HomeMy WebLinkAbout01. (Handout) EchoWater Project
Item1.
(Handout)
EchoWater Project
April 7, 2017
REGIONALSAN
Topics
Program Background |
Early Efforts, Pilot Testing
Program Delivery |
Program Management Structure,
Cost Control, BIM
Program Status |
Schedule, Budget, Project Updates
UPDATE
1
Early Planning Efforts
•Early 2011 –Initial Studies Identified Processes for Testing
•July, 2011 to April 2012 –Design and Build 0.5 MGD Pilot Plant
•February 2012 –Commissioned Program Management Office
•2012 -Define Treatment Processes and Design/Construction
Packages
•Early 2015 –Environmental Document Complete
Pilot Study for Technology Selection
•Plant designed for a flow capacity
of 0.25 mgd with peak flow capacity
Pilot Project
of 0.50 mgd (for scale up factors)
•Gather data to verify BNR process
and test processes for Title 22
treatment requirements.
•Total pilot project cost = $17.5
million
–CalFed grant funding $3.24 million
2
Pilot Study Configuration
Primary EffluentPrimary Effluent
BNR-Biological Nutrient Removal
Chlorine -Chlorine Disinfection
UV-Ultraviolet Disinfection
O-Ozone Disinfection
3
AirActivated SludgeAirActivated Sludge
AirActivated SludgeAirActivated Sludge
BNR ProcessBNR ProcessBNR ProcessBNR Process
3 Filtration Options
GMF with GMF with
Membrane Membrane
Granular Media Granular Media
Granular Media Granular Media
Pre-OzonationPre-Ozonation
FiltrationFiltration
FiltrationFiltration
FiltrationFiltration
ChlorineChlorineUVUVOOChlorineChlorineUVUVOO
3333
3 Disinfection Options
ChlorineChlorineChlorineChlorineUVUVOO
33
Pilot Study Findings
•BNR and GMF facilities would reliably meet permit
limitations and were the lowest cost alternative
•Higher GMF loading rate will reduce construction costs
about $100 million (Title 22)
•Reduction in Disinfection Contact Time from 450 mgl-min
to 250 mgl-min reduces construction cost by $20 million
(Title 22)
•Eliminating the need for coagulant chemical feed saves
$2.9 million/year (Title 22)
3
Process Upgrades
Current
Chlorine
Disinfection
Preliminary Primary High Purity Secondary
Effluent
TreatmentTreatmentOxygenTreatment
Dechlorination
Existing ProcessFuture –EchoWater Process
Preliminary Primary Air Activated Secondary New New
Effluent
TreatmentTreatmentProcess SedimentFiltrationEnhanced
(BNR)Disinfection
PMO Structure, Decision-
Making and Communication
Sacramento Regional County Sanitation District
4
Unique Aspects of Project Delivery
Integrated Program
Management Structure
Cost Control Measures
Owner Controlled
Insurance Program
Integrated PMO
Construction
Planning ProcessDesign Process
Process
•Engage Regional •Core team of •Combination of
San staff in the PMO/Regionaltwo third-party
development and San staff CM contracts,
review of assigned to each Sac County
process analysis, designCMID, and PMO
business case Staff
•Design reviews
evaluations, and
by Regional San •Commissioning
Basis of Design
staffinvolves Plant
Reports
operators
5
PMO Structure Blends Consultant with
Regional San Staff
BNR Core Team
PositionNameBV Position
PMMarkHammerPM/DeputyPM
PEWilliamYuEngineeringManager
BNR Core
O&MRepresentativeMarioGuadamuzElementLeads
EngineerJimMorrisElementLeads
Team
O&MBioTeamMikeMeladyOperations
ElectricalSanjaySivaprasadElectrical
PCCSControlsMikeSeamonsI&C
ControlsGaryDubinDaveWhite/Dan
KenAbraham,etI&CGott
ProcessEngrsalCivilEllaineTaraya
Tech
ArchitecturalMikeLambert
QCRonBrown
resources
GeotechTBD
TomMingee
CostEstDesOrsinelli
SiteCoordinators/JillTeplin
BIM/CADDRonAgnew
StructuralEdGardoQuiroz
CorrosionBrienClark
MechanicalGrahamCalciano
SchedulerBobCampbell
NoiseTBD
MechanicalRyanHougham
SurveyMaggieKido
ElectricalDanGott
6
Program Participant Roles
PMORegional San O&M Construction
and EngineeringManager
Works as an extension
of Regional San staff
Sounding board during Oversees Project
for on-schedule
project planning, design construction
delivery of the Program
and construction–
receives ongoing
information and
provides input
Delivers detailed Implements
DesignConstruction
designs and bid construction
EngineerContractor
documentscontracts
