CENTRAL SAN BOARD OF DIRECTORS
' POSITION PAPER
DRAFT
MEETING DATE: FEBRUARY20, 2018
SUBJECT: REVIEW DRAFT POSITION PAPER TO APPROVE A CONTINGENCY
PROJECT IN THE AMOUNT OF $1,400,000 FOR THE RECYCLED WATER
CLEARWELL REPAIRS, DISTRICT PROJECT 7365; CONSIDER
EXEMPTION FROM THE CALIFORNIA ENVIRONMENTAL QUALITYACT
(CEQA); AND AUTHORIZE A TRANSFER OF FUNDS WITHIN THE CAPITAL
IMPROVEMENT BUDGET
SUBMITTED BY: INITIATING DEPARTMENT:
CHATHU ABEYRATHNA, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
Board of Directors (Board) authorization is required to include a contingency project in the Capital
Improvement Budget (CI B)for an amount that exceeds $100,000. Board authorization is also required to
transfer funds above $500,000.
BACKGROUND
The Clearwell structure, installed in 1975, provides storage and chlorine contact time for recycled water
prior to delivery to the treatment plant and Zone 1. The Clearwell is an earthen basin with a sloped bottom
that is lined with a propylene liner and separated into two cells by a concrete divider wall. Only the East Cell
is currently in operation. In 1996, a reinforced polypropylene floating cover was added to the East Cell to
reduce algae, reduce fecal contamination from birds, and help minimize sodium hypochlorite usage. There
is no cover on the West Cell of the Clearwell. Over the last six months, the cover on the East Cell has
deteriorated due to failed drains and tears in the cover. In addition, based on a recent dive inspection,
portions of the cover are deteriorating from the underside. Leakage on the top of the Clearwell cover and
accumulation of water could cause the cover to fail resulting in a failure to meet Title 22 requirements (e.g.
increased turbidity).
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 21 of 73
Page 2 of 9
The Comprehensive Wastewater Master Plan (CWMP) and the 2017 Ten-Year Capital Improvement Plan
(CI P) recommends a project to replace the Clearwell liner and cover in Fiscal Year(FY) 2023-24 that
includes inspection of the Clearwell, replacement of the liners and the East Cell cover, and installation of a
new West Cell cover. Staff is proposing to expedite this project to begin this fiscal year and deliver the
project in two phases. Phase 1, Recycled Water Clearwell Repairs, will restore the West Cell to
operational condition to solve immediate redundancy and reliability issues by dewatering and cleaning the
West Cell, including mechanical improvements, and repair of the East Cell cover.
Phase 2 will construct the permanent and long-term improvements. Staff is proposing to include Phase 2
of the Recycled Water Clearwell Improvements to the Filter Plant Improvements project already identified
in the CI B. Staff is currently soliciting proposals for pre-design and final design for the Filter Plant
I mprovements. I n the meantime, the Phase 1 project needs to be addressed and staff has proposed to
bid the Recycled Water Clearwell Repairs (Project), District Project 7365 as soon as possible and return
back to the Board with a final project amount at award.
C E .A:
Staff has concluded that this Project is exempt from the CEQA under Central San's CEQA Guidelines
Section 15301, since it involves minor alterations to existing public facilities involving no expansion of use.
Approval of this Project will establish the Board's independent finding that this Project is exempt from
CEQA.
ALTERNATIVES/CONSIDERATIONS
The purpose of repairing and commissioning the West Cell is to allow minimal disruption to delivering
recycled water. Another alternative would be to shut down the Clearwell to perform any repairs, if possible,
and be out of service for several months.
Postponing the proposed Phase 1 work could result in an interruption and/or discontinuance of recycled
water supply to our customers and the treatment plant. The treatment plant has the ability to operationally
use another source of water instead of recycled water, but this is not preferred by Operations.
Staff is also evaluating the feasibility of renting temporary equipment, bypassing recycled water, and still
meeting permit conditions.
FINANCIAL IMPACTS
The total estimated cost for this contingency project is $1,400,000, which includes $140,000 for staff time,
$975,000 for construction costs, $60,000 for construction management, and $225,000 in contingency.
