HomeMy WebLinkAbout05. Approve $1.4 million contingency project for the Recycled Water Clearwell Repairs, DP 7365 Page 1 of 4
Item 5.
CENTRAL SAN BOARD OF DIRECTORS
' POSITION PAPER
MEETING DATE: MARCH 1, 2018
SUBJECT: APPROVE A CONTINGENCY PROJECT IN THE AMOUNT OF $1,400,000
FOR THE RECYCLED WATER CLEARWELL REPAIRS, DISTRICT
PROJECT 7365; CONSIDER EXEMPTION FROM THE CALIFORNIA
ENVIRONMENTAL QUALITYACT (CEQA); AND AUTHORIZE A TRANSFER
OF $1,400,000 WITHIN THE CAPITAL IMPROVEMENT BUDGET
SUBMITTED BY: INITIATING DEPARTMENT:
CHATHU ABEYRATHNA, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
Board of Directors (Board) authorization is required to include a contingency project in the Capital
Improvement Budget (CI B)for an amount that exceeds $100,000. Board authorization is also required to
transfer funds above $500,000.
BACKGROUND
The Clearwell structure, installed in 1975, provides storage and chlorine contact time for recycled water
prior to delivery to the treatment plant and Zone 1. The Clearwell is an earthen basin with a sloped bottom
that is lined with a propylene liner and separated into two cells by a concrete divider wall. Only the East Cell
March 1, 2018 Regular Board Meeting Agenda Packet- Page 46 of 225
Page 2 of 4
is currently in operation. In 1996, a reinforced polypropylene floating cover was added to the East Cell to
reduce algae, reduce fecal contamination from birds, and help minimize sodium hypochlorite usage. There
is no cover on the West Cell of the Clearwell. Over the last six months, the cover on the East Cell has
deteriorated due to failed drains and tears in the cover. In addition, based on a recent dive inspection,
portions of the cover are deteriorating from the underside. Leakage on the top of the Clearwell cover and
accumulation of water could cause the cover to fail resulting in a failure to meet Title 22 requirements (e.g.
increased turbidity).
The Comprehensive Wastewater Master Plan and the 2017 Ten-Year Capital Improvement Plan (CI P)
recommends a project to replace the Clearwell liner and cover in Fiscal Year(FY) 2023-24 that includes
inspection of the Clearwell, replacement of the liners and the East Cell cover, and installation of a new
West Cell cover. Staff is proposing to expedite this project to begin this fiscal year and deliver the project
in two phases.
This project, Phase 1, Recycled Water Clearwell Repairs, will restore the West Cell to operational
condition to solve immediate redundancy and reliability issues by dewatering and cleaning the West Cell,
including mechanical improvements, and repair of the East Cell cover.
Phase 2 will construct the permanent and long-term improvements. Staff is proposing to include Phase 2
of the Recycled Water Clearwell Improvements to the Filter Plant Improvements project already identified
in the CI B. Staff is currently soliciting proposals for pre-design and final design for the Filter Plant
Improvements. In the meantime, the Phase 1 project needs to be addressed and staff has proposed to
bid the Recycled Water Clearwell Repairs (Project), District Project 7365 as soon as possible and return
back to the Board with a final project amount at award.
C E .A:
Staff has concluded that this Project is exempt from the CEQA under Central San's CEQA Guidelines
Section 15301, since it involves minor alterations to existing public facilities involving no expansion of use.
Approval of this Project will establish the Board's independent finding that this Project is exempt from
CEQA.
ALTERNATIVES/CONSIDERATIONS
The purpose of repairing and commissioning the West Cell is to allow minimal disruption to delivering
recycled water.Another alternative would be to shut down the Clearwell to perform any repairs, if possible,
and be out of service for several months.
Postponing the proposed Phase 1 work could result in an interruption and/or discontinuance of recycled
water supply to our customers and the treatment plant. The treatment plant has the ability to operationally
use another source of water instead of recycled water, but this is not preferred by Operations.
Staff is also evaluating the feasibility of renting temporary equipment, bypassing recycled water, and still
meeting permit conditions.
FINANCIAL IMPACTS
The total estimated cost for this contingency project is $1,400,000, which includes $140,000 for staff time,
$975,000 for construction costs, $60,000 for construction management, and $225,000 in contingency.
Staff is recommending a 23-percent contingency amount ($225,000) based on the uncertainty of solids
disposal costs and for the repairs on the existing East Cell cover.
To fund this contingency project, staff plans to bid the Phase 1 project and then transfer the total project
costs from the following two projects:
March 1, 2018 Regular Board Meeting Agenda Packet- Page 47 of 225
Page 3 of 4
1. Ultraviolet (UV) Disinfection Upgrades, District Project 7352 ($400,000 available).
2. Informational Technology(IT) Development, District Project 8240 ($1,000,000 available).
Both projects have been delayed and have budget available this fiscal year. The UV project includes
several improvements to improve the reliability of the existing UV disinfection system by replacing various
components. The parts associated with the UV project are currently in the procurement stage and delivery
is anticipated next fiscal year. The available I T Development project funds were to be used for the
Enterprise Resource Planning (ERP) and other IT projects that have not progressed on the same pace as
originally anticipated. The ERP and other IT projects are still forecast to occur, but with the bulk of the
spending in FY 2018-19 and the following two years.Accordingly, funds will need to be restored to the IT
and UV project budgets from other sources, in those years. No future C I B or C I P increase is anticipated
as indicated in the following table:
Financial Impact Table: Amount
❑ Funds budgeted this FY 2017-18 for this project $ 0
❑ Funds taken from current FY 2017-18 C I B contingency $ 0
Funds transferred from current FY 2017-18 projects:
❑ a. Updated forecast; estimated savings from project available $ 0
0 b. Acceleration of funds for project that is budgeted in future year $1,400,000
❑ c. Combined project scope for bidding purposes: $ 0
d. Potential future year budget impact
❑ (May be mitigated through (1) savings from close-outs of current $ 0
year projects; (2) reprioritizing future year projects; (3) cost
savings on future year projects)
Total Current Year Cost $1,400,000
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at the February 20, 2018
meeting. Member McGill recommended Board approval on the project. Chair Causey also supported the
project; however, he recommended only 2 of the 3 staff recommendations, stating that he could not
recommend Board approval on the transfer of funds in the Capital Improvement Program. Both Members
agreed to have this item listed as part of the Board Consent Calendar. Member Causey said that he may
make a statement regarding funding at the Board meeting.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Approve a contingency project for$1,400,000 for the Recycled Water Clearwell Repairs,
District Project 7365; and
3. Authorize the General Manager to transfer$1,400,000 within the Capital Improvement Budget.
Strategic Plan Tie-In
GOAL TWO: Strive to Meet Regulatory Requirements
March 1, 2018 Regular Board Meeting Agenda Packet- Page 48 of 225
Page 4 of 4
Strategy 1 - Strive to Achieve 100% Permit Compliance in Air, Water, Land and Other Regulations
GOAL FIVE:Maintain a Reliable Infrastructure
Strategy 1 - Manage Assets Optimally Throughout Their Lifecycle
March 1, 2018 Regular Board Meeting Agenda Packet- Page 49 of 225