Program Participant Roles
Timely, direct exchange of
information for decision making
District
O&M
PMO
and
Engineering
7
Program Participant Roles
Timely, direct exchange of
information for decision making
District
O&M
PMO
and
Engineering
Project
Manager
Program Participant Roles
Timely, direct exchange of Integration of core functions: scheduling,
information for decision makingcost estimating, CM standards
District
O&M
Construction
PMO
and
Manager
Engineering
ProjectConstruction
ManagerContractor
8
PMO Roles and Responsibilities
•Overall management of planning,
and integration of design and
construction projects
•Facilities Plan
•Basis of design reports, business
case evaluations, and technical
reports
•Web-based information
management system
•Cost and resource forecasting
•Risk management
•SCADA Programming
•Commissioning Lead
Cost Control
Sacramento Regional County Sanitation District
9
Cost Control Through Three Core
Elements
Mining key
Business Case Reliability Centered
data from
Evaluations (BCEs) Design (RCD)
data-driven designs
and
(smart P&IDs
for lifecycle cost
Reliability Centered
and 3-D BIM)
containment
Maintenance
(RCM)
to populate CMMS
for smart asset
decisions and
maintenance
strategies
Building Information Modeling –the Ds
5D5D
3D3D
4D4D6D6D
ESTIMATINGESTIMATING
VISUALIZATIONVISUALIZATIONSCHEDULINGSCHEDULINGFACILITYFACILITY
MANAGEMENTMANAGEMENT
••Cost PhasingCost Phasing
ExistingExistingProjectProject
ConditionsConditions
PhasingPhasing••Life-CycleLife-Cycle
••Quantity Quantity
ExtractionsExtractions
AnimationsAnimations
VisualVisual••As-builtsAs-builts
ValidationValidation
RenderingsRenderings
••O&MO&M
WalkthroughsWalkthroughs
••Asset Asset
AssessmentAssessment
10
Why Building Information Modeling (BIM)?
Or this?
This?
11
Benefits During Design
•Site planning
•Visualization of
design options
•Helps visualize
potential
constructability
issues
•Advance
coordination of
site logistics and
utility
connections
•O&M staff can
“walk” the site
before it is
constructed
12
BIM-Clash Detection
Inter-Project Connections
13
Construction Use of BIM
Federated Model and Schedules
Construction Use of BIM
Inter-Project Conflicts
14
Data Migration Framework
Equipment Vendor
Construction
Information
Data
RCD
(Reliability Centered Design)
RCM
Asset Management
Smart
BIM/Revit
(Reliability Centered Maintenance)
P&IDsSpare Parts, LTVs, Job Plans
Design Database
Models
Unstructured Data
•Procedures (SOPs)
•Vendor manuals
•O&M data
•Control strategies
Maximo
•Asset hierarchies
eO&M
•As-build drawings
•PM, job plans
CMMS
•Photos/videos
•Spare parts
•Process schematics
Owner Controlled Insurance Program
Coverages
•Worker’s Compensation
•General Liability
•Excess Liability
•Builders Risk
•Pollution Liability
15
EchoWater Project
Update
REGIONALSAN
Summary Program Schedule
16
Program Cash Flow
Aerial Photo of EchoWater Project
September 2016
17
Aerial Photo of EchoWater Project
January 11, 2017 –Post Rain Event
EchoWater Construction Update
18
Temporary Power
Access Paving
Electrical Duct Bank
North Contractor Area
Expand WRL/WRH
Site Preparation Project
Overaa & Co. -$31M
Excess Soil Stockpile
Flow Through Diversion Structure
Mass Excavation Completed
Basin Concrete Paving
Flow Equalization Project
Teichert Construction -$113M
19
Chlorine Tanks
Area 9
Disinfection Chemical Storage Project
GSE Construction -$15M
•Treat the ammonia rich flows
from the solids handling
processes Reduces size of
new BNR system
•Improves BNR performance by
treating peak SSB flows
•Produces nitrate rich effluent
for odor control
Nitrifying Sidestream Treatment Project
Flatiron Construction -$40M
20
•Biological Nutrient
Removal System
•Primary Effluent Pump
Station
•Biological Odor Control
Facility
Biological Nutrient Removal Project
Dragados USA -$414M
Biological Nutrient Removal Project
Dragados USA -$414M
21
•Filtration
•Disinfection Contact Basin
•Filter Influent Pump Station
Tertiary Treatment Facility Project
Bidding Late 2017 -$350M Estimate
Questions?
Visit us at
RegionalSan.com
Like us on Facebook!
Facebook.com/SacRegionalSan
22