Central Contra Costa Sanitary District
August 21, 2017
TO: ADMINISTRATION COMMITTEE
FROM: ANN SASAKI, DEPUTY GENERAL MANAGER
REVIEWED BY: ROGER BAILEY, GENERAL MANAGER
SUBJECT: FISCAL YEAR 2016-17 STRATEGIC PLAN ANNUAL REPORT - SUMMARY
OF ACHI EVEMENTS
Attached is Central Contra Costa Sanitary District's Fiscal Year 2016-17 Strategic Plan Annual Report -
Summary of Achievements. The full Board will be asked to receive this annual report next month.
ATTACHMENTS:
Fiscal Year 2016-17 Strategic Plan Annual Report - Summary of Achievements
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 87 of 119
CENTRAL
CONTRA
COSTA
SANITA
DISTRI
FISCAL YEAR 2016-17
STRATEGIC PLAN
ANNUAL REPORT
SUMMARY OF
Page 2 of 33
•
+ •
� „�, ,may, �' • .
dG
t�.• - #-M
i�
Iftow -
ACIIIEVE—.MENTS
Y �
` d
� • _ �.+.
_ r -
August 21. 2017 Regu ar ommi ee Meeting Agenda Packet - Page 88 0r
- - - AN
9 —now
t `0 —
A MESSAGE FROM THE
GENERAL MANAGER
Page 3 of 33
On behalf of the Central Contra Costa
Sanitary District (District) I am proud to
present our accomplishments for
Fiscal Year (FY) 2016-17 of our two-year
FY 2016-18 Strategic Plan. The Strategic
Plan lays out the direction for the District
and draws upon the six Goals adopted by
our Board of Directors and the Effective
Utility Management (EUM) framework.
This approach has enabled the District to
increase efficiencies, fulfill our mission,
and continue in our role as stewards of
the environment. The Plan includes
16 key strategies and 40 initiatives to
address current and future challenges,
and key performance metrics related to
each goal. This report provides an
overview of the many achievements
made by our dedicated and professional
staff, who continually strive to uphold the
District's Mission and Values.
Some of the highlights over the past
year include continuing to achieve
19 years of total compliance with our
wastewater discharge permit and
successfully renewing our
National Pollutant Discharge
Elimination System Permit; completing the
Comprehensive Wastewater Master Plan;
implementing new software and hardware to improve operational efficiency, including the use of
mobile devices in the field; implementing treatment plant operational efficiencies; hosting a large-
scale, award-winning 70th Anniversary Open House Event; and successfully completing the second
Central San Academy.
The District has built a strong culture of providing excellent service to our customers. We will
continue with our commitment to the public and our customers to strive for excellence daily and to
put our values of People, Community, Principles, and Leadership and Commitment first. As we
move forward, we wish to acknowledge that these accomplishments would not be possible without
the leadership and support of our Board of Directors and the continued support and confidence of
our customers.
jq
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 89 of 119
Page 4 of 33
Overview of the M40 40
ission, Vision, Values,
and Goals of the District
The FY 2016-18 Strategic Plan draws upon the work accomplished under previous Strategic Plans.
Many of the goals and strategies have remained the same. However, the initiatives have been
updated to move the District on a continuous path forward as we strive to optimize operations,
streamline processes, and look for innovative technology and methods to manage and contain
costs. The Strategic Plan consists of six goals. Each of these goals has corresponding strategies
and initiatives that are focused on completing the District's Mission and addressing challenges and
opportunities on the horizon. In addition to the initiatives, key performance metrics are tracked to
evaluate the factors that are critical to the success of the goals.
Our Mission
To protect public health and the environment
Our Vision
To be ahigh-performance organization that provides exceptional
customer service and regulatory compliance at responsible rates
Our Values
• People
o Value customers and employees
o Respect each other
o Work as a team
o Community relationships
o Celebrate our successes and learn from our challenges
• Community
o Value water sector partners
o Foster excellent community relationships
o Be open, transparent and accessible
o Build partnerships
o Understand service level expectations
• Principles
o Be truthful and honest
o Be fair, kind and friendly
o Take ownership and responsibility
• Leadership and Commitment
o Work effectively and efficiently
o Promote a passionate and empowered workforce
o Encourage continuous growth and development
o Inspire dedication and top-quality results
14% N
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 90 of 119
Page 5 of 33
Effective Utility Management
The Effective Utility Management (EUM) framework is regarded as the industry standard for
strategic planning and performance metrics monitoring. The EUM framework consists of ten
attributes that describe desired outcomes that are applicable to wastewater utilities. The EUM
served as the framework for developing the initiatives. The initiatives are aligned with our goals
and one or more of the ten EUM attributes, ensuring that the District's priorities are in line with
best management practices.
i-%
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 91 of 119
Page 6 of 33
The following is a summary of the goals and strategies and their alignment with the EUM attributes.
