` BOARD OF DIRECTORS
-------............... POSITION P
Board Meeting Date: October 6, 2016
Subject: AWARD A GUARANTEED MAXIMUM PRICE CONSTRUCTION
CONTRACT AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE
CONTRACT DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS
WITH MAN ITO CONSTRUCTION, INC. FOR THE CONSTRUCTION OF
THE PUMP AND BLOWER BUILDING SEISMIC UPGRADES, DISTRICT
PROJECT 7291; AND AUTHORIZE AN AGREEMENT AMENDMENT
WITH COMPLETE PROJECT SOLUTIONS
Submitted By: initiating Dept/Div.:
and Technical
Jason DeGroot, Associate Engineer Eng
Services/Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Mizutani—Senior Engineer X—
E. Lopez—Capital Projects Division Manager
JM. Petit--Director of Engineering and Technical Counsel
Alm .�-� Roger S.Bailey
ounsel for the District General Manager
Services
ISSUE: On May 19, 2016, the Board of Directors (Board) authorized the General
Manager to solicit and negotiate a construction contract for the Pump and Blower
Building Seismic Upgrades, District Project 7291. On September 13, 2016, three
sealed proposals were received and evaluated. The Board must award the contract or
reject proposals within 50 days of receiving the proposals. Board authorization is also
required for the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements, amend a professional engineering agreement in an amount
greater than $100,000, and transfer funds in the Capital Improvements Program budget
above $500,000.
BACKGROUND: In January 2008, California adopted the 2007 California Building
Code (2007 CBC). Among the updates in the 2007 CBC were significant changes to
seismic design. in 2009, a seismic evaluation of the treatment plant facilities was
completed and included a recommendation to bring the Pump and Blower Building up to
higher seismic design standards.
The Pump and Blower Seismic Upgrades will update the Pump and Blower Building and
Machine Shop to meet current seismic design standards. The scope of work includes
demolition of existing walls, installation of reinforced concrete shear walls, installation of
buckling restrained braces with associated foundations, and structural steel work.
Complete Project Solutions (CPS), the project structural engineering consultant along
with MWH Global, the electrical-mechanical engineering consultant, and District staff
prepared the plans and specifications for the project.
On March 10 and 16, 2016, the project was advertised for public bid and zero (0) bids
were received on April 27, 2016. District staff proposed to solicit proposals and select a
Page 1 of 5
POSITION PAPER
Board Meeting Date: October 6, 2016
Subject: AWARD A GUARANTEED MAXIMUM PRICE CONSTRUCTION CONTRACT
AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH MANITO
CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE PUMP AND
BLOWER BUILDING SEISMIC UPGRADES, DISTRICT PROJECT 7291; AND
AUTHORIZE AN AGREEMENT AMENDMENT WITH COMPLETE PROJECT
SOLUTIONS
contractor by an alternate method, by requesting for Guaranteed Maximum Price (GMP)
proposals for construction of the project. District Legal Counsel has reviewed the
project and is confident the District has met the statutory obligations for bidding, and the
District can now enter into a negotiated contract directly with a contractor.
Staff hired Ewing Construction Services (ECS) to provide engineering services related
to developing the GMP procurement and construction contract documents, in
accordance with Legal Counsel review. A request for statement of qualifications was
sent on May 31, 2016 to several Contractors, some of which were interested parties
from the original planholder's list, and others from private or commercial contractors that
specialize in this type of project and who do not normally participate in the public low bid
process. Out of six contractors, four continued into the GMP proposal stage. The
request for proposal was sent on August 5, 2016, and three proposals were received
September 13, 2016 and scored by the District's selection committee. The construction
estimate for the GMP proposal was at $4,250,000. Proposals were issued by Overaa
Construction, Manito Construction, and Roebbelen. Selection was based on a detailed
scoring system that included qualifications and GMP pricing. The overall weight of the
scores consisted of 40% on qualifications and 50% on price. The successful proposer,
which also was the lowest GMP price, is Manito Construction, Inc. (Manito).
Manito has successfully performed several construction projects at the District, most
recently for the Wet Scrubber Caustic Injection System, District Project 7297. Manito
also constructed the Sludge Loading Facility at the treatment plant, which included
major concrete and structural work.
