HomeMy WebLinkAbout11.h. Award construct contract to Manito Construction, Inc. for the Pump and Blower Building Seismic Upgrades, District Project 7291 Central Contra Costa Sanitary District 11 h ` BOARD OF DIRECTORS -------............... POSITION P Board Meeting Date: October 6, 2016 Subject: AWARD A GUARANTEED MAXIMUM PRICE CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH MAN ITO CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE PUMP AND BLOWER BUILDING SEISMIC UPGRADES, DISTRICT PROJECT 7291; AND AUTHORIZE AN AGREEMENT AMENDMENT WITH COMPLETE PROJECT SOLUTIONS Submitted By: initiating Dept/Div.: and Technical Jason DeGroot, Associate Engineer Eng Services/Capital Projects REVIEWED AND RECOMMENDED FOR BOARD ACTION: C. Mizutani—Senior Engineer X— E. Lopez—Capital Projects Division Manager JM. Petit--Director of Engineering and Technical Counsel Alm .�-� Roger S.Bailey ounsel for the District General Manager Services ISSUE: On May 19, 2016, the Board of Directors (Board) authorized the General Manager to solicit and negotiate a construction contract for the Pump and Blower Building Seismic Upgrades, District Project 7291. On September 13, 2016, three sealed proposals were received and evaluated. The Board must award the contract or reject proposals within 50 days of receiving the proposals. Board authorization is also required for the General Manager to execute the Contract Documents subject to SUBMITTAL requirements, amend a professional engineering agreement in an amount greater than $100,000, and transfer funds in the Capital Improvements Program budget above $500,000. BACKGROUND: In January 2008, California adopted the 2007 California Building Code (2007 CBC). Among the updates in the 2007 CBC were significant changes to seismic design. in 2009, a seismic evaluation of the treatment plant facilities was completed and included a recommendation to bring the Pump and Blower Building up to higher seismic design standards. The Pump and Blower Seismic Upgrades will update the Pump and Blower Building and Machine Shop to meet current seismic design standards. The scope of work includes demolition of existing walls, installation of reinforced concrete shear walls, installation of buckling restrained braces with associated foundations, and structural steel work. Complete Project Solutions (CPS), the project structural engineering consultant along with MWH Global, the electrical-mechanical engineering consultant, and District staff prepared the plans and specifications for the project. On March 10 and 16, 2016, the project was advertised for public bid and zero (0) bids were received on April 27, 2016. District staff proposed to solicit proposals and select a Page 1 of 5 POSITION PAPER Board Meeting Date: October 6, 2016 Subject: AWARD A GUARANTEED MAXIMUM PRICE CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH MANITO CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE PUMP AND BLOWER BUILDING SEISMIC UPGRADES, DISTRICT PROJECT 7291; AND AUTHORIZE AN AGREEMENT AMENDMENT WITH COMPLETE PROJECT SOLUTIONS contractor by an alternate method, by requesting for Guaranteed Maximum Price (GMP) proposals for construction of the project. District Legal Counsel has reviewed the project and is confident the District has met the statutory obligations for bidding, and the District can now enter into a negotiated contract directly with a contractor. Staff hired Ewing Construction Services (ECS) to provide engineering services related to developing the GMP procurement and construction contract documents, in accordance with Legal Counsel review. A request for statement of qualifications was sent on May 31, 2016 to several Contractors, some of which were interested parties from the original planholder's list, and others from private or commercial contractors that specialize in this type of project and who do not normally participate in the public low bid process. Out of six contractors, four continued into the GMP proposal stage. The request for proposal was sent on August 5, 2016, and three proposals were received September 13, 2016 and scored by the District's selection committee. The construction estimate for the GMP proposal was at $4,250,000. Proposals were issued by Overaa Construction, Manito Construction, and Roebbelen. Selection was based on a detailed scoring system that included qualifications and GMP pricing. The overall weight of the scores consisted of 40% on qualifications and 50% on price. The successful proposer, which also was the lowest GMP price, is Manito Construction, Inc. (Manito). Manito has successfully performed several construction projects at the District, most recently for the Wet Scrubber Caustic Injection System, District Project 7297. Manito also constructed the Sludge Loading Facility at the treatment plant, which included major concrete and structural work. District staff will administer the construction contract and provide construction management, oversee consultant services, and coordinate activities with Plant Operations. Staff also recommends retaining CPS to provide services during the construction phase, including reviewing shop drawings and submittals, responding to design questions, performing site visits to verify compliance with the design, inspection, and other related activities. An as-needed construction support services agreement amendment with a cost ceiling of $345,000 is recommended for CPS. The new cost ceiling for the CPS agreement, including the original amount, will be $588,400. CEQA: Staff has concluded that this project is exempt from the California Environmental Quality Act (CEQA) under District CEQA Guidelines Section 15301 since it involves repairs to existing public facilities involving no expansion of use. Approval of this project will establish the Board of Directors' independent finding that this project is exempt from CEQA. Page 2 of 5 POSITION PAPER Board Meeting Date: October 6, 2016 Subject: AWARD A GUARANTEED MAXIMUM PRICE CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH MANITO CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE PUMP AND BLOWER BUILDING SEISMIC UPGRADES, DISTRICT PROJECT 7291; AND AUTHORIZE AN AGREEMENT AMENDMENT WITH COMPLETE PROJECT SOLUTIONS FINANCIAL IMPACTS: The total project cost is anticipated to be $0,782,000, which includes planning, design, GMP proposal price, contingency, and construction management as shown in Attachment 2. This project is included in the Fiscal Year (FY) 2016-17 Capital Improvement Budget (CIB) with a total estimated project budget of $5,953,000, therefore, contingency funds are required. There is currently $1.45 million in the CIB contingency account, and a budget transfer of$829,000 is needed to fund this project. This will leave $021,000 in the FY 2015-17 contingency account. ALTERNATIVES/CONSIDERATIONS: Reject all proposals, which is not recommended. COMMITTEE RECOMMENDATION: The Engineering and Operations Committee reviewed this project at its meeting on September 22, 2015, and recommended award of the project. RECOMMENDED BOARD ACTION: Staff recommends the following: 1. Find that the project is exempt from CEQA, 2. Award a Guaranteed Maximum Price construction contract in the amount of $4,887,800 for.the construction of the Pump and Blower Building Seismic Upgrades, District Project 7291, to Manito Construction, Inc., the selected proposer, 3. Authorize the General Manager to execute the Contract Documents subject to SUBMITTAL requirements, 4. Authorize the General Manager to execute an agreement amendment with Complete Project Solutions to increase the cost ceiling from $243,400 to $588,400 to provide as--needed construction support services, and 5. Authorize the General Manager to transfer $829,000 from the CIB contingency account to the Pump and Blower Seismic Upgrades, District Project 7291. Attached Supporting Documents: I. Project L oca tion Map 2. Post Bid/Preconstructi'on Estimate Page 3 of 5 r Ju Q k 0 PUMP&BLOWER BLDG. �a 0 MACHINE SHOP STAGING AREA MAIN GATE i u /Ir 1 I !f! 7 �•`Y l� Vii, !.J ,f �4y q� rte, � ���,.,• ak Q Q3 c. F AREA IAP Q 250 -r FEET �} Centrol Contra Costa Atachment =Y Sa r'ar as o PUMP AND BLOWER BUILDING E� SEISMIC UPGRADESCD 1 S�1 �.s District Projed 7291 Project Location z� Page 4 of 5 ATTACHMENT 2 PUMP AND BLOWER BUILDING SEISMIC UPGRADES DISTRICT PROJECT 7291 POST-BID 1 PRECONSTRUCTION ESTIMATE No. Item Description Amounts % construction Cost 1. CONSTRUCTION a. Construction Contract $4,887,800 b. Contingency at 5% $244,200 SUBTOTAL- CONSTRUCTION $5,132,000 100% 2. CONSTRUCTION MANAGEMENT a. District Forces - Resident Engr. $210,000 - Construction Management $280,000 - Operations Coordination $80,000 b. Consultants - CPS (Structural and Inspection) $3451000 - ECS (Contract Admin) $20,000 SUBTOTAL- CONSTRUCTION $935,000 18% MANAGEMENT 3. PREBID EXPENDITURES a. Engineering (Design) $8251000 b. GMP Proposal process $90,000 SUBTOTAL- PREBID EXPENDITURES $715,000' 14% 4. TOTAL ESTIMATED PROJECT COST $6,782,000 5. CIB TOTAL PROJECT BUDGET $5,953,000 5. BUDGET TRANSFER REQUIRED* $829,00 *Budget transfer from the contingency account. Page 5 of 5