Goal
Strategy
EUM Attribute
Be a Fiscally Sound
and Effective Water
Foster Customer Engagement and
Customer Satisfaction
Goal 1
Awareness
Operational Optimization
Provide Exceptional
Business Operations
Customer Satisfaction
Customer Service
Improve Interdepartmental Collaboration
p p
Employee and Leadership
Environmental
Development
Product Quality
Sustainability
Encourage the Review and Testing of
Goal 2
Strive to Achieve 100% Permit Compliance
Stakeholder Understanding and
Strive to Meet
in Air, Water, Land and Other Regulations
Support
Regulatory
Community Sustainability
Requirements
Strive to Minimize the Number of Sanitary
Infrastructure Strategy and
Sewer Overflows
Performance
Goal 3
Conduct Long Range Financial Planning
Financial Viability
Be a Fiscally Sound
and Effective Water
Manage Costs
Enterprise Resiliency
Sector Utility
Ensure Adequate Staffing and Training to
Operational Optimization
Employee and Leadership
Technolo gyp
Business Operations
Meet Current and Future Operational Levels
Development
Goal 4 Employee and Leadership
Develop and Retain Enhance Relationship with Employees and Development
a Highly Trained Bargaining Units
and Innovative g g Stakeholder Understanding and
Workforce Support
Meet or Exceed Industry Safety Standards Employee and Leadership
Development
Manage Assets Optimally Throughout Their Infrastructure Strategy andPerformance
Lifecycle
Goal 5 Enterprise Resiliency
Maintain a Reliable Facilitate Long -Term Capital Renewal and Infrastructure Strategy and
Infrastructure Replacement Performance
Protect District Personnel and Assets from Enterprise Resiliency
Threats and Emergencies p
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 92 of 119
Augment the Region's Water Supply
Water Resource Sustainability
Goal 6
Embrace
Evaluate Business Processes and Optimize
Operational Optimization
p p
Technolo gyp
Business Operations
Innovation, and
Reduce Reliance on Non -Renewable Energy
Community Sustainability
Environmental
Sustainability
Encourage the Review and Testing of
Operational Optimization
p p
Promising and Leading Technology
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 92 of 119
Page 7 of 33
Initiative Achievement Summary
The following provides a brief description of the level of achievement for each of the initiatives and
the factors that contributed to their achievement.
Goal 1
Provide Exceptional
Customer Service
Strategy 1
Foster Customer Engagement
and Awareness
Invest in Business Process Changes and Technologies to Effectively
Increase Access to District Information and Promote Customer Care,
Convenience and Self -Service
Achievement: This initiative is ongoing. The District installed
a display monitor in the main lobby for customer information.
The monitor provides a continuous presentation of information
about the wastewater treatment process; plant and collection
system maintenance; the Central San Academy; and
awareness on the hazards of fats, oils and grease, flushable
wipes, and pharmaceutical waste in the wastewater system.
The District also actively engages customers through social
media including Facebook, Twitter, YouTube and the
Central San Blog to build customer awareness on issues
of importance.
In the upcoming fiscal year, the District will be updating its
website with the goal of improving the customer experience;
improving and facilitating communication of important business
information; and delivering the information that our customers
expect and want from the District.
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 93 of 119
Page 8 of 33
Increase Customer Understanding and Support for Key Issues Facing the District
Achievement: This initiative is ongoing. The District successfully completed the second
Central San Academy, a six-week program which focuses on educating our customers on the
mission of Central San, including curriculum that covered our infrastructure, future regulations,
recycled water opportunities, budgeting, rates and financing.
The District also developed video public service announcements that focused on important
Central San programs, operations and pollution prevention messages reaching 34.8% of
households in our service area (delivering the message to an estimated 113,000-137,000 viewers).
Regarding capital improvements, the District provided compelling outreach and engagement for
the Comprehensive Wastewater Master Plan (CWMP) and infrastructure improvements including
holding three public workshops (two for residential customers and one for commercial customers)
to discuss the CWMP recommendations, infrastructure improvements, financial outlook, and other
District programs and services. The District also focused CWMP outreach in creative ways
through presentations to city councils, taxpayer associations, televised broadcasts, Pipeline
newsletter articles, community events and meetings.
The District additionally grew educational outreach through our publications and programs. More
than 4,500 students were reached through our Science, Technology, Engineering, and
Mathematics Program, and pollution prevention and career development information.
Build and Maintain Relationships with
Federal, State and Local Elected Officials
and Key Stakeholder Groups
Achievement: This initiative is ongoing. Members of the
Board of Directors and the General Manager met with mayors,
city council members, and/or city managers within the District's
service area. Members of the Board of Directors also spoke at
CIENTRAL CONTRA (_ 71,
AkA_ JP * dft council meetings in various cities providing updated information
on the District. Additionally, Board of Director Members
throughout the year have met with Federal and State elected
officials through member conferences in Sacramento and
Washington D.C. and in -District meetings to discuss regional
water issues; legislation effecting the District; future infrastructure improvement plans; and other
important issues.
The District also hosted a large-scale, award-winning 70th Anniversary Open House event that
brought over 1,000 customers and 20 elected officials to the District to learn more about programs,
services, operations, and to take tours of the treatment plant and Household Hazardous Waste
Collection Facility.
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 94 of 119
Page 9 of 33
Provide High Quality Customer Service
Achievement: This initiative is ongoing. The District takes considerable pride
in the services that we provide to our customers, and we have built a strong
culture of providing excellent service. Over the past year, Operation Collection
Systems staff have arrived onsite to all emergency calls on average within
39.5 minutes; and for those calls, our customers rated our services 3.96 out of
4.0. On our capital improvement construction projects, we strive to minimize
disruption to the public. On those projects, our customers have given us a
satisfaction rating of 97%. At our Development Services permit counter, our
customers have rated our services at 95%. Individual customers routinely write
in to the District expressing appreciation for the level of respect and quality of
service they receive.
