HomeMy WebLinkAbout05. Draft Position Paper to award contract for Pump and Blower Building Seismic Upgrades, DP 7291Central Contra Costa Sanitary District
BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: October 6, 2016
Subject:
5.
AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE
GENERAL MANAGER TO EXECUTE CONTRACT DOCUMENTS
SUBJECT TO SUBMITTAL REQUIREMENTS WITH MANITO
CONSTRUCTION, INC. FOR THE CONSTRUCTION OF THE PUMP AND
BLOWER BUILDING SEISMIC UPGRADES, DISTRICT PROJECT 7291;
AND AUTHORIZE AN AGREEMENT AMENDMENT WITH COMPLETE
PROJECT SOLUTIONS
Submitted By:
Jason DeGroot, Associate Engineer
Initiating Dept./Div.:
Engineering and Technical
Services/Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
C. Mizutani β Senior Engineer
E. Lopez β Capital Projects Division Manager
JM. Petit β Director of Engineering and Technical
Services
Kent AIm Roger 5. Bailey
Counsel for the District General Manager
ISSUE: On May 19, 2016, the Board of Directors (Board) authorized the General
Manager to solicit and negotiate a construction contract for the Pump and Blower
Building Seismic Upgrades, District Project 7291. On September 13, 2016, three
sealed proposals were received and evaluated. The Board must award the contract or
reject proposals within 50 days of receiving the proposals. Board authorization is also
required for the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements, and amend a professional service agreement in an amount
greater than $100,000.
BACKGROUND: In January 2008, California adopted the 2007 California Building
Code (2007 CBC). Among the updates in the 