HomeMy WebLinkAbout05.f. Authorize transfer of funds for Plant Energy Optimization Project, District Project 7320, and amend contract with Carollo Engineers, Inc. for design services for the projectCentral Contra Costa Sanitary District
BOARD OF DIRECTORS
POSITION PAPER
5.f.
Board Meeting Date: November 3, 2016
Subject:
AUTHORIZE THE GENERAL MANAGER TO TRANSFER FUNDS AND
EXECUTE A PROFESSIONAL AGREEMENT WITH CAROLLO
ENGINEERS FOR DESIGN SERVICES FOR THE PLANT OPTIMIZATION
PROJECT, DISTRICT PROJECT 7320
Submitted By:
Initiating Dept./Div.:
C. Shima, Senior Engineer Operations/Plant Maintenance
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
E. Lopez — Capital Projects Division Manager
JM. Petit — Director of Engineering and Technical Services
460.0 4 74) ,.►
Roger S. Bane
9 Y
General Manager
ISSUE: Board authorization is required to transfer funds withine Capital
Improvement Budget in amounts greater than $500,000. Authorization is also required
for the General Manager to execute a professional engineering agreement in the
amount above $100,000.
BACKGROUND: The project aligns with the District's Strategic Plan Goal 6,
Strategy 4, to optimize energy efficiency and meets the recently adopted Energy Policy.
The District received a notice of violation from the Bay Area Air Quality Management
District in April 2016 for carbon monoxide (CO) emissions for the cogeneration gas
turbine (GT) engine, which is the main power generation unit for the treatment plant.
The cogeneration system (Cogen) must operate within site specific Title V Permit
pollutant mass limits at all times. The Title V limits are 118 pounds per day for nitrogen
oxides (NOx) and 157 pounds per day for CO. The GT engine and gearbox was
overhauled in December 2015 under a maintenance agreement with Solar Turbines.
Prior to the overhaul, the GT engine was operating at an average load of about 90
percent. Therefore, to meet these regulated mass limits, staff has reduced fuel
throughput by approximately six percent less than normal, which increases the amount
of electricity imported and results in less energy savings from operating the Cogen.
To reserve our contract rights, in August 2016, the District submitted a warranty claim to
Solar Turbines related to the performance of the GT engine. Solar Turbines promptly
responded by sending technicians to retune the GT engine on several occasions to
improve the emissions performance. A third -party air quality service verified that the
GT engine meets the Solar Turbines' Centaur 40 engine technical specification
concentration limits of 42 parts per million (ppm) of NOx corrected to 15 percent oxygen,
Page 1 of 3
POSITION PAPER
Board Meeting Date: November 3, 2016
Subject:
AUTHORIZE THE GENERAL MANAGER TO TRANSFER FUNDS AND
EXECUTE A PROFESSIONAL AGREEMENT WITH CAROLLO
ENGINEERS FOR DESIGN SERVICES FOR THE PLANT OPTIMIZATION
PROJECT, DISTRICT PROJECT 7320
and 50 ppm of CO, which matches industry standard for this GT engine type. These
types of GT engines can operate at full Toad within the Title V concentration and mass
permit limits, but not consistently. Due to limitations in air testing equipment accuracy
(Le., a repeatability of plus/minus 7 percent in general), the only means to ensure full
regulatory compliance, while maximizing the output of the Cogen, is through improved
emissions control technology.
Staff researched various alternatives to modify the Cogen to meet compliance and
increase efficiency. Two improvements were identified. First, oxidation catalyst
(CO catalyst) technology can reduce CO by approximately 50 to 75 percent, which
when combined with injection water will provide Title V Permit compliance at full load.
Second, evaporative cooling technology appears promising from a fuel efficiency
standpoint. Carollo Engineers, Inc. was hired to provide a technical memorandum
evaluating installation costs and payback duration. Carollo was selected based on their
past experience in designing the original 1995 installation of the Cogen, the repairs in
2012, and the the control modifications in 2014.