Annually, we provide our staff with customer service training. This past year all
employees were provided with training on the Roles and Responsibilities of
Public Employees.
Strategy 2
Improve Interdepartmental Collaboration
Foster Employees' Understanding of District Operations
and Their Role in Our Success
Achievement: This initiative is
ongoing. The District provides a
monthly award-winning employee
newsletter, the Lateral Connection,
that helps connect important District
initiatives with all employees. It also
serves to empower employees to
develop new processes and
procedures to provide better service
to internal and external customers.
This is made possible by the
amount of multi -departmental
information shared in the employee
newsletter.
In the upcoming fiscal year, the
District will be updating its internal
intranet site. Our staff will benefit
from the modernizing of the site by
more easily accessing District
policies, procedures, Division information, and other documents related
to ongoing projects.
�j
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 95 of 119
IF.,
f.TuVAVC;0MNP.* 6°apa&fWrWrV.,<hI 4k� -7 �J19wd11}est
Page 10 of 33
Increase Internal Partnerships
Achievement: This initiative is ongoing. The District has employed
numerous multi -departmental teams to review critical projects. Examples of
this coordination are the following projects:
• Public Private Partnership for Development and Implementation of
a Full -Scale Bioenergy Facility (Planning, Regulatory, Plant
Operations, Plant Maintenance, Finance)
• Solids Handling Facility Wet Scrubber Pilot Project (Planning,
Engineering, Regulatory, Plant Operations, Plant Maintenance)
• Districtwide Vulnerability Assessment (Planning, Plant Operations,
Finance, Risk Management, Information Technology)
• Project Management Information System Procurement (Planning,
Engineering, Finance, Information Technology)
The District has also continued the Information Technology Leadership
Committee, which is a multi -departmental team of employees involved in
the review and analysis of information technology projects, processes and
procedures.
A,
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 96 of 119
Page 11 of 33
How are we doing?
lqwr�l
--
Average onsite response time
for collection system
Less than 20 minutes
34.25 minutes
emergency calls, during
working hours
Average onsite response time
for collection system
Less than 30 minutes
37.88 minutes
emergency calls, after hours
Average customer service
At least 3.8 out of 4.0
3.96
rating for emergency calls
Average customer satisfaction
Greater than 95%
97.5%
rating on construction projects
Average customer satisfaction
rating on permit counter
Greater than 95%
94.8%
interactions
Number of students served by
Greater than 2,200 per
year
2,797
our education programs
Number of District employees
attending annual customer
At least 50% of all District staff
7.3%
service training
Number of participants on Greater than 563
treatment plant tours 150 participants per year
Number of participants at Greater than 416
speaker bureau presentations 400 participants per year
)-
Number of students attending Greater than ''
Citizens Academy 30 participants per session 36
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 97 of 119
Page 12 of 33
Goal 2 Strategy 1
Strive to Achieve 100% Permit
Strive to Meet Compliance in Air, Water, Land,
Regulatory and Other Regulations
Requirements
Renew Treatment Plant
National Pollutant Discharge Elimination System Permit
which Expires on March 31, 2017
Achievement: This initiative was met. In April 2016, District staff established a permit
application review team to successfully achieve renewal of the District's National Pollutant
Discharge Elimination System (NPDES) Permit. Staff submitted a report of waste discharge to
the San Francisco Bay Regional Water Quality Control Board on September 30, 2016. On
April 12, 2017, the San Francisco Bay Regional Water Quality Control Board adopted the District's
new NPDES Permit. The permit became effective on June 1, 2017 with an expiration date of
May 31, 2022.
Meet Existing Regulations and Plan for Future Regulations
Achievement: This initiative is ongoing. The District continues to maintain operations to ensure
compliance with all permit requirements. The District met all requirements of our NPDES Permit
and completed 19 consecutive years of 100% compliance. The District also met all requirements
of Title 22 of the California Code of Regulations related to recycled water.
The Environmental and Regulatory Compliance Division staff developed and implemented a permit
matrix to track all regulatory permits. The staff also provided an annual update on significant
regulatory issues to the Real Estate, Environmental and Planning Committee in November 2016
and provides periodic updates as necessary.
1
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 98 of 119
Page 13 of 33
Foster Relationships with Regulatory Agencies
Achievement: This initiative is ongoing. District staff continues to foster
positive working relationships with the San Francisco Bay Regional Water
Quality Control Board, State Water Resources Control Board, Bay Area Air
Quality Management District, United States Environmental Protection Agency,
and other regulatory agencies through active participation in meetings,
workshops and routine engagement.
,... -----r----- - -
Monitor and Track Proposed and Pending
Legislation/Regulatory
Changes That May Impact District Operations
Achievement: This initiative is ongoing. Through active participation in
professional associations and engagement with regulatory agencies, District
staff continues to monitor proposed and pending legislation/regulatory changes
and analyze potential impacts on the District's operations. Environmental and
Regulatory Compliance Division staff has submitted comment letters to
regulatory agencies and has appeared before regulatory agency boards to
engage rule developers on issues that may have significant impacts.
