HomeMy WebLinkAbout04. Review draft Position Paper to authorize the General Manager to execute a Professional Engineering Services Agreement with V.W. Housen and Associates with a cost ceiling of $780,000 for the preliminary design of the Pump Station Upgrades Project 4■
..�_ Central Contra CostaSanitary District
y-
BOARD ODIRECTORS
POSITION P
�PSP
Board Meeting Date: July 20, 2017
Subject: AUTHORiZE THE GENERAL MANAGER TO EXECUTE A PROFESSIONAL
ENGINEERING SERVICES AGREEMENT WITH V.W. HOUSEN AND
ASSOCIATES FOR DESIGN SERVICES UNDER THE PUMP STATION
UPGRADES, DISTRICT PROJECT 8435
Submitted By. Initiating Dept.fDiv..
Amanda Schmidt —Associate Engineer Engineering and Technical Services/ Capital
Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION
S. Mestetsky—Senior Engineer
E. Lopez—Capital Projects Division Manager
JM. Petit— Director of Engineering and Technical Services Roger S. Bailey
General Manager
ISSUE: Board of Directors authorization is required for the General Manager to execute a
professional engineering services agreement in an amountreater than $100 000.
g ,
BACKGROUND: In 2015, capital Projects initiated an evaluation of the Morag a and
Orinda Crossroads Pumping stations at the request of Operations due to several
deficiencies with the standby generator systems, electrical and instrumentation concerns
and other equipment identified for near term replacement. The most impactful item
identified was replacement of the 1 ,000-horse power Waukesha diesel (circa en ines 1959g )
at both stations. staff hired V. W. Housen and Associates (VWHA) to assist in the roject
project
and prepared a basis of design report with options to replace the engines and other station
improvements.
Concurrently, the Comprehensive Wastewater Master Plan identified several structural
mechanical, electrical, and instrumentation improvements needed at the Martinez
Fairview, Maltby, and Flush Kleen pumping stations. These stations have multiple'
concerns, including reliability of existing equipment and infrastructure, corrosion, are prone
to fl
coding, and have some pumping capacity limitations. central San staff decided to
package these stations with Mora a and Orinda crossroads to form one all-encompassing
encompassing
pumping station project, vwrhich has been included in the current Capital Improvements
p p
Budget titled Pump Station Upgrades Project, District Project 3435.
In addition, staff sought a single engineering consultant to coordinate andre are the
p p
predesign work and continue final design services based on the recommendations
provided, while focusing on the most critical elements identified in the1
ro'ect.
p
Page 1 of 4
POSITION PAPER
Board Meeting Date: July 20, 2017
Subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A
PROFESSIONAL ENGINEERING SERVICES AGREEMENT WITH V.W.
HOUSEN AND ASSOCIATES FOR DESIGN SERVICES UNDER THE
PUMP STATION UPGRADES, DISTRICT PROJECT 8436
The improvements identified and included in this project are aimed at addressing the
following drivers:
* Providing long-term reliable wet weather pumping;
0 Provide firm pumping capacity at all pumping stations;
0 Replace and upgrade the emergency backup power systems;
0 Replace or rehabilitate the electrical, instrumentation, and controls at allpump
stations;
0 Safety improvements and implementing recommendations from the Arc-Flash Study
completed in 2015;
0 Equipment replacement (flow meters, variable frequency drives, automatic transfer
switches, and others)
0 Replacing deteriorating piping, gates, valves, and structures and provide long-term
corrosion protection; and
9 Providing resiliency from flooding.
Central San staff prepared a Request for Proposals (RFP) and it was advertised from May
22, 2017 to June 19, 2017 on PlanetBids to select a professional engineering consultant to
provide design serves for the project. The design services included arepreliminary services
(up to 30% design) and detailed final design services (to 100%). Three proposals were
received (Carollo Engineers, Inc., Stantec Consulting Services (MWH), and VWHA. Staff
evaluated the proposals and interviewed the consultant teams. VWHA had the highest total
score and is considered the best overall fit for the project.