To fund this contingency project, staff plans to bid the Phase 1 project and then transfer the total project
costs from the following two projects:
1. UV Disinfection Upgrades, District Project 7352 ($400,000 available).
2. IT Development, District Project 8240 ($1,000,000 available).
Both projects have been delayed and have the budget available this fiscal year. The UV project is in
procurement and will not be delivered until next fiscal year. The IT Development project funds were to be
used for the Enterprise Resource Planning (ERP) and other projects that have not progressed on the
same pace as originally anticipated. The ERP and other projects are still forecast to occur, but with the
bulk of the spending in FY 2018-19 and the next two years.Accordingly, funds will need to be restored to
the IT budget from other sources, in those years. No future CI B or CI P increase is anticipated as
indicated in the following table:
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 22 of 73
Page 3 of 9
Financial Impact Table: Amount
❑ Funds budgeted this FY 2017-18 for this project $ 0
❑ Funds taken from current FY 2017-18 CI B contingency $ 0
Funds transferred from current FY 2017-18 projects:
❑ a. Updated forecast; estimated savings from project available $ 0
0 b. Acceleration of funds for project that is budgeted in future year $1,400,000
❑ c. Combined project scope forbidding purposes: DP $ 0
d. Potential future year budget impact
❑ (May be mitigated through (1) savings from close-outs of current $ 0
year projects; (2) reprioritizing future year projects; (3) cost
savings on future year projects)
Total Current Year Cost $1,400,000
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the February 20, 2018 meeting
and recommended approval of the Project.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Approve a contingency project for$1,400,000 for the Recycled Water Clearwell Repairs,
District Project 7365; and
3. Authorize the General Manager to transfer$1,400,000 within the Capital Improvement Budget.
Strategic Plan re-In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to Achieve 100% Permit Compliance in Air, Water, Land and Other Regulations
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 1 - Manage Assets Optimally Throughout Their Lifecycle, Strategy 2- Facilitate Long-term Capital Renewal
and Replacement
ATTACHMENTS:
1. Presentation
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 23 of 73
Page 4 of 9
RECYCLED WATER
CLEARWELL REPAIRS
Engineering & Operations Committee
February 20, 2018 Meeting
Presented by
Edgar J. Lopez, PE
Capital Projects Division Manager
and
Chathura Abeyrathna, PE
Associate Engineer
1'
ISSUES-BACKGROUND
• Clearwell stores recycled water (ReW)
• Only East Cell has been used to store ReW
• East Cell has a 20 year-plus old membrane cover
• West Cell has never been used and never been covered
• Filter Improvements Project currently identified in the CIB
• Clearwell cover replacement identified in CWMP; included
in CIP in four years
• Last year heavy rain and drain failure accelerated
deterioration of cover
1
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 24 of 73
Page 5 of 9
CLEARWELL COVER PICTURE JUNE 2014
West Cell
East Cell
without cover
with cover
Aida W-10 _.
COVER INSPECTION JANUARY 2018
r
I
�1
2
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 25 of 73
Page 6 of 9
COVER CONDITION
AFTER INSTALLATION OF INNER TUBES
REPAIR SCOPE
Dewater, clean, and dispose solids on West Cell
Replace gates and make the West Cell operable
Install temporary cover on West Cell
Continue inspection of East Cell and repair cover
Minimize risk in meeting Title 22 and supplying ReW to
plant and Zone 1
I.
3
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 26 of 73
Page 7 of 9
TEMPORARY COVER
FLOATING BALLS OR LILY PADS
Temporary cover provides:
Reduced evaporation
Shades water from sunlight to prevent algae growth
Covers water,which deters waterfowl from entering
the reservoir and nesting in the water or other fluid
Reduces water treatment chemical use
rr Deters wildlife
CLEARWELL REPAIRS TIMELINE
• Design: January — February 2018
• Pre-purchase Inlet and Outlet Gates: February— June 2018
• Construction: April — June 2018
4
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 27 of 73
Page 8 of 9
CLEARWELL REPAIRS PROJECT BUDGET
Design Costs $ 140,000
Construction Contracts:
a. Cleaning and Removal of Solids $ 600,000
b. Temporary Floating Cover: (Balls/Lilly Pad) $ 250,000
c. New Gates $ 125,000
Estimated Total Construction Cost $ 975,000
Construction Management Costs $ 60,000
Contingency $ 225,000
Estimated Project Budget $ 1,400,000
1.
RECOMMENDATIONS
Approve a $1,400,000 contingency project for the ReW
Clearwell Repair Project, District Project 7365
Authorize the General Manger to transfer the required
funds from the Fiscal Year 2017-18 Capital Improvement
Budget
5
February 20, 2018 EOPS Regular Committee Meeting Agenda Packet- Page 28 of 73
Page 9 of 9
QUESTIONS?
6