HomeMy WebLinkAbout05. (Handout) Revised draft Position Paper to award contract to Cratus, Inc. for the construction of the Walnut Creek Sewer Renovations, Phase 11, DP 8422 Central Sang
4. BOARD OF DIRECTORS RAFT
POSITION P
Board Meeting Date: April 6, 2017
Subject: AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH CRATUS, INC. FOR THE
CONSTRUCTION OF THE WALNUT CREEK SEWER RENOVATIONS,
PHASE 11, DISTRICT PROJECT 8422
Submitted By: Initiating Dept./Div.:
Mark Wenslawski, Associate Engineer Engineering and Technical
Services/Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
S. Mestetsky—Senior Engineer
E. Lopez—Capital Projects Division Manager
JM. Petit—Director of Engineering and Technical Services Roger S.Bailey
General Manager
ISSUE: On February 28, 2017, three (3) bids were received for the construction of the
Walnut Creek Sewer Renovations, Phase 11, District Project 8422 (Project). The Board
of Directors (Board) must award the contract or reject bids within 50 days of the bid
opening. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements.
BACKGROUND: The Project is part of the ongoing sewer renovation within the
Collection System Program of the capital Improvements Budget to replace or
rehabilitate aging sewer infrastructure that is in poor condition. This Project aligns with
Central San's Strategic Plan, specifically the following:
• Goal No. 1 — Provide exceptional customer service
• Goal No. 2 — Strive to meet regulatory requirements
• Goal No. 6— Maintain a reliable wastewater infrastructure
The Project is primarily located in the Walnut Heights neighborhood between Mt. View
Boulevard and Rudgear Road, includes Boulevard Way and other locations in Walnut
Creek. The scope of work consists of replacement or rehabilitation of approximately
91100 lineal feet of 6-inch to 10-inch diameter sewer mains, construction of manholes,
and other related work within public rights-of-way, easements, and near creeks. The
project location map is identified in Attachment 1.
Central San staff prepared the plans and specifications for the Project. The Engineer's
estimate for construction is $2,800,000. This project was advertised on January 27
and February 2, 2017. Three (3) sealed bids ranging from $2,698,845 to $5,497,622
were received and publicly opened on February 28, 2017. The Engineering Department
conducted a technical and commercial review of the bids and determined that Cratus,
Inc. is the lowest responsive and responsible bidder. References were provided for
Cratus, Inc. and staff received satisfactory feedback. Cratus, Inc. is new to Central San,
Page 1 of 6
POSITION P
Board Meeting Date: April 6, 2017
subject. AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT
TO SUBMITTAL REQUIREMENTS WITH CRATUS, INC. FOR THE
CONSTRUCTION OF THE WALNUT CREEK SEWER RENOVATIONS,
PHASE 11, DISTRICT PROJECT 8422
however, has done sewer work in the City of Berkeley and San Jose, and is a
prequalified sewer contractor for the San Francisco Public Utilities Commission. A
summary of bids received is shown in Attachment 2. Central San will administer the
construction contract and provide contract administration, inspection, survey, office
engineering, and submittal review. Consultant inspection will be used to supplement
staff on an as-needed basis.
CEQA: Staff has concluded that this project is exempt from CEQA under District CEQA
Guidelines Section 15302, because it involves replacement of existing sewer facilities at
substantially the same locations and with the same purpose and level of activity as the
facilities being replaced. Any capacity increases are for non-growth inducing, wet
weather purposes. This project also is exempt under District CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that
the activity in question may have a significant effect on the environment. This certainty
is based on Central San's experience with numerous sewer construction projects of this
nature, the relatively short distances involved, and Central San's mitigating construction
specifications. These specifications are standardized general and special conditions
that are made part of the project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with
applicable federal, state, county, district, municipal and local laws, ordinances, orders,
and regulations. Approval of this project will establish the Board of Directors'
independent finding that this project is exempt from CEQA.
ALTER NATIVESICONSIDERATIONS: Reject all bids, which is not recommended.
FINANCIAL IMPACTS: The total estimated project cost is $3,934,000, including
design, bid price, contingency, construction management, and consultant costs as
detailed in Attachment 3. This project is included in the Fiscal Year 2016-17 Capital
Improvement Budget on page 107 with a total estimated project budget of $3,750,000.