Staff recommends VWHA in association with HDR and ArcSine Engineering for the design
of the Pump Station Upgrades project. The scope of work for the consultant agreement will
include, but is not limited to, the following:
An "all electric" evaluation for the Moraga and Orinda Crossroads Pump Stations
that includes replacing the existing wet weather diesel driven engines at each station
with electric variable speed pumping;
An assessment for the six pump stations for corrosion, structural, electrical,
instrumentation and controls;
An assessment of the Concord Main Metering Station for corrosion, structural,
electrical, instrumentation and controls;
• A high-level evaluation to determine the scope of improvements and planning level
construction cost to possibly eliminate the Fairview Pump Station;
• An investigation of the six pump station sites to identify the flood risk potential based
on existing conditions, proposed conditions, and sea level rise;
Page 2 of 4
POSITION PAPER
Board Meeting Date: July 20, 2017
subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A
PROFESSIONAL ENGINEERING SERVICES AGREEMENT WITH V.W.
HOUSEN AND ASSOCIATES FOR DESIGN SERVICES UNDER THE
PUMP STATION UPGRADES, DISTRICT PROJECT 8436
• Three-dimensional (3D) visualization of pump room and main electrical room at
Moraga and Orinda Crossroads Pump Stations;
• A preliminary level (30 percent) design for the upgrades required at Moraga and
Orinda Crossroads Pump Stations;
• A preliminary level (30 percent) design for the upgrades required at Maltby, Fairview,
Martinez, and Flush Kleen Pump Stations;
• A preliminary level (30 percent) design for the upgrades required at the Concord
Main Metering Station; and
• A preliminary design report that will include reliability and redundancy design criteria,
planning-level construction cost estimates by station, a planning-level construction
schedule, an implementation strategy including procurement considerations and
project design package recommendations, phasing plan(s), and preliminary (30%)
design drawings.
ALTERNATIVE /CONSIDE RATIONS: An alternative would be not to package all the
pump stations to be designed by one consultant and perform the projects individually with
six separate contracts, which is not recommended. The goal of the predesign work is to
finalize the scope of work, construction constraints, determine any special requirements,
develop a realistic schedule, and cost estimates. In addition, this effort will determine how
to package and sequence the construction phase.
Final design is not be included in the VWHA agreement at this stage. Staff intends to
negotiate a final design fee with VWHA after the predesign work is complete and provide
an update and seek further approval of the design at a future Board Meeting. The budget
for final design is planned for the project in Fiscal Year (FY) 2018-19.
FINANCIAL IMPACTS: The VWHA predesign services is expected to reach $780,000.
This project is included in the FY 2017-18 Capital Improvement Budget on page 131 with a
total estimated FY 2017-18 budget of $850,000, including staff time.
The total estimated project cost is $33,435,000, which includes $450,000 for planning (FY
2016-17)7 $2,596,000 for design (staff and consultant work in FY 2017-19), and
$30,389,000 for construction (FY 2019-22). The agreement for VWHA may reach up to
$2,300,000 if all the project elements are completed, which is 7.5 percent compared to the
total estimated construction costs.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at the meeting on July 11, 2017, and XXXXX approval of the
agreement.
Page 3 of 4
POSITION PAPER
Board Meeting Date: July 20, 2017
subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A
PROFESSIONAL ENGINEERING SERVICES AGREEMENT WITH V.W.
HOUSEN AND ASSOCIATES FOR DESIGN SERVICES UNDER THE
PUMP STATION UPGRADES, DISTRICT PROJECT 8436
RECOMMENDED BOARD ACTION: Authorize the General Manager to execute a
Professional Engineering Services Agreement with V.W. Housen and Associates with a
cost ceiling of $x'80,000 for the preliminary design of the Pump Station Upgrades, District
Project 8436.
Page 4 of 4
.r 4 iaw so.