The purpose of the Plant Energy Optimization Project, District Project 7320, is to
increase energy efficiency and decrease greenhouse gas emissions at the treatment
plant. District staff has identified a project that will add evaporative cooling equipment
to the inlet of the Cogen and a CO catalyst to the exhaust ducting. These modifications
will increase operational flexibility and electricity generation by allowing operation at full
Toad, while decreasing emissions. Continued operation at the current reduced Toad will
cost the District approximately $150,000 to $200,000 per year in additional electrical
import costs. The evaporative cooler and CO catalyst alternative has a payback period
of approximately three years as detailed in Attachments 1 and 2, Project Business case
Analyses. This project has been coordinated with the Comprehensive Wastewater
Master Plan team to ensure that the potential future replacement of the Cogen does not
negatively impact the benefit of these improvements. The replacement of the District's
Centaur 40 engine falls within the ten-year timeframe of the Comprehensive
Wastewater Master Plan.
Staff is recommending that the agreement with Carollo be revised to include design
services for this project. Carollo has unique knowledge and understanding of the
Cogen, and it is in the best interest of the District to retain their professional engineering
service. The agreement revision will include detailed field investigation, project
specifications and drawings for bid and other related professional services to design the
project.
Page 2of3
POSITION PAPER
Board Meeting Date: November 3, 2016
Subject:
AUTHORIZE THE GENERAL MANAGER TO TRANSFER FUNDS AND
EXECUTE A PROFESSIONAL AGREEMENT WITH CAROLLO
ENGINEERS FOR DESIGN SERVICES FOR THE PLANT OPTIMIZATION
PROJECT, DISTRICT PROJECT 7320
ALTERNATIVES/CONSIDERATIONS: Continue to operate the Cogen as -is and import
electricity from Pacific Gas and Electric. Other options reviewed as part of the Business
Case Analysis include Selective Catalytic Reduction (SCR), SoloNOx, and a chiller unit.
These other options are more costly and are not recommended.
FINANCIAL IMPACTS: The total Fiscal Year (FY) 2016-17 project cost is anticipated
to be $600,000, which includes planning, design, consulting fees, bid price, and
construction management. This project is listed on page 133 of the FY 2016-17 District
Budget. The approved budget for this project in FY 2016-17 is $50,000. Additional
funds of $550,000 will need to be transferred from projects in the treatment plant
program to complete the work this fiscal year. The following budget transfers are
recommended:
• Transfer $ 50,000 from District Project 7297.
• Transfer $ 25, 000 from District Project 7310. (Project Closing)
• Transfer $188,000 from District Project 7324.
• Transfer $137,000 from District Project 7312.
• Transfer $150,000 from District Project 7341. (Delayed to FY 2017-18)
Transfer $550,000 to District Project 7320.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this subject at the October 21, 2016, meeting and recommended approval of
the budget transfer and project.
RECOMMENDED BOARD ACTION:
1. Authorize the General Manager to transfer up to $550,000 budgeted for other
projects in the current fiscal year treatment plant program to the Plant Energy
Optimization Project, District Project 7320; and
2. Authorize the General Manager to execute a revision to Agreement 044520 with
Carollo Engineers, Inc. to increase the cost ceiling from $29,495 to $120,000 for
design services under the Plant Energy Optimization, District Project 7320.
3.