Actively Manage Greenhouse Gas Emissions in the Most Cost
Effective and Responsible Manner
Achievement: This initiative was met. The District successfully maintained
the annual anthropogenic greenhouse gas (GHG) emissions below 25,000
metric tons for the calendar year 2016. The annual 2016 GHG inventory report
was submitted to the California Air Resources Board on March 3, 2017. The
Environmental and Regulatory Compliance Division staff issues internal
monthly GHG emission inventory updates to ensure that operational strategies
are aligned with the internal GHG emissions target. The 2015 Greenhouse
Gas Inventory Summary and Verification Report was issued to internal staff in
October 2016.
,at
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 99 of 119
Page 14 of 33
Strategy 2
Strive to Minimize the Number of
Sanitary Sewer Overflows
Complete the Collection System Scheduled
Maintenance on Time and Optimize Cleaning
Schedules to Improve Efficiencies
Achievement: This initiative was met. The District continues to maintain the
sewer collection system to minimize sewage stoppages and overflows. In the
past year, the District has transitioned its computerized maintenance
management system (CIVIMS) from Accela to Cityworks. With the new CMMS
system, the District has also implemented paperless work orders. Staff in the
field are using mobile devices to access work orders, past work history, maps,
and videos. This has enabled staff to respond to overflows and stoppages
more efficiently by having information more readily available. In FY 2016-17,
744 miles of sewer pipes were cleaned; and of those miles, 98.58% were
cleaned on-time and on -schedule.
Continue the Pipeline Condition Assessment and Cleaning
Quality Assurance Program Using the System Wide Closed
Circuit Televising Program
Achievement: This initiative is ongoing. The District has a goal to televise all
sewers on average once every seven years. In FY 2016-17, 195 miles of sewer
pipes were televised; 59 miles were televised by District staff and 136 miles
were televised by a contractor. In addition to televising our sewers to assess
their condition, a select number of sewer lines are also televised after they are
cleaned to determine the efficiency of our cleaning operations. In FY 2016-17,
22 miles of sewers were televised for quality assurance purposed, and 94.34%
had a passing rating.
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 100 of 119
Page 15 of 33
How are we doing?
NPDES compliance Zero violations Zero violations
Title V compliance Zero violations Zero violations
Recycled Water Title 22
Compliance Zero violations Zero violations
Sanitary sewer overflows Less than 3.0 spills per 100 2.53
miles of pipeline
Spills to public water Less than 3 9
Percent of spills less than Greater than 95% 88.55%
500 gallons
Pipeline cleaning schedules Greater than 95%o
completed on time 98.58 /o
Pipeline cleaning quality On at least 3% of pipeline
assurance/quality control cleaned on an annual basis 3.04%
Annual source controls Greater than 98%0
inspections completed on time 95 /o
Pipeline cleaning quality
assurance/quality control 100% 100%
passing rate
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 101 of 119
Page 16 of 33
Goal 3
Strategy 1
Be a Fiscally Sound
Conduct Long Range
and Effective Water Financial Planning
Sector Utility
Ensure Rate Structure is Consistent with Cost of Service Principals
Achievement: This initiative is ongoing. The two-year rate structure adopted for FY 2017-18 and
FY 2018-19 reflect the cost of service principles established in the 2015 Cost of Service Study. As
part of the Mentorship Program, one of the mentee projects was to conduct a survey of mixed-use
rate structures. This information will be reviewed by a consultant in the upcoming fiscal year to
determine what, if any, modifications should be made to the District's rate structure. Mixed-use
rate changes will be reviewed and any changes will be included in FY 2019-20 rate review
Improve the Application and Processing of Capacity Fees for
Consistency Across User Classes
Achievement: This initiative is ongoing. Staff reviewed 39 Multi -Use Developments and
identified changed uses. Where the usage has changed, staff is working on collecting these
outstanding fees. A consultant has been engaged to assist with assessing capacity fees for
accessory dwelling units, patio dining, and mixed -used developments in FY 2017-18. Staff has
developed a sampling plan for a sewer permit application audit and conducted a survey of
12 statewide wastewater agencies for capacity fee methodologies. The consultant will use this
information in accessing our method of calculating capacity fees.
014
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 102 of 119
Page 17 of 33
Develop along-Range Debt Management Policy
Achievement: This initiative was met. The Administration Committee reviewed a draft Debt
Management Policy and Administrative Procedures in June and July 2017. The debt policy was
developed in accordance with SB 1029. Additional feedback has been obtained at each meeting
and will be reflected in the revised drafts before being brought to the Board of Directors for
potential adoption in August 2017.
Develop Alternatives for New Revenues and Funding Sources
(i.e. Interagency Agreements, Services, Recycled Water)
Achievement: This initiative is ongoing. During the year, staff met with Contra Costa Water
District to discuss the framework for a wholesale agreement for the Concord Community Reuse
Project. Staff continues to look for innovative ideas to increase revenues for the District.
Strategy 2
Manage Costs
Perform Targeted Audits of
Critical/High Risk Functions
or Processes
Achievement: This initiative is ongoing.
As part of the Mentorship Program, a
project was initiated to identify high
cost/high risk functions in each Division
that could be audited. A list of areas of
opportunities has been established.