IVA
Bra
PUMP STATION UPGRADES
Engineering and Operations Committee
July 11, 2017
Amanda Schmidt,Associate Engineer
Capital Projects Division
5
rr
�dyia
'■lam �~•�
Presentation Agenda
•� t .t
Project Drivers &
•" .,1. 4t
lAralCantra CesK�
W Sar tarpD11tr{rt
Background
FdIryIET!'f
ivrnp318t ev)
Project Scope and
L.ltar Approach
Iump St�tt#pA 141t sfrlm�Statlan o
r i'�•.Kv:t �
' . ;,• RFP and consultant
Selection
Fluth Kle[n e•fF�IS+ 1rkt 1
Pump SlASlon Y Creri
OtindaCcoswoWi Project Schedule
Pump.= Qr'vi
Project Budget
01=1 Ulm
-� - 0 Recommendations
4
• n 1 1 - �
�1
1
7/6/2(317
1 PROJECT DRIVERS AND BACKGROUND
. - der
PROJECT BACKGROUND
} s rt i n ez ratnx,.�j ! sash
0 )
Ireatment larFlush
PV
�iJ1AR#
K►IQei1 ` -10
0
t s hush UrH h
41.
CI"i ssroada
Moraga
2
7/6/2Ol7
PROJECT DRIVERS
AGING AsSETS, RELIABILITY AND SUSTAINABILITY
• Moraga and Orinda Crossroads pump stations
Long-term reliable wet weather pumping concerns
Need to replace and upgrade the emergency backup
generators to power one dry weather pump
• Major electrical, instrumentation, and controls
replacement or rehabilitation at all pump stations
Implement recommendations from the Arc-Flash Study
completed in 2015 by Protective Relay Engineering
Replace deteriorating piping, gates, valves, and
provide long-term corrosion protection
Resiliency from flooding
Asset Conditions Technical memo prepared under
CWMP
*KL
PROJECT BACKGROUND
Moraga & Orinda
Crossroads projects
identified in last year's
Capital Improvement Budget
Completed Moraga & Orinda +
Basis of Design Report by
No r
V.W. Housen & Associates
Pump Stations
'doe
3
7/6/2017
PROJECT RISKS AND OBJECTIVES
FACILITIES 0 CONCERNS
Identified as High Risk * Master Plan Condition Assessment Needs
a District Operation and Maintenance Staff
• Maltby Pump Station 0 Aging Assets,including Electrical/I&C
0 Fairview Pump Station 0 Unreliable Pumping Capacity
• Martinez Pump Station, 0 Corrosion
• Flush-Kleen Pump Station 0 Ground Settlement
• Concord Main Metering Vault Flooding(external and internal)
Provide Reliable Pumping Capacity Increase Overall Reliability
Extend Useful Life Improve Resiliency
PUMP STATION CAPACITIES
Firm Capacity Pump Motor
Station
(mgd) Horsepower
Martinez 12.24 3-75 HP
Fairview 13.16 3-100 HP
Maltby 15.12 3-100 HP
Orinda Crossroads 24.77 3-150 HP
Flush Kleen 1.47 2—15 HP
4
7/6/ZOl7
PUMP STATION HISTORY OVERVIEW
Pump Station Year Last Major Major Work Completed since
Constructed Renovation Original Construction
Martinez 1969 1996 New building, pumps,piping,
electrical equipment
Fa i rview 1969 1999* New pumps,added bypass piping
Maltby 1969 1999* New pumps,added bypass piping
Moraga 1959 2001 Replacement of dry weather pumps,
and associated Electrical/I&C
Orinda Replacement of dry weather pumps,
Crossroads 1959 2001 and associated Electrical/I&C,surge
tank
Flush Kleen 1950 1984 Electrical/I&C,Valve Vault,new FM
and Gravity Sewer
IMM
77
MARTINEz AREA PUMP STATIONS
Facilities deliver all
wastewater flow from
Martinez and are critical Maltby
facilities (daisy chain)
Maltby and Fairview PS
need work:
• O&M access
no
• Drywell show signs of corrosion
• Potential wet weather capacity pal
issues
Treatniet
` 5
7/6/2017
MARTINEZ P
Main Ps in Martinez
Major Concerns:
Corrasion concerns
a `
Protection from a
flooding
Electrical and controls
panels z
� w
X41 ;
+ I
FAIRVIEW PS
• Fart of the three Martine PS
• Major Concerns:
Electrical; instrumentation and •.
controls improvements and
upgrades w
g
Very tight site
s
Replace flow meters
Replace electrical switchgear
Outdated automatic transfer
switch
c
Corrasion issues of metal cans
Difficult access
Redundancy: All three pumps
operating during winter 2017AVA
wet weather * �
Consider eliminating ? '
7/6/2017
MALTBY PS
• Largest of the three Martinez
stations
• Major Concerns:
Very tight site
Electrical, instrumentation and
controls improvements and
upgrades
Replace flow meters
Replace electrical switchgear ,
Outdated automatic transfer
switch
Corrosion issues of metal cans '
Difficult access
`x
Redundancy: All three pumps
operating during winter 2017
wet weather
0. .