The additional $184,000 budget required to fund the Project will be transferred from the
Urgent Repairs Project, District Project 8434, which received only one bidder
significantly above the engineer's estimate. A portion of the scope of work under the
Urgent Repairs Project is anticipated to be completed under the proposed contract. Per
Board Resolution 2016-018, the General Manager has the authority to transfer the
additional budget after approval of the project.
COMMUNITY OUTREACH: Central San held a public meeting on January 12, 2017, at
the Collection System Operations Department building in Walnut Creek to assist with
any questions or concerns by the residents along the proposed construction alignments.
Page 2 of 6
POSITION P
Board Meeting Date: April 6, 2017
Subject AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT
TO SUBMITTAL REQUIREMENTS WITH CRATUS, INC. FOR THE
CONSTRUCTION OF THE WALNUT CREEK SEWER RENOVATIONS,
PHASE 11, DISTRICT PROJECT 8422
In addition, staff has notified and met with several homeowners directly to discuss the
upcoming sewer work, construction impacts, and schedules for easements.
COMMITTEE RECOMMENDATION: The Engineering and operations Committee
reviewed this project at its meeting on March 17, 2017, and recommended approval of
the project.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $2,898,848 for the construction of
the Walnut Creek Sewer Renovations, Phase 11, District Project 8422, to Cratus
Inc., the lowest responsive and responsible bidder, and
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements and include up to 10-percent contingency.
Attached Supporting Documents:
1. Project Location Map
2. Summary of Bids
3. Post-Bid I Preconstruction Estimate
Page 3 of 6
i
BOY•-R•
Project Areas
0-
✓J y
�ASPN� *-%GE RD
— Q �
f
� JQ�
�o
T
24
C�
r
�RU•`jRRD
IN
VAC1LE.y-6�J� C
Np1Rp
T
0 2,400 1 E�
r r
Feet
/ � 1
Central Contra Costa Walnut Creek Sewer Renovation Phase 11 Attachment
Sanitary District District Project 8422 1
Pro teding Publir Health and the Environment Project Location
Page 4 of 6
ATTACHMENT 2
WALNUT CREEK SEINER RENOVATIONS, PHASE 11
DISTRICT PROJECT 8422
SUMMARY OF BIDS
PROJECT NO.: 8422 NO. OF ADDENDA: Q DATE: FEBRUARY 28 2017
PROJECT NAME: WALNUT CREEK SEWER_RENOVATIONS, PHASE 11
PROJECT LOCATION: WALNUT CREEK, CA
ENGINEER'S ESTIMATE: $2,800,000
NO, BIDDER BID PRICE
Cratus, Inc.
1 $2,898,845
San Francisco, CA 94124
K. J. Woods Construction, Inc.
2 $3,180,000
San Francisco, CA 94124
Ranger Pipelines, Inc.
3 $5,4979622
San Francisco, CA 94124
BIDS OPENED BY/s/ Elaine R. Boehme CMC DATE: February 28, 2017
Page 5 of 6
ATTACHMENT 3
WALNUT CREEK SEINER RENOVATIONS, PHASE 11
DISTRICT PROJECT 8422
POST-BID 1 PRECONSTRUCTION ESTIMATE
No. Item Description Amounts % Construction
Cost
1. CONSTRUCTION
a. Construction Contract $296989845
b. 10% Contingency $289,155
c. Perm it $35,000
SUBTOTAL- CONSTRUCTION COST $3,003,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
-Construction Management (Engineering, $298,000
Inspection, Survey)
- Public Relations $25,000
- Right of Way $2,090
b. Consultants
- Inspection $35,000
- Material Testing $20,000
-Geotechnical and Arborist $10,000
SUBTOTAL- CONSTRUCTION MANAGEMENT $390,000 12.9%
3. PREBID EXPENDITURES
a. Engineering (Design, Survey, Drafting) $5412000
SUBTOTAL- PREBID EXPENDITURES $541,000 18.0%
4. TOTAL ESTIMATED PROJECT COST $3,9349000
Page 6 of 6