Funding was included in the FY 2017-18
Budget for an outside auditor and it is
anticipated that audits will be performed
in FY 2017-18.
414
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 103 of 119
Page 18 of 33
Perform Optimization Studies of Treatment Plant and Field
Operations to Reduce Costs
Achievement: This initiative is ongoing and has been expanded beyond the Operations
Department to the entire District. In December 2016, staff made great strides toward the objective
of creating a framework to track optimizations and their results by assembling a report of
completed and planned optimizations throughout the District. This report was used to establish a
mechanism to record the optimizations, status updates and performance measurements moving
forward. Additionally, a vacant position has been repurposed to a Management Analyst which will
assist in supporting and growing the District's innovative culture and continue to encourage more
achievements such as these:
• Development of a portable oil filtration and flushing system.
• Installation of fixed vibrations sensors and monitoring of the induced draft fan to provide
early notification of elevated vibration and to allow for predictive maintenance.
• Reduction of 35% in backwashes per week at the Filter Plant by using three filters
instead of one or two, which processes more water, increasing the time between filter
backwashes, thereby reducing labor and energy costs
• Modification of the caustic soda injection point from the first stage to the quench stage
for the wet scrubber of Furnace No. 2 and optimizing the injection rate, to save future
chemical costs which still ensuring compliance.
Evaluate and Implement Risk Management
Practices to Minimize Loss
Achievement: This initiative is ongoing. On an annual basis, the Risk Management Section
presents a Risk Management Report to the Board of Directors. The last report was presented in
September 2016. The report includes annual claims assessments and trend analysis in addition to
other key metrics. Additionally, after major losses or incidents, staff will prepare an "after action" or
"lessons learned" report. The last reports were completed in August 2016 for the flood loss at
La Espiral in Orinda and in December 2016 related to efforts to collect late commercial capacity
fees. On a routine basis after every sewer overflow or stoppage, the Operation Collection Systems
staff reviews the specific details of the event and assesses changes that may need to be
implemented to prevent future occurrences or losses.
04
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 104 of 119
Page 19 of 33
How are we doing?
Standard and Poor's
AAA
AAA
Credit Rating
Debt service coverage ratio
Greater than 2.0 times
9.82
Sewer Service Charge less
Maintain service affordability
than median of Bay Area
Target Met
agencies
Actual reserves as a
100%
100%
percentage of target
Operating expenditures
as a percentage of
Greater than 90%
92.5%
operating budget
Workers Compensation
Less than 1.0
0.67
experience modifier
Provide modified duty for
Return to work
greater than 80% of
95%
occupational injuries
Self-insurance reserves as a 100%°
percentage of target 100 /°
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 105 of 119
r
0
k7
Goal 4
Strategy 1
Page 20 of 33
Develop and Retain ' Ensure Adequate Staffing and
a Highly Trained Training to Meet Current and Future
and Innovative Operational Levels
Assess, Develop, and Implement District -Wide Training Needs
Achievement: This initiative is ongoing. During the year, the Human Resources Section held
five mandatory human resources related training sessions for all District supervisors and twelve
human resources related brown bag sessions open to all District staff. Specialty courses on
business and technical writing, customer service, and understanding the roles and responsibilities
of public employees were also held.
In the upcoming fiscal year, staff will be issuing a request for proposal to hire a training consultant
to assist in the development of specific training plans for each operational section.
Develop and Train Our Future Leaders
Achievement: This initiative is ongoing. In FY 2016-17, the District initiated the new Mentorship
Program with four participants working on various projects with different Management mentees
each quarter. Some of these mentee projects, which were presented to the Board of Directors,
included development of a training plan for maintenance staff, an assessment of the impact of
patio dining on capacity fees, and optimization of the data transfer between environmental
compliance staff and development review staff.
The District also continued the successful Management Leadership Academy program with
20 participants engaged in the six-month program. The District also offered one-on-one coaching
sessions to all Management employees.
Outside of District staff, the District partnered with Earn and Learn East Bay to increase student
exposure and engagement with Science, Technology, Engineering and Mathematic Program
careers and to encourage students to pursue a career in the water and wastewater industry. For
these efforts, the District was awarded the Youth Advocacy Award from the Workforce
Development Board of Contra Costa County.
Aq
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 106 of 119
Strategy 2
Enhance Relationship with Employees
and Bargaining Units
Cultivate a Positive Work Culture and Promote Teamwork
Achievement: This initiative is ongoing. The District continues to recognize
staff at Board of Directors meetings for their award-winning achievements
including the California Water Environment Association — Plant of the Year,
Safety Program of the Year, Public Outreach Program of the Year, Gimmick and
Gadget of Award; the National Association of Clean Water Agencies Platinum
Peak Performance Award (19 consecutive years compliance with treatment plant
discharge standards); Achievement of Excellence in Procurement Award
(6 consecutive year); and Comprehensive Annual Financial Report Award
(16 consecutive year). The District further received a California Association of
Public Information Officials Award for the Lateral Connection newsletter for
showing a "commitment to employee information and staff relations."
Staff is also encouraged to work together as a team and does so on a regular
basis on capital improvement projects and as mentioned under Goal One,
Strategy Two, on special studies and projects.
