HomeMy WebLinkAbout07. Authorize the General Manager to execute a construction contract change order up to $160,000 with K.J. Wood Construction, Inc. for the sewer replacement at the Ygnacio Valley Road/Lacassie Avenue Easement in the City of Walnut Creek.Page 1 of 4
Item 7.
POSITION PAPER
iCENTRAL SAN BOARD OF DIRECTORS
MEETING DATE: SEPTEMBER 21, 2017
SUBJECT: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A CONSTRUCTION
CONTRACT CHANGE ORDER UP TO $160,000 WITH K.J. WOODS
CONSTRUCTION, INC. FOR THE SEWER REPLACEMENT AT THE
YGNACI O VALLEY ROAD/LACASSI E AVENUE EASEMENT IN THE CITY
OF WALNUT CREEK. APPROVAL RECOMMENDED BY ENGINEERING &
OPERATIONS COMMITTEE.
SUBMITTED BY:
INITIATING DEPARTMENT:
TOM GODSEY, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL
ERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
J EAN-MARC PETIT, DI RECTOR OF ENGI NEERI NG AND TECHNI CAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
Authorization by the Board of Directors is required for the General Manager to execute a construction
contract change order in an amount greater than $100,000.
BACKGROUND
The existing 370 -foot long 10 -inch diameter sewer in the easement from Ygnacio Valley Road to Lacassie
Road in Walnut Creek was built in 1949. In 2009, the replacement of an adjoining retaining wall allowed
Central San to replace a 185 -foot length of the deteriorated sewer with a new 12 -inch high-density
polyethylene pipe. The remaining 185 -feet of 10 -inch clay pipe that extends into Ygnacio Valley Road
remained and needs to be replaced within the next five to 10 -year time frame. The existing sewer segment
has several deficiencies and replacement is complicated due to all the utilities, structures, and Ygnacio
September 21, 2017 Regular Board Meeting Agenda Packet - Page 47 of 91
Page 2 of 4
Valley Road being a major arterial roadway. Furthermore, the project is located near the Highway 24/680
off -ramp and is right across from the Walnut Creek BART Station.
This is an opportune time to complete the pipe renovation and minimize disruption for the affected
property owners and the public. In addition, this work would be completed before the sidewalk restoration
and repaving of Ygnacio Valley Road. Due to the timing of the development projects and potential city
paving moratorium requirements, staff does not have the time necessary to conduct the standard public
bid process and recommends performing this work under change order with an existing contractor. The
construction contract being used allows Central San to add additional sites to the project after award. The
subject work is considered within the scope of the construction contract.
The development project (Vaya) has constructed the large five story wood frame for the new building and
has removed the majority of landscaping on Central San's easement. They are also going to replace much
of the curb and sidewalk frontage along Ygnacio Valley Road. Another development project (Walnut Creek
Village Parking Garage) is planning to construct a covered parking lot and a new condominium building at
the BART parking lot (similar to the Pleasant Hill BART project completed several years ago). All these
developments will be connecting to our sewer system and have paid, or will be paying, their associated
permit and capacity fees.
CE A
Staff has concluded that this sewer project is exempt from the California Environmental Quality Act
(CEQA) under Central San's CEQA Guidelines Section 15302, because it involves replacement of
existing sewer facilities at substantially the same locations and with the same purpose and level of activity
as the facilities being replaced. Any capacity increases are for non -growth inducing, wet weather or
maintenance purposes. This sewer project also is exempt under Central San's CEQA Guidelines Section
15061(b)(3), since it can be seen with certainty that there is no possibility that the activity in question may
have a significant effect on the environment. This certainty is based on Central San's past experience with
numerous sewer construction projects of this nature, the relatively short distances involved, and Central
San's impact -limiting construction specifications. These specifications are standardized general and
special conditions that are made part of the sewer project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with applicable federal,
state, county, district, municipal and local laws, ordinances, orders, and regulations. Approval of this
change order will establish the Board of Directors' independent finding that this sewer project is exempt
from CEQA.
ALT ERNATIVES/CONSIDERAT IONS
nitially, Central San proposed to work with the Vaya developer to include the sewer replacement within the
scope of the development and reimburse them; however, the costs were higher than anticipated and we
elected not to include the work. The Vaya development will be connecting to the sewer downstream of the
proposed sewer work.
Two contractors are currently doing sewer pipe rehabilitation and replacement construction projects for
Central San. Central San staff requested a proposal from both - Cratus, Inc. (Walnut Creek Phase 11
contractor) and K.J . Woods Construction, Inc. (Lafayette Phase 11 and Martinez Phase 5 contractor).
Staff received a proposal from K.J . Woods Construction, Inc.; Cratus, Inc. chose not to propose since
they were committed to other projects.
An alternative would be not to do the construction work as a change order and include the sewer
replacement in a future collection system renovation project, which is not recommended. Staff believes
the work would be more costly due to restoration at the Vaya development and the street moratorium
requirements on Ygnacio Valley Road. Central San could be required to do additional paving
(maximum curb to curb), which would be very costly.
September 21, 2017 Regular Board Meeting Agenda Packet - Page 48 of 91
Page 3 of 4
In addition, the Walnut Creek Village Parking Garage developer has agreed in writing to participate 25 -
percent of the sewer project cost.
FINANCIAL IM PACTS
The cost for the construction work is expected to reach up to $200,000, which includes contractor costs,
contingency, staff time, city permit, and testing. The change order work is estimated to cost approximately
$160,000. The funding for this change order work will be paid for by the Walnut Creek Sewer Renovations
Project - Phase 12, District Project 8435, which is included in the Fiscal Year (FY) 2017-18 Capital
Improvements Budget on page 130 with a FY budget of $1,000,000.
COMMUNITY OUTREACH
The nearby businesses, residents, and City of Walnut Creek will be notified prior to the construction work.
COMMITTEE RECOMMENDATION
The Engineering & Operations Committee reviewed this matter at its meeting held September 12, 20171
and recommended authorizing the change order.
RECOMMENDED BOARD ACTION
Authorize the General Manager to execute a construction contract change order up to $160,000 with K.J .
Woods Construction, I nc. for the sewer replacement at the Ygnacio Valley Road/Lacassie Avenue
Easement in the City of Walnut Creek.
Strategic Plan re -In
GOAL TWO: Strive to Meet Regulatory Requirements
Strategy 1 - Strive to Achieve 100% Permit Compliance in Air, Water, Land and Other Regulations
GOAL FIVE: Maintain a Reliable Infrastructure
Strategy 2 - Facilitate Long-term Capital Renewal and Replacement
ATTACHMENTS:
1. Project Location Map
September 21, 2017 Regular Board Meeting Agenda Packet - Page 49 of 91
Page 4 of 4
ATTACHMENT 1
YGNACIO VALLY ROAD/LACASSIE AVENUE EASEMENT
PROJECT LOCATION MAP
WALNUT CREEKGIC1 1/p��-�-�.�
BART STATION ��`�'P
DETAIL
AREA
z
75B1 -M110 I \
.00 75B 1-M79
Z
75B1- 77 75B1 -RI$
pr
75B1 -W .9 0 Z
� G�PG�O �
t�
5B1 -RD
LACASSIE AVE 7581-M75 7561-M73
Q Manhole
I Reducer
0 Rodding Inle3
t N
Wye 0 40 80
Sewer Main Feet
Central Contra Costa
Sewer Easement Attachment
Sanitary District Ygnacio Valley Road 1
Protecting Public Health and the Environment Walnut Creek
September 21, 2017 Regular Board Meeting Agenda Packet - Page 50 of 91