0. io.
MORAGAmORINDA PUMP
Facilities deliver majority of
wastewater flows from Orinda
FEusn
and Moraga are and are critical Kleen
facilities (daisy chain for
Orinda Crossroads) -601nda
Mora ga and Orinda Crossroads
Crossroads PS need work:
Electrical upgrades NRvraga
r i
Instrumentations and controls
Standby power evaluation
Wet weather pumps:
Pumping capacity
All electric option
yri
7
7/6/2017
MORAGA
* Major PS: Second Largest PS
for Central San
Major Concerns:
4
Located in residential
neighborhood near school
Diesel engines on wet weather °
Pumps �-
Consider wet weather pump
replacement? �
Electrical, instrumentation and
controls improvements and y
upgrades - .
Existing electrical equipment
issues(overheating)
Evaluate back-up power
Evaluate installation of
mechanized grinders(currently
manual cleaning)
ORINDA ROSS O AD P
toil
Largest PS for Central San
Major Concerns: owl
Very tight site
Located in very busy
commercial area in orinda
Diesel Engines on wet weather
Pumps
Consider wet weather pump
replacements
Electrical, instrumentation and
controls improvements and
upgrades
Existing electrical equipment
issues (overheating)
Evaluate back-up power
Evaluate replacement of
mechanized grinders
8
7/6/2017
WAUKESHA DIESEL ENGINES AT MORAGA
AND ORINDA CROSSROADS PS
. Original installation
icu
•
DiffIt to obtain
�
parts and perform
rep a i rs
s ,
°
,
�..
FLUSH
V
i oldest PS in our System
(1950)
• Mayor concerns. ,
Electrical, instrumentation
and controls improvements
and upgrades
r
Replace standby y
p Y P ower
generator
r
4 `
9
7/6/2017
CONCORD METERING
• This flow meter ,
measures 80% of city
of concord Flows
• Rece
V&A study ....
recommended . . ..
replacement
1
• corrosion
iz
sk
2
i PROJECT SCOPE AND APPROACH
16 f
10
7/6/ZO17
ALL=ENCOM PASSING PROJECT
Project packages the Martinez Area PS with
Moraga and Orinda Crossroads to form one all-
encompassing pumping station project
Bring PS stations to predesign level (30% complete)
Complete predesign (all electric option) for Moraga
Orinda Crossroads
Detailed project costs
Station construction constraints, scheduling
alternatives, bidding recommendations
Single engineering consultant to prepare the
predesign work and continue final design services
&LIZ:
MAJOR SCOPE OF WORK
For every station,scope includes a a hydraulic analysis to first understand
the requirements for reliable pumping of buildout PWWFs
A corrosion, electrical, instrumentation &controls assessment
A high-level evaluation to determine the scope of improvements and
planning level construction cost to eliminate the Fairview Pump Station
Flood risk analysis of the six pump station sites, including protection/sea
level rise and flooding due to mechanical failure inside the stations
An all electric evaluation for the Moraga and'Orinda Crossroads Pump
Stations
3D/BlM visualization of pump room and main electrical room at Moraga and
Orinda Crossroads Pump Stations.
A preliminary level (30 percent)design to identify upgrades required at
Maltby, Fairview, Martinez, and Flush Kleen Pump Stations
A preliminary level (30 percent)design to identify upgrades required at
Martinez Pump Stations
A preliminary level (30 percent) design to identify upgrades required at the
Concord Main Metering
Construction sequencing and constraints
A.