Sustain and Grow Collaborative Relationships with the
Labor Bargaining Units
Achievement: This initiative is ongoing. The District continues its quarterly
Labor Management meetings with the Management Support/Confidential Group
employees. We completed a District -wide Classification Study, a Total
Compensation Study, and initiated labor negotiations with the three bargaining
units. The goal is to complete labor negotiations prior to the expiration of the
current contracts in December 2017.
The General Manager also continued his bi-monthly lunches with the two main
bargaining group representatives and his monthly "Meet the GM" lunches with
individual work units.
Page 21 of 33
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 107 of 119
Page 22 of 33
Strategy 3
Meet or Exceed Industry Safety Standards
Achieve Consistent Improvement on State of California
and Bay Area Industry Injury Rate
Achievement: This initiative was met. The District continued to monitor accident/incident
causal factors and reported back to the respective departments, safety teams, and the
Board of Directors. This awareness highlighted the hazards and identified corrective measures
to reduce the number of incidents. In combination with education through the Lateral Connection,
safety tailgates and training sessions has resulted in a reduction of the injury incident rate for
FY 2016-17 to 3.8 compared to the Bay Area/State of California rate of 7.4.
The District received the Plant of the Year: Safety Award from the California Water Environment
Association — San Francisco Bay Section in Fall 2016 and was awarded the Plant of the Year:
Safety Award statewide in Spring 2017.
Enhance the Safety Culture Through Improved Training and Communications
Achievement: This initiative is ongoing. The District continues to keep up to date and
communicates safety regulatory changes and safe practices to District staff via distribution of the
Cal/OSHA Reporter, safety articles in the Lateral Connection, and through training and tailgates
conducted by Safety staff.
The District began implementation of a Safety Data Sheet management online database which
allows employees to access chemical hazard information via a mobile device application and web
browser. The Safety Data Sheet documents are automatically kept up to date to ensure the most
accurate information.
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 108 of 119
Page 23 of 33
How are we doing?
Metri FY 2016-17 Target Results
Average time to fill vacancy
(from request to hire)
Percentage turnover rate to
remain at or below
industry average
Average annual training hours
per employee
Actual versus budgeted usage
of tuition reimbursement
Percentage of performance
evaluations completed on time
Employee injury and illness
lost time incident rate
Less than 60 days 53.25 days
Less than 3.4% 9.14%
Track in FY 2016-17 Average of 7.46 per FTE
Set target for FY 2017-18
Greater than 80% 25.59%
1000 0 44.5%
Less than BLS California
Sewage Treatment Facilities 3.8
Rate of 7.4
41D
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 109 of 119
Goal 5
Maintain a Reliable
Infrastructure
Strategy 1
Manage Assets Optimally
Throughout Their Lifecycle
Page 24 of 33
Implement Board of Directors Approved Recommendations from the
Comprehensive Wastewater Master Plan and Condition Assessment
Achievement: This initiative was met. The District completed the CWMP for the collection
system and the treatment plant. The plan was presented to the Board of Directors in June 2017,
and its recommendations and condition assessment findings have been incorporated into the
current Capital Budget and the 10 -year Capital Improvement Plan.
Update the Consequence of Failure Matrices
Achievement: This initiative was met. As part of the CWMP, the consequence of failure scores
were determined for gravity sewers, pumping stations and forcemains. The consequence of failure
matrix for the treatment plant was updated by District staff.
Implement the Reliability Centered Maintenance Program
Achievement: This initiative was met. The Plant Maintenance Division staff has been trained
on reliability centered maintenance. During the past year, they performed two reliability centered
maintenance pilots; one on the Dewatering System, Centrifuge Subsystem and one on the
Steam System, Waste Heat Boiler Subsystem. This is a systematic approach to developing a
comprehensive maintenance program based on asset criticality and consequence of failure. It also
establishes a repeatable program with documented processes and procedures. Pilot results were
presented to the Board of Directors on April 6, 2017 as part of the Asset Management update. A
framework has been developed and implemented to improve maintenance efficiency based on
reliability centered maintenance. The framework provides methods that identify and analyze the
equipment and systems that cause a majority of reactive work orders based on cost and work
order count. Additionally, the framework includes methods to analyze the remaining equipment
and systems to an appropriate level of detail, resulting in the application of the most effective
preventative maintenance task for all treatment plant equipment and systems.
4D
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 110 of 119
Manage and Maintain Current Equipment and Vehicle Fleet
to Provide Maximum Value
Achievement: This initiative is ongoing. The District continues to maintain
our vehicles and equipment to minimize unscheduled downtime. During this
past year, the Vehicle and Equipment Shop has transitioned to a new
CMMS from Accela to Cityworks and is using field tablets to perform vehicle
inspections, and input work orders and inventories.
There were 966
services on vehicles
with an uptime of
100%. The District has
also entered into an
agreement with Verizon
NetworkFleet to pilot
test automated vehicle
location and vehicle
diagnostic software.
The pilot study will take
place during the month
of July 2017 and then a
decision will be made
for full implementation.
