial Impact Table: Amount x❑ Funds budgeted for this project $4,061,000 ❑ Funds taken from current FY 2017-18 Cl B contingency $ 0 Funds transferred from current FY 2017-18 projects: ❑ a. Updated forecast; estimated savings from project available $ 0 ❑ b. Acceleration of funds for project that is budgeted in future year $ 0 ❑ c. Combined project scope for bidding purposes $0 May 3, 2018 Regular Board Meeting Agenda Packet- Page 75 of 225 Page 3 of 6 d. Potential future year budget impact 0 (May be mitigated through (1) savings from close-outs of current $306,000 year projects; (2) reprioritizing future year projects; (3) cost savings on future year projects) Total Current Year Cost $4,367,000 COMMUNITY OUTREACH Central San held a public meeting on March 14, 2018, at the Orinda Library to assist with any questions or concerns by the residents along the proposed construction alignments. In addition, staff has notified and met with several easement homeowners directly to discuss the upcoming sewer work, construction impacts, project schedule, and to receive input. COMMITTEE RECOMMENDATION The Engineering and Operations Committee reviewed this Project at the meeting on April 25, 2018, and recommended approval of the Project. RECOMMENDED BOARD ACTION Staff recommends the following: 1. Find that the Project is exempt from CEQA; 2. Award a construction contract in the amount of $3,306,370 for the construction of the North Orinda Sewer Renovations, Phase 7, District Project 8445, to Cratus, Inc., the lowest responsive and responsible bidder; and 3. Authorize the General Manager to execute the Contract Documents subject to submittal requirements and include up to a five-percent contingency. Strategic Plan re-In GOAL ONE: Provide Exceptional Customer Service Strategy 1 - Foster Customer Engagement and Awareness GOAL TWO: Strive to Meet Regulatory Requirements Strategy 2- Strive to Minimize the Number of Sanitary Sewer Overflows GOAL FIVE: Maintain a Reliable Infrastructure Strategy 2- Facilitate Long-term Capital Renewal and Replacement ATTACHMENTS: 1. Project Location Map 2. Summary of Bids 3. Post-Bid/P reconstruction Estimate May 3, 2018 Regular Board Meeting Agenda Packet- Page 76 of 225 Page 4 of 6 Briones Reservoir P-c Project Areas - ` �K-RD yQ� AN-k--e--RD l C (� 2 �l i Qpm 24 1�J��1s P 2p l O� Q- t Lafayette mom' Reservoir Q� ti ti w� SEM BLVD �N N 0 3,000 Feet l North Orinda Sewer Renovations Phase 7 Attachment CENTRAL SAN District Project 8445 1 • Project Location May 3, 2018 Regular Board Meeting Agenda Packet- Page 77 of 225 Page 5 of 6 ATTACHMENT 2 NORTH ORINDA SEWER RENOVATIONS, PHASE 7 DISTRICT PROJECT 8445 SUMMARY OF BIDS PROJECT NO.: 8445 NO. OF ADDENDA: 0 DATE/TIME: APRIL 12, 2018/2:00 PM PROJECT NAME: NORTH ORINDA SEWER RENOVATIONS, PHASE 7 PROJECT MANAGER: MARK WENSLAWSKI PROJECT LOCATION: ORINDA, CALIFORNIA ENGINEER'S ESTIMATE: $3,200,000 NO. BIDDER BID PRICE 1 Cratus, Inc. $3,306,370 San Francisco, California 2 K.J. Woods Construction, Inc. $3,388,000 San Francisco, California BIDS OPENED BY: /s/ Katie Young DATE: April 12, 2018 May 3, 2018 Regular Board Meeting Agenda Packet- Page 78 of 225 Page 6 of 6 ATTACHMENT 3 NORTH ORINDA SEWER RENOVATIONS, PHASE 7 DISTRICT PROJECT 8445 POST-BID/PRECONSTRUCTION ESTIMATE % of No. Item Description Amounts Construction Cost 1. CONSTRUCTION a. Construction Contract $3,306,370 b. 5% Contingency $165,630 c. Permits $20,000 SUBTOTAL— CONSTRUCTION COST $3,492,000 100% 2. CONSTRUCTION MANAGEMENT a. District Forces - Construction Management $130,000 (Engineering, Survey) - Public Relations/Right of Way $20,000 - Inspection $160,000 b. Consultants - Material Testing/Geotechnical/Others $40,000 SUBTOTAL - CONSTRUCTION MANAGEMENT $350,000 10% 3. PREBID EXPENDITURES a. Engineering (Design, Survey, Drafting) $525,000 SUBTOTAL - PREBID EXPENDITURES $525,000 15% 4. TOTAL ESTIMATED PROJECT COST $4,367,000 May 3, 2018 Regular Board Meeting Agenda Packet- Page 79 of 225