IL
1�
7/6/2017
"ALL ELECTRIC" WET WEATHER PUMP
ALTERNATIVES INCLUDE:
C
Y•y
Reuse of Existing Morris Pump k
Casings with Smaller Impellers
and New 650 and 700 HP
Horizontal Electric Motors
Least Cost Alternative
Install New Dry Pit Submersible
Electric Pumps
-x,
Provides Increased Resiliency -
Moraga Pump Station 30 Visualization
PROTECTION
SURGE
* Provided for dry
weather electric pumps
Diesel engines have
significant inertia to
prevent rapid ; NZ
:
shutdown, which
reduces surpotential
r k
surge p
Under the "All Electric
option, the forcemains a
may require additional
surge protection .�
'01
1 F
12
7/6/2Ol7
"ALL ELECTRIC" OPTION
Requires broader scope
4.
of electrical work than
"Keep Engine" option
New PG&E service
VFDs for wet weather
pumps
Larger standby generators
Byfirst understanding the reliable pumping requirement,sizes and
costs of electrical service,motor control,and standby power can be
right sized
UNDER "ALL ELECTRIC" OPTION, STANDBY POWER
is REQUIRED FOR ONE WET WEATHER PUMP +
AUXILIARY LOADS
700 kW 650 M
Preferred Standby
Ii. Generator Location Potential
Generator
ocations
otenfial Alternate
Locations
Smaller than Anticipated Wet Weather Pump Horsepower Could Result in
Smaller Generators that May Fit in Existing RadiatorlGenerotor Enclosures
13
14
7/6/2017
CORROSION PROTECTION
e Central San has experienced corrosion- Pump
Discharge
related failures Piping at
Project approach includes: Martinez
Field investigations and ultrasonic thickness -Wol Wealher Pump
testing Suction Piping at Moraga
Determination of cause of coating and and Orinda Crossroads
corrosion failures
Evaluation of existing cathodic protection
systems and installation of temporary systems
to determine current demand
Recommendations and cost for
repair/replacement
Recommendations to prevent future corrosion
and provide long-term protection
Dtywell Pimp Cans at
Project opprocich will not only design repair and replace deteriorated facilities, Maltby and Fairview
but will determine the cause to provide long-term corrosion protection
FLOOD
PROTECTION/ ;���
SEA LEVEL RISE
Pump Flooding Potential at Site $64 Level flits
Station (P fo]a c I a d Walt r
Sirlato Efeyaltoi NAYD
Sol
FEMA FEMA"01*6 00 +50 *100
Flood Yeats Yost* Yeats
Hazaid
2066 1rr
%Ivr*z AE Wthe t(*yew 60-A plant[1w ptad"0(r 11 5 126 lea
Z"AE a K0 r6k Vda Nat*W nXd Ingo V4*ftraln)
NO he.t wl"MW Plan V%i7ob"01 YW
A li 5 126 166
bro A.Hgh cask uVv N arcnal Food Ins V"Fto7 W�) _7 7am
X AW-W4 to 14 y#N&M p4M(I%ft0b9ftF 0(ko6rq ih" it 5 Ia IE6
yw.Zvo AE v Kqh 60 v4v Nates f"ftv&YA
Wsda of F EJUA Nod W"ior,*
Year.Zav AE■No dst v4v Wcfuil Nod k4vww
4.
414 WtW I*yw lloodpian(I%ptcb@bMya(ftxdrqrmyyw
sh"k0"W&q)*0*ftot 1-3 lWoldol3h)
J—PrLia wed
r,
15
7/6/2017
CONSTRUCTION SEQUENCING AND
CONSTRAINTS
Detailed sequencing
and constraints will be
included in contract
43
documents to:
LOWER ORINDA
PLIMP STATION
Minimize risk to the RE NOVAT ION PROJ EC T
District
Keep facilities
operational
Avoid change orders
USE OF BIM 3D DESIGN
BIM/3D advantages:
* Visualize improvements
* Optimize tight spaces/clash detection
Convey information to stakeholders
Construct 3D/BIM models for drawing
production
BIM13D Visualization of
Wet Weather..Dry Pit
Submersible Pumps at
Morago Pump Station
16
7/6/2017
3m RFP ANS CONSULTANT
SELECTION
J�
r
ti
SELECTION PROCESS
RFP �
-Tr '+trrs..„arr�ry-
�, � € •Selected
advertised on i ■Pre-Proposal •Received •Interviewed VWHA with
PlanetBids Meetings and PS threeHDR and
with three
tours for interested proposals teams ArcSine Eng.