Strategy 2
Facilitate Long -Term Capital Renewal
and Replacement
Integrate the Data from the Asset Management Program into
the Analysis of Long Term Capital Improvement Needs Based
on the Board of Directors Approved
Comprehensive Wastewater Master Plan
Achievement: This initiative was met. Planning staff completed the
implementation of the InfoMaster® software. The InfoMaster® software
leverages data from the Asset Management Program such as closed circuit
televised scores and cleaning frequency to calculate the likelihood of failure
and considers likelihood of failure and consequence of failure to analyze
and prioritize gravity sewer pipe renovation needs.
Also, as stated previously, the District completed the CWMP which includes
near-term and long-term recommendations that are coordinated with the
condition assessment findings. The CWMP will be updated on a routine
basis, likely every five years, and will be referenced during the annual
budget process to incorporate long-term (10 -plus years) recommendations
and update the 10 -year Capital Improvement Program.
Page 25 of 33
40
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 111 of 119
Page 26 of 33
Implement Business Case Evaluations, Including Life -
Cycle Cost, into Proposals for New Capital Improvement
Program Projects to Determine Most Cost -Effective
Projects and Solutions for Projects That Were Not
Identified in the Approved CWMP or Already Included in
the Capital Improvement Budget
Achievement: This initiative was met. Staff developed and started
using business case evaluations, including life -cycle cost and triple
bottom line analysis, when evaluating new capital projects to
determine most cost-effective projects and solutions; the most recent
example being the Cogeneration System Improvement Project.
Strategy 3
Protect District Personnel and Assets from
Threats and Emergencies
Enhance Our Capability to Mitigate, Prepare,
Respond and Recover from Emergencies
Achievement: This initiative is ongoing. Risk Management staff
provided a presentation to the Board of Directors in February 2017 on
the District's Emergency Management Program, which included an
assessment of the District's response capability and the components
of our Program. The Program includes plans, training,
communications, supplies and equipment, and coordination. Our
Emergency Operations Plan was updated in September 2016.
District staff is also currently participating in the multi jurisdictional
Local Hazard Mitigation Plan update along with staff from 35 other
agencies, including Contra Costa County. The update process began
in November 2016, and we have submitted all updates specific to the
District. The Plan is being finalized for Federal Emergency
Management Agency review. Regarding training, the annual
Emergency Operations Center activation exercise was held in
September 2017.
The Information Technology staff procured the services of a remote
co -location facility to replicate server and application data to improve
the ability to recover from a disaster or prolonged system outage.
Also, a new tape backup system was implemented to compliment the
primary disk based backup system, which provides an additional
viable recovery method.
4)
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 112 of 119
Page 27 of 33
Evaluate and Implement Appropriate Improvements to Our
Security Program to Meet New or Evolving Threats
Achievement: This initiative is ongoing. The District completed a comprehensive Security
System Study, which included physical security assessments of District facilities. This report is
scheduled to be presented to the Board of Directors in August 2017. The recommendations
include consolidation of security monitoring, standardization, enhanced security culture and
policies, and specific security improvement recommendations for District facilities. Additionally,
enhanced access control measures have been implemented in the lobby area of the Martinez
Headquarters Building.
The Information Technology staff made a presentation to District staff focusing on security
awareness that emphasized common cyberattack tactics and how to protect against them. Key
security applications were upgraded which provided enhanced malware detection, prevention, and
removal capabilities. A mandatory password change was implemented for all District employees.
Also, all legacy servers and workstations running insecure operating systems have been retired.
Ito
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 113 of 119
Page 28 of 33
How are we doing?
Metric
&L
FY 2016-17 Target
Mak
Safety work orders completed
100%
93.5%
on time
Regulatory Title V work orders
100%
95.03%
completed on time
Planned treatment plant
preventative maintenance
Greater than 95%
87.8%
completed on time
Complete implementation
By first quarter of 2017
Completed
of Infomaster
Miles of pipeline replaced Greater than 1 % of assets 0.33%
Capital expenditures as a 89.1%
percentage of capital budgeted Greater than 90%
cash flow *Results remain under review
Information system uptime
(excluding planned 100% 99.99%
maintenance)
Data backup and recovery Zero lost data Zero lost data
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 114 of 119
� 1 t c
Embrace Technology,
Innovation, and
Environmental
Sustainability
Page 29 of 33
Strategy 1
Augment the Region's Water Supply
Explore Partnering Opportunities
(e.g. Contra Costa Water District and East Bay Municipal Utility District)
Achievement: This initiative is ongoing. District staff continues to pursue discussion and
interest in the potential projects identified in the District's Wholesale Recycled Water Study.
In FY 2016-17, staff conducted meetings to discuss the District's potential supply of recycled
water with the U.S. Bureau of Reclamation, Dublin San Ramon Services District, and
Zone 7 Water Agency.
In addition, the District's General Manager represented the Bay Area Clean Water Agencies
on the Bay Area Regional Reliability Task Force, a stakeholder group charged with reviewing
and providing input on the Bay Area's planning efforts to establish a resilient water supply.
The General Manager was instrumental in promoting a regional exchange program that
has become one of the top recommendations of this regional planning study, which was jointly
funded with the United States. Bureau of Reclamation.
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 115 of 119
Page 30 of 33
Develop a Satellite Recycled Water Facilities Program
Achievement: This initiative is ongoing. In FY 2016-17, the District
executed a Planning Agreement with the Diablo Country Club and initiated
the environmental review process, including completion and release of the
Initial Study and Notice of Preparation of an Environmental Impact Report in
compliance with the California Environmental Quality Act, and conducting
two Open House public meetings to receive input on the project. In
FY 2016-17, District staff also supported the Diablo Country Club's efforts
to issue a request for proposals to procure the design -build team for the
project.
