HomeMy WebLinkAbout07. Construction update on Pleasant Hill-Grayson Creek Trunk Sewer, DP 8412CONSTRUCTION UPDATE: PLEASANT HILL-GRAYSON CREEK TRUNK SEWER PROJECT October 21, 2016 E&O Committee Meeting Nancy Molina, PE Associate Engineer PROJECT BACKGROUND Construction contract awarded to Mountain Cascade, Inc. (MCI) for $10,401,854 at the February 18, 2016 Board meeting. Notice to Proceed was issued on April 4, 2016. Scope of Work includes: Installation of approximately 10,000 LF of new trunk and sewer mains by both open -trench and trenchless methods and abandonment of approximately 6,000 LF of old sewer, majority by Grayson Creek. 7. 1 1 t'4 PROJECT MAP yr .4. .-- -I _----sti, L�--� -rte , i!,-;:: . 4 1 1,1 r_i 1 • :-.1 ,/-1 ..„:7„..„,:,,,,,..„. ,,,,,,I 7. ; ' r 1 \IR.'. j rim as 1. or ,,,,...4 ,,,:,,,i 1 i 1. '4 s'-, vir J' 1 s • ■ = Work Completed • or Work Remaining • s Existing 36' Trunk Sewer Major Crossing Installed CONSTRUCTION PROGRESS • Open -trench • 1,200 LF of 18" and 20" PVC • Depths of up to 30' ■ 3 Major Crossings • Installed 36" Steel Casing and sewer under: • Contra Costa Canal (62" RCP) • Grayson Creek (96" RCP) • Twin Box Culverts (96"x36") • Pilot Tube Guided Boring • 1,460 LF of 18-24" VCP 2 CONSTRUCTION CHALLENGES Soil Conditions More hard rock than anticipated Rock was not consistent Rock hardness varied CONSTRUCTION CHALLENGES Traffic Control • Complicated traffic control plans (TCPs) and requirements • Narrow streets • Highly traveled roadways • Multiple schools in the area • Limited ingress and egress to neighborhoods • Hired consultant to assist with TCPs Existing Utilities • Avoiding utilities • Narrow residential streets • Low overhead utilities 3 CONTRACT ADMINISTRATION • MCI Original Bid: • Change Orders: • Current Contract: • Work completed to date: • Zero (0) Stop notices $10,401,854 55.,550 $10,457,404 $ 4,086,715 COMPLETION SCHEDULE • NTP Issued: • Completion required by: • Construction Began: • Estimated Completion: April 4, 2016 April 16, 2017 May 2016 April 2017 • Project -40% complete and projected to meet schedule 4 QUESTIONS?