parties {
•�1 7
i
.l
17
7/6/2617
THREE PROPOSALs
RECEIVED
.. Consultant
Carollo EngineJDH {Corrosion}
ConsultingStantec - Lee and Ro(Electrical)
Inc. (MWH) • V&A(Corrosion)
,� . es
HDR R (Carrvsion)
• ArcSine Engineering(Electrical)
• Northwest Hydraulic Consultants
(Surge Analysis)
AM Design Services
for Pump Station
Upgrades
Selected
plected VWHAA
�a;att:cii+rq c:sR'Sti
A Tea n Ynr)itnorr and Tru sl,w1h rr71r1!(AFU1:.7t
!^
pin"" or YQUr Purn,4 vitruru
4 a I r
L
MMd
4. PROJECT
6. 1
tr
18
7/6/2017
OVERALL PROJECT SCHEDULE
AnticipatedActivity
Date
Request for Proposals from Consultants Issued May 22,2017
Consultant Notice to Proceed August 1, 2017
Preliminary Design Complete January 2015
Final Design Complete December 2010
Anticipated Bid January 2020
Construction(Preliminary) March 2020 to June
2022
CURRENT TASK SCHEDULE
f i1► It+iwir�!
&""I ,�+.nlrr,100 0.46n" — 1Fr.,-.i.?')'0 0.. 7G„ 1.ti"7�M.
? + k ti JO . tl t0 It 4 If y i3 I i 1A 3) 1+ . Il 14 a1 r 10 yI 14 h
h#i.iM Ih:rf CIY� �
11Ar1+ %ULf-,q IF.!i 1a Fal 3 y
i'4a1+44Y1,�ik#W I Afi f k.tr ctrl.••,
A
Nap M.6%"Nvr 4'.1 i ow j
4Yt�
7 Fie+��aM O+irl�Crs#woa�'At 1k«}r.t`C*I p r Iwak+.+#l*"
fM 4.sr.I raM.sfea#r.1�.i'1•hf -
t�. �!! r0-0
De kqm
1! RrFsti+�I.-�4'*.S,l.sl��r.rr 1lJ tr.r ass"IR.efi.�E1j.p titrrr.o
-
FV' 'aIa req
1V; �;r,}�/`�+;y��F-y*A�I#.�'�S1}111K1.i"e4{��.tM hl►1µ'•Nv..P �+� ��
y I l i.r.,'W A6w%.�t:Vx}j+n era!A4rMa anl'W#A*-wt. E31< lalr�Fli�
'+vd- 0ft0-s..v4Van v4dsrT
.awnAwnaPr-41P2 Al.1 wV Jofrer rULyra r...}IA.r rkr•ry"a.ti-. - _ [!�
kALw dw rral'sNyw _ 0. 01800100.
E��' sFlkyr�.ea �w
4A*"F+ak h.&,w+}Nvp A I
iw*411ariY,d,IPP w1wIliftw+060..14.w.t+...1
!•.a Nat-rr p 06W fl0:rr Iwr'••.r.,•# { t w#r,.r! s
'41f*t ICVJ.fr„wr[a..*. ,,,• dee rR',...�.1 +,Madre"!lYrF+►�c
19
7/6/2017
5. PROJECT BUDGET
PROJECT BUDGET FOR DP 8436
• Fiscal Year 2017-18 Capital Improvement
Budget total estimated budget of $850,000
(page 131 of budget).
VWHA predesign services $780,000.
Remaining budget for staff
Total estimated project cost is
$33,435,000
�c
20
7/6/2017
6. RECOMMENDATIONS
RECOMMENDED BOARD ACTIONS
• Staff recommends that the Board
authorize the General Manager to execute
a professional consulting services
agreement for $780,000 with V.W. Housen
and Associates (VWHA) for the Pump
Station Upgrades Project, District Project
8436.
21
7/s/zov
QUESTIONS AND COMMENTS
1
22