Strategy 2
Evaluate Business Processes and Optimize
Business Operations
Perform Business Process Mapping
and Re -Engineering
Achievement: This initiative is ongoing. Staff met with our current
Enterprise Resource Planning (ERP) vendor, SunGard, to discuss
optimization. Select improvements were made to the purchasing process,
and ERP system limitations were identified. The District also entered into an
agreement with the Government Finance Officers Association to assess the
District's readiness to transition to a new ERP system. The scope of this
agreement includes the analysis and documenting of our current business
processes; an assessment of areas for optimization; requirements for a new
ERP system; an assessment of organizational readiness; and assistance in
the procurement of a new ERP. It is anticipated that this work will be
completed by the fall of 2017.
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 116 of 119
Page 31 of 33
Strategy 3
Reduce Reliance on Non -Renewable Energy
Explore Opportunities for Self -Generation, Conservation,
and Efficiency Based on the Board of Directors
Approved Comprehensive Wastewater Master Plan
Achievement: This initiative is ongoing. District staff routinely tracks
energy usage and provides a summary of usage to the Board of
Directors on a quarterly basis. An Energy Policy (BP027) was �
presented to and approved by the Board of Directors in August 2016,
which includes criteria for evaluating energy generation projects. An
energy self-sufficiency assessment was completed as part of the CWMP.
Recommendations for energy efficiency improvements and other
improvements to strive towards net zero energy are included in the
CWMP and were presented to the Board of Directors in 2016 and 2017. Ilk
The District has completed installation and start-up of the solar
photovoltaic systems at the Household Hazardous Waste Collection
Facility and Collection System Operations Building. We will be pursuing
solar photovoltaic opportunities for the treatment plant and/or buffer
properties in FY 2017-18.
The District is also pursuing public-private partner interest in a Bioenergy
Facility that will produce renewable energy and process a portion of the
District's solids. A request for interest for innovative bioenergy projects, �
such as gasification and other solids to energy processes, was issued
and letters of interest were received in June 2017.
August 21, 2017 Regular Committee Meeting Agenda Packet -Page 117 of 119
Page 32 of 33
Strategy 4
Encourage the Review and Testing of Promising and Leading
Technology
Expand and Improve the Use of Cost Effective Mobile Computing
and Communication Technologies
Achievement: This initiative is ongoing. The District implemented new software and
hardware to improve operational efficiency, including implementation of a new CMMS,
Cityworks. As part of this implementation, the District also rolled out mobile devices in the
field for maintenance staff to use with the Cityworks CMMS system to improve efficiency and
access to information. The District also rolled out mobile devices to the Environmental
Compliance staff to automate the inspection process and provide current information in the
field.
Other efficiencies include the implementation of a streamlined Section 125 Flexible Spending
Account plan which includes a debit card, mobile application, a third -party administrator to
process all claims, and a mobile application (Ben IQ) which contains information on all District
benefits.
Continue Developing and Investing in Cost Effecti
Innovation, Technology, and Applied Research and
Development
Achievement: This initiative is ongoing. The Applied
Research Committee continues to meet on a quarterly
basis to discuss pilot and optimization opportunities.
The District is completing a comprehensive pilot of new
wet scrubber technology as part of the Solids Handling
Facilities Improvements Predesign Project. The pilot plant
began operation in May 2017 and is scheduled for
completion by September 2017.
The District is also part of a consortium of organizations and public agencies led by the
Water Environment and Reuse Foundation that was selected by the Department of Energy to
plan and design a three -to -five dry tons per day, innovative bioenergy pilot plant. The District
was selected as the host site for the pilot plant, which is 50% funded with a $1.2 million grant
from the Department of Energy. The District hosted the project kickoff workshop in June 2017
where over 30 attendees from across the United States and Canada were in attendance.
The District is also currently evaluating several other innovative nutrient removal technologies
for potential pilot projects, such as aerobic granular sludge and membrane aerated biofilm
reactors.
�a
August 21, 2017 Regular Committee Meeting Agenda Packet - Page 118 of 119
Page 33 of 33
How are we doing?
and EnvironmentalSustainability
W liar I
ift FY 2016-17 Target
Total gallons of recycled water
Greater than 240 million
distributed to external
gallons per year
g Y
204,122,430 gallons per year
customers
Maximum residential fill station
15 minutes
Less than 5 minutes
customer wait time
Gallons of recycled water
Greater than 14 million gallons
distributed at the residential
perY ear
4,833,536 gallons per year
fill station
Gallons of recycled water
Greater than 4 million gallons
199,511 gallons per year
g Y
distributed at truck fill program
per year
Greater than
kWh of electricity produced 18 million kWh per year
(reported as a rolling average)
kWh of solar power produced
at Collection System Greater than 200 kWh per year
Operations and Household (reported as a rolling average)
Hazardous Waste
Pilot test new and
promising technology
Present research papers
and findings
Greater than 3 pilot tests or
reviews per year
Greater than 3 papers per year
79.3 million kWh
136,215 kWh
5
5
Ail