Attached Supporting Documents:
1. Business Case Analysis No. 1
2. Business Case Analysis No. 2
Page 3 of 3
Date:
Project:
Prepared By:
Capital Costs For 1st Year:
Planning/Design Costs
Direct Equipment Costs
Construction Costs
CM Costs
••
O&M Costs For ist Year:
District Staff Time Cost
Solar Turbine PM Contract Additional Cost*
Chemical Costs
PG&E Costs
Natural Gas Costs
8/16/2016
Cogen Exhaust Upgrades
Clint 5hima 'Checked By:
Sarwan Wason
BUSINESS CASE ANii
ATTACHMENT 1
Typical
Alternative 1
Alternative 2 Alternative 3 Alternative 4
Baseline
Do Nothing
CO Catalyst
SCR
SoloNOx C40
$0
$0
$95,000
$220,000
$410,000
$0
$0
$150,000
$350,000
$650,000
$0
$0
$245,000
$560,000
$1,030,000
$0
$0
$60,000
$130,000
$250,000
$25,000
$25,000
$30,000
$45,000
$25,000
$0
$0
$0
$0
$47,280
0
0
$11,000
$0
$390,000
$600,000
$390,000
$390,000
$290,000
$1,920,000
$1,880,000
$1,920,000 ,
$1,920,000
$1,920,000
O&M Costs for Year 1 $2,335,000
Capital Costs for Year 1
Net Present Value for 10 years
Assumptions:
:Discount Rate, %
-O&M Cost Inflation Rate, %
-Capital Costs Inflation Rate, %
N/A
50
$2,505,000 $2,340,000 $2,366,000 • $2,282,0.00
$0 $550,000 $1,260,000 $2,340,000,
$24,108,000 $22,988,000 $24,002,000 524,032,000"
Recomn111149191 e
Not
Recommended
4.00%
2.60%
2.50%
Not Recommein.
Based upon CWMP Basis of Cost TM 3
Based on 2011-2015 Average CPI
Based on 2011-2015 Average ENR CCI
Based on 2012-2016 normalized PG&E Average Total Rate
PG&E Cost Inflation Rate, % 4.72% ($/KWh)
Natural Gas Cost Inflation Rate, % 0.00% (-0.42%) inflation from 2002-2016
Lifecycle period, years 10 years
* Solar Turbines PM Contract Cost is currently $216,000 annually
_**Alternatives are compared using an average plant load of 2.9 MW
Typical
Baseline from 2015 Cogen operating conditions
Alternative 1 Run Cogen as -is producing —2.3MW and continue increased PG&E import
Alternative 2
Alternative 3
Alternative 4
;Add a CO catalyst to the exhaust stack with increased water injection to
'produce 2.7 MW while keeping Nox and CO emissions below Title V limits
Insert a Selective Catalytic Reduction system using urea to lower NOx
emissions while running cogen to produce 2.7 MW, removing water injection
system, and reducing CO emissions
Replace existing conventional combustion engine to a low emission engine
that reduces emissions and is able to produce 3 MW at the same fuel rate...
Date:
:Project:
•Prepared By:
Capital Costs For ist Year:
Planning/Design Costs
Direct Equipment Costs
Construction Costs
-CM Costs
08:.11/1 Costs For lst Year:
District Staff Time Cost
Chemical Costs
PG&E Costs
Natural Gas Costs
L
O&M Costs for Year 1:
Capital Costs for Year 1
Net Present Value for 10 years
Assumptions:
Discount Rate, %
O&M Cost Inflation Rate, %
Capital Costs Inflation Rate, %
PG&E Cost Inflation Rate, %
Natural Gas Cost Inflation Rate, %
Lifecycle period, years
Alternative 1
10/13/2016
Cogen Improvements
Chathu Abeyrathna Checked By: Sarwan Wason
BUSINESS CASE ANALYSIS
Alternative 1
Do Nothing
so
Alternative 2
Evaporative Cooler
$0
sol
$600,000
$1,880,000
$2,480,000;
$0
$22,049,000
Not Recommended
Recommended
$15,0001
$43,000
$37,000
$13,000
$i0,000
$3,000
$524,000
$1,912,000
$2,449,000
$108,000
$21,765,000
Recommended
4.00%
2.60%
2.50%
4.72%
0.00%
10 years
ATTACHMENT 2
Based upon CWMP Basis of Cost TM 3
Based on 2011-2015 Average CPI
Based on 2011-2015 Average ENR CCI
Based on 2012-2016 normalized PG&E
Average Total Rate ($/KWh)
(-0.42%) inflation from 2002-2016
Run Cogen as -is producing —2.3MW and continue increased PG&E
import
Alternative 2
Add an Evaporative cooler to reduce cogen intake air temperature.