HomeMy WebLinkAbout05. Award construction contract for Walnut Creek Sewer Renovations, Ph. 12, DP 8435 Page 1 of 7
Item 5.
CENTRAL SAN BOARD OF DIRECTORS
' POSITION PAPER
MEETING DATE: FEBRUARY 15, 2018
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $3,380,975
TO CALIFORNIA TRENCHLESS, INC. FOR THE WALNUT CREEK SEWER
RENOVATIONS, PHASE 12, DISTRICT PROJECT 8435, AND CONSIDER
EXEMPTION FROM THE CALIFORNIA ENVIRONMENTAL QUALITYACT
(CEQA)
SUBMITTED BY: INITIATING DEPARTMENT:
DAMASI0 ZEPEDA ARAGON, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
On February 1, 2018, three bids were received for the construction of the Walnut Creek Sewer
Renovations, Phase 12, District Project 8435 (Project). The Board of Directors (Board) must award the
contract or reject bids within 50 days of the bid opening.
BACKGROUND
The Project is part of the ongoing sewer renovation within the Collection System Program of the Capital
Improvement Budget (CI B)to replace or rehabilitate deteriorated sewer infrastructure that is in poor
condition. This work is coordinated with local jurisdictions, cities, utilities, and private property owners and
February 15, 2018 Regular Board Meeting Agenda Packet- Page 15 of 77
Page 2 of 7
tenants.
The original Project scope of work included replacement or rehabilitation of approximately 8,500 feet of
sewer mains, primarily 6-inch clay sewers, construction of manholes, and other related work within public
rights-of-way and easements.An additional 500 feet of sewer replacement was included in the Project
based on urgent needs, such as the Ygnacio Valley Road site and other nearby critical sites identified
under the Collection System Sewer Renovation - Phase 1, District Project (DP) 8451. The current Project
consists of 9,000 feet of sewer replacement using open trench construction, pipe-bursting, and other
trenchless methods. The majority of this Project is located within the unincorporated area of Walnut
Creek, several sites in the City of Walnut Creek, and one site in unincorporated Alamo, as shown
in Attachment 1.
Central San staff prepared the plans and specifications for the Project. The Engineer's estimate for
construction is $3,200,000. This Project was advertised on January 19 and 24, 2018. Three sealed bids
ranging from $3,380,975 to $3,658,455 were received and publicly opened on February 1, 2018. The
Engineering and Technical Services Department conducted a technical and commercial review of the bids
and determined that California Trenchless, Inc. (CTI) is the lowest responsive and responsible bidder.
CTI has worked for Central San in the past and new references were provided with satisfactory feedback.
A summary of bids received is shown in Attachment 2. Central San will administer the construction contract
and provide construction management, resident engineering, inspection, survey, administration and
submittal review. Consultant inspection will be used to supplement staff on an as-needed basis.
CEQA:
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15302, because it involves replacement of existing facilities at substantially the same locations and with the
same purpose and level of activity as the facilities being replaced.Any capacity increases are for non-
growth inducing, wet weather purposes. The Project also is exempt under Central San CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that the activity in
question may have a significant effect on the environment. This certainty is based on Central San's
experience with numerous sewer construction projects of this nature, the relatively short distance involved,
and Central San's mitigating construction specifications. These specifications are standardized general
and special conditions that are made part of the Project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with applicable federal,
state, county, district, municipal and local laws, ordinances, orders, and regulations. Approval of this
Project will establish the Board's independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Reject all bids, which is not recommended. Delaying or postponing the sewer replacement work is not
recommended since several sites have been coordinated with the public and Contra Costa County's
upcoming 2018 paving plan.
FINANCIAL IMPACTS
The total estimated Project cost is $4,550,000, including planning, design, bid price, contingency,
construction management, and consultant costs as detailed in Attachment 3. This Project is included in
Fiscal Year(FY) 2017-2018 Cl B on page 130 with a total estimated project budget of$4,100,000. The
Collection System Sewer Renovation - Phase 1, DP 8451, is on page 142 with an estimated budget of
$500,000. The project scopes and budgets will be combined; therefore, a transfer of$450,000 will be
completed under the General Manager's delegated authority for the Capital Improvements Program.
February 15, 2018 Regular Board Meeting Agenda Packet- Page 16 of 77
Page 3 of 7
Financial Impact Table: Amount
0 Funds budgeted this FY 2017-18 for this project $ 4,100,000
❑ Funds taken from current FY 2017-18 CI B contingency $ 0
Funds transferred from current FY 2017-18 projects:
❑ a. Updated forecast; estimated savings from project available $ 0
❑ b. Acceleration of funds for project that is budgeted in future year $ 0
0 c. Combined project scope for bidding purposes: DP 8451 $ 450,000
d. Potential future year budget impact
❑ (May be mitigated through (1) savings from close-outs of current $ 0
year projects; (2) reprioritizing future year projects; (3) cost
savings on future year projects)
Total Current Year Cost $ 4,550,000
COMMUNITY OUTREACH
Central San held a public meeting on January 11, 2018, at the Collection System Operations Department
building in Walnut Creek to assist with any questions or concerns by the residents along the proposed
construction alignments. I n addition, staff has notified and met with several easement homeowners directly
to discuss the upcoming sewer work, construction impacts, project schedule, and to receive input.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this Project at the meeting on February 2, 2018,
and recommended approval of the Project.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of $3,380,975 for the construction of the Walnut Creek
Sewer Renovations, Phase 12, District Project 8435, to California Trenchless, Inc., the lowest
responsive and responsible bidder; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements and include up to a seven and one-half percent contingency.
GOAL ONE: Provide Exceptional Customer Service
Strategy 1 - Foster Customer Engagement and Awareness
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 2- Strive to Minimize the Number of Sanitary Sewer Overflows
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 2- Facilitate Long-term Capital Renewal and Replacement
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
February 15, 2018 Regular Board Meeting Agenda Packet- Page 17 of 77
Page 4 of 7
3. Post-Bid/P reconstruction Estimate
February 15, 2018 Regular Board Meeting Agenda Packet- Page 18 of 77
Page 5 of 7
� ••� � ® Project Areas
b S
w
V
�N
24
RF���F�k I�
r-rte � 44
qW �,�+
. pIRD
PA
N
0 3,600 . {3NER
L-L
Feet
LICENTRAL SAN Walnut Creek Sewer Renovations Phase 12 Attachment
District Project 8435 1
• EM Project Location
February 15, 2018 Regular Board Meeting Agenda Packet- Page 19 of 77
Page 6 of 7
ATTACHMENT 2
WALNUT CREEK SEWER RENOVATIONS, PHASE 12
DISTRICT PROJECT 8435
SUMMARY OF BIDS
PROJECT NO.: 8435 NO. OF ADDENDA: 1 DATE/TIME: FEBRUARY 1, 2018 /11 AM
PROJECT NAME: WALNUT CREEK SEWER RENOVATIONS, PHASE 12
PROJECT MANAGER: DAMASIO ZEPEDA ARAGON
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $3,200,000
NO. BIDDER BID PRICE
1 California Trenchless, Inc. $3,380,975
Hayward, California
2 K.J. Woods Construction, Inc. $3,438,000
San Francisco, California
3 Cratus, Inc. $3,658,455
San Francisco, California
BIDS OPENED BY: /s/ Donna M. Anderson DATE: February 1, 2018
February 15, 2018 Regular Board Meeting Agenda Packet- Page 20 of 77
Page 7 of 7
ATTACHMENT 3
WALNUT CREEK SEWER RENOVATIONS, PHASE 12
DISTRICT PROJECT 8435
POST-BID/PRECONSTRUCTION ESTIMATE
% of
No. Item Description Amounts Construction
Cost
1. CONSTRUCTION
a. Construction Contract $3,380,975
b. 7.5% Contingency $253,525
c. Permits $35,000
SUBTOTAL— CONSTRUCTION COST $3,669,500 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $145,000
(Engineering, Survey)
- Public Relations/Right of Way $25,500
b. Consultants
- Material Testing/Geotechnical/Others $40,000
- Inspection $120,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $330,500 9%
3. PREBID EXPENDITURES
a. Engineering (Design, Survey, Drafting) $550,000
SUBTOTAL - PREBID EXPENDITURES $550,000 15%
4. TOTAL ESTIMATED PROJECT COST $4,550,000
February 15, 2018 Regular Board Meeting Agenda Packet- Page 21 of 77