District staff will administer the construction contract and provide construction
management, oversee consultant services, and coordinate activities with Plant
Operations. Staff also recommends retaining CPS to provide services during the
construction phase, including reviewing shop drawings and submittals, responding to
design questions, performing site visits to verify compliance with the design, inspection,
and other related activities. An as-needed construction support services agreement
amendment with a cost ceiling of $345,000 is recommended for CPS. The new cost
ceiling for the CPS agreement, including the original amount, will be $588,400.
CEQA: Staff has concluded that this project is exempt from the California
Environmental Quality Act (CEQA) under District CEQA Guidelines Section 15301 since
it involves repairs to existing public facilities involving no expansion of use. Approval of
this project will establish the Board of Directors' independent finding that this project is
exempt from CEQA.
Page 2 of 5
POSITION PAPER
Board Meeting Date: October 6, 2016
Subject: AWARD A GUARANTEED MAXIMUM PRICE CONSTRUCTION CONTRACT
AND AUTHORIZE THE GENERAL MANAGER TO EXECUTE CONTRACT
DOCUMENTS SUBJECT TO SUBMITTAL REQUIREMENTS WITH MANITO
CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE PUMP AND
BLOWER BUILDING SEISMIC UPGRADES, DISTRICT PROJECT 7291; AND
AUTHORIZE AN AGREEMENT AMENDMENT WITH COMPLETE PROJECT
SOLUTIONS
FINANCIAL IMPACTS: The total project cost is anticipated to be $0,782,000, which
includes planning, design, GMP proposal price, contingency, and construction
management as shown in Attachment 2. This project is included in the Fiscal Year (FY)
2016-17 Capital Improvement Budget (CIB) with a total estimated project budget of
$5,953,000, therefore, contingency funds are required. There is currently $1.45 million
in the CIB contingency account, and a budget transfer of$829,000 is needed to fund
this project. This will leave $021,000 in the FY 2015-17 contingency account.
ALTERNATIVES/CONSIDERATIONS: Reject all proposals, which is not
recommended.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at its meeting on September 22, 2015, and recommended award
of the project.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a Guaranteed Maximum Price construction contract in the amount of
$4,887,800 for.the construction of the Pump and Blower Building Seismic
Upgrades, District Project 7291, to Manito Construction, Inc., the selected
proposer,
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements,
4. Authorize the General Manager to execute an agreement amendment with
Complete Project Solutions to increase the cost ceiling from $243,400 to
$588,400 to provide as--needed construction support services, and
5. Authorize the General Manager to transfer $829,000 from the CIB contingency
account to the Pump and Blower Seismic Upgrades, District Project 7291.
Attached Supporting Documents:
I. Project L oca tion Map
2. Post Bid/Preconstructi'on Estimate
Page 3 of 5
r
Ju
Q
k
0
PUMP&BLOWER BLDG.
�a
0
MACHINE SHOP
STAGING
AREA
MAIN GATE
i
u /Ir
1 I
!f!
7 �•`Y l� Vii,
!.J
,f
�4y q� rte, � ���,.,•
ak
Q
Q3
c.
F AREA IAP Q 250
-r
FEET
�}
Centrol Contra Costa Atachment
=Y Sa r'ar as o PUMP AND BLOWER BUILDING
E�
SEISMIC UPGRADESCD
1
S�1
�.s
District Projed 7291 Project Location
z�
Page 4 of 5
ATTACHMENT 2
PUMP AND BLOWER BUILDING SEISMIC UPGRADES
DISTRICT PROJECT 7291
POST-BID 1 PRECONSTRUCTION ESTIMATE
No. Item Description Amounts % construction
Cost
1. CONSTRUCTION
a. Construction Contract $4,887,800
b. Contingency at 5% $244,200
SUBTOTAL- CONSTRUCTION $5,132,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Resident Engr. $210,000
- Construction Management $280,000
- Operations Coordination $80,000
b. Consultants
- CPS (Structural and Inspection) $3451000
- ECS (Contract Admin) $20,000
SUBTOTAL- CONSTRUCTION $935,000 18%
MANAGEMENT
3. PREBID EXPENDITURES
a. Engineering (Design) $8251000
b. GMP Proposal process $90,000
SUBTOTAL- PREBID EXPENDITURES $715,000' 14%
4. TOTAL ESTIMATED PROJECT COST $6,782,000
5. CIB TOTAL PROJECT BUDGET $5,953,000
5. BUDGET TRANSFER REQUIRED* $829,00
*Budget transfer from the contingency account.
Page 5 of 5