HomeMy WebLinkAbout03.b. Review draft Position Paper to award a construction contract for the Fire Protection System -Phase 2 Revised, District Project 7322Page 1 of 6
Item 3.b.
' CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
� DRAFT
MEETING DATE: DECEMBER 12, 2017
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT FOR THE FIRE PROTECTION SYSTEM -PHASE 2 REVISED,
DISTRICT PROJECT 7322; AUTHORIZE THE GENERAL MANAGER TO
EXECUTE THE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL
REQUIREMENTS; AND AUTHORIZE THE GENERAL MANAGER TO AMEND
AN EXISTING PROFESSIONAL SERVICES AGREEMENT WITH DTN
ENGINEERS, INC. FOR SUPPORT SERVICES DURING CONSTRUCTION
SUBMITTED BY: INITIATING DEPARTMENT:
JAY LIN, ASSOCIATE ENGINEER ENGINEERINGAND TECHNI CAL SERVI CES -
CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN -MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY GENERAL MANAGER
ISSUE
On December 15, 2017, bids were received and opened for the construction of the Fire Protection
System — Phase 2 Revised, District Project 7322 (Project). The Board of Directors must award the
contract or reject bids within 50 days of the bid opening.
BACKGROUND
Existing fire protection systems at the treatment plant have been installed over a 45 -year period and been
expanded or upgraded on a project -to -project basis. The older systems are becoming unreliable and
difficult to maintain. The original, circa 1970's treatment plant fire alarm system (main system) was
designed to monitor pull stations and sprinkler activation in the Plant Operations Building (POB), treatment
plant, and monitor other building fire systems. I n addition, this system is the primary notification to the
Control Room operators and occupied buildings in the event of a fire. Very little work has been done on
the main system, other than a panel and device replacement in 2002. Troubleshooting and repairing the
main system has been extremely difficult and the system is problematic. Repeated expensive service
calls have not fully resolved the issues. Due to the age, maintenance difficulty, and criticality of the system,
December 12, 2017 EOPS Regular Committee Meeting Agenda Packet - Page 6 of 43
Page 2 of 6
staff hired DTN Engineers, Inc. (DTN) to evaluate the fire alarm system, and replacement of the system
was recommended.
Phase 1 of the project, completed in 2013, replaced the outdated Headquarters Office Building fire
system and corrected limited treatment plant deficiencies. A predesign was performed to provide a
comprehensive evaluation of all staffed and critical process areas in the treatment plant, and recommend
improvements for life safety of occupied (public and staff) areas. As a result, scope was identified for
existing and future project phases. Phase 2 was initially bid last summer, but had to be revised due to
the high costs of the bids received. Phase 2 Revised includes the installation of the highest priority items,
including the POB Multi -Purpose Room smoke detectors, gas detection system in the Solids
Conditioning Building, standby power fire panel replacement, fuel tank area foam trailer addition, and other
related improvements.
Central San staff and DTN prepared the plans and specifications for the Project. The Engineer's estimate
for construction was $700,000. This Project was advertised on November 17 and 27, 2017. sealed
bids ranging from $xxx,xxx to $=,= were received and publicly opened on December 15, 2017.
The Engineering and Technical Services Department conducted a technical and commercial review of the
bids and determined that [Company Name] is the lowest responsive and responsible bidder with a total bid
amount of $xxx,xxx. A summary of bids received is shown in Attachment 2.
Staff recommends retaining DTN to provide support services during the construction phase, which
includes reviewing shop drawings and submittals, responding to design questions, evaluating change
order requests, performing site visits to verify compliance with the design, electrical inspection,
coordination with the Contra Costa Fire Protection District, and other related activities. An as -needed
construction support services agreement amendment with a cost ceiling of $80,000 has been negotiated
with DTN.
CEQA
Staff has concluded that this Project is exempt from the California Environmental Quality Act (CEQA)
under District CEQA Guidelines Section 15301, since it involves minor alterations to existing public
facilities involving no expansion of use, and CEQA Guidelines Section 15302, since it involves
replacement of existing public facilities at the same location and with the same purpose. Approval of this
Project will establish the Board of Directors' independent finding that this Project is exempt from CEQA.
ALT ERNAT IVES/CONSIDERAT IONS
Reject all bids, which is not recommended. Staff does not have the certification or license required to
perform the installation or consulting work identified in this Project. The existing fire alarm and suppression
systems are permitted by and under the jurisdiction of the Contra Costa County Fire Protection District.
FINANCIAL IMPACTS
The total estimated project costs is $1,327,000, which includes planning, design, bid (rebid), construction
contract, contingency, and construction management costs as shown in Attachment 3. The Fire Protection
System -Phase 2, District Project 7322, included in the Fiscal Year (FY) 2017-18 Capital Improvement
Budget on page 153, has a total of $1,200,000 budgeted for the project. An additional $127,000 is
required for this project and will be transferred from District Project 7355, Odor Control Upgrades under
the delegated authority of the General Manager. Project 7355 has been rescheduled to start in FY 2018-
19 since the project is awaiting the conclusion of the Treatment Plant Health Risk Assessment, currently
being conducted under the Solids Handling Facility Improvements.
The current agreement with DTN has a cost ceiling of $172,500. The new cost ceiling for this agreement,
December 12, 2017 EOPS Regular Committee Meeting Agenda Packet - Page 7 of 43
Page 3 of 6
including the $80,000 amendment for construction services, will be $252,500.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at the meeting on December 12, 2017,
and recommended approval of the Project.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of $xxx,xxx for the construction of the Fire Protection
Systems — Phase 2 Revised, District Project 7322 to [Company Name], the lowest responsible and
responsive bidder;
3. Authorize the General Manager to execute the Contract Documents subject to submittal requirements
and include up to 15 -percent contingency; and
4. Authorize the General Manager to execute an amendment with DTN Engineers Inc. to increase the
cost ceiling from $172,500 to $252,500 to provide as -needed construction support services for the
Project.
Strategic Plan Tie -In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to Achieve 100% Permit Compliance in Air, Water, Land and Other Regulations
GOAL FOUR: Develop and retain a highly trained and innovative workforce
Strategy 3 - Meet or Exceed Industry Safety Standards
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 3 - Protect District Personnel and Assets from Threats and Emergencies
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids (Draft)
3. Post-Bid/P reconstruction Estimate
December 12, 2017 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 43
Page 4 of 6
ATTACHMENT 1
FIRE PROTECTION SYSTEM - PHASE 2 REVISED
DISTRICT PROJECT 7322
LOCATION MAP
.L(;EQ
N
PROJECT SITE 5
pw
Illi ��
------ ......
moo, .
'no
FUEL OIL
STORAOF
06REA
SWUS
OULN4C,
STN"y
POWM
t K%Dw
IN
Central Contra Cost,'i
Sanitary District FIRE PROTECTION SYSTEM -PHASE 2 1 r
District Project 7322
Martinez, California
December 12, 2017 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 43
Annex
.= r1Vt+AtIVN
FUEL OIL
STORAOF
06REA
SWUS
OULN4C,
STN"y
POWM
t K%Dw
IN
Central Contra Cost,'i
Sanitary District FIRE PROTECTION SYSTEM -PHASE 2 1 r
District Project 7322
Martinez, California
December 12, 2017 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 43
Page 5 of 6
ATTACHMENT 2
FIRE PROTECTION SYSTEMS — PHASE 2 REVISED
DISTRICT PROJECT 7322
SUMMARY OF BIDS
PROJECT NO.: 7322 NO. OF ADDENDA: 0 DATE/TIME: DECEMBER 15. 2017/2PM
PROJECT NAME: FIRE PROTECTION SYSTEMS — PHASE 2 REVISED
PROJECT MANAGER: JAY LIN
PROJECT LOCATION: 5019 IMHOFF PLACE. MARTINEZ. CALIFORNIA
ENGINEER'S ESTIMATE: $700,000
NO.
BIDDER
BID PRICE
1
TBD
$xxx,xxx
City, California
2
TBD
�YYY'YYY
City, California
3
TBD
$zzz,zzz
City, California
BIDS OPENED BY: Donna M. Anderson
DATE: December 15, 2017
December 12, 2017 EOPS Regular Committee Meeting Agenda Packet - Page 10 of 43
Page 6 of 6
ATTACHMENT 3
FIRE PROTECTION SYSTEMS — PHASE 2 REVISED
DISTRICT PROJECT 7322
POST-BID/PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% of
Construction
Costs
1.
CONSTRUCTION
a. Construction Contract
$700,000
b. Contingency at 15%
$105,000
c. Permits
$5,000
SUBTOTAL - CONSTRUCTION
$810,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management
$30,000
- Operations Support
$10,000
b. Consultants
- DTN Support Services
$80,000
- Inspection
$35,000
SUBTOTAL - CONSTRUCTION
$155,000
19.1%
MANAGEMENT
3.
PREBID EXPENDITURES
a. Staff Engineering and Operations
$178,650
b. Consultant Fees
$172,500
c. Prior Expenditures
$10,850
SUBTOTAL - PREBID EXPENDITURES
$362,000
44.7%
4.
TOTAL ESTIMATED PROJECT COST
$1,327,000
* Cost includes prior expenditures and rebid.
December 12, 2017 EOPS Regular Committee Meeting Agenda Packet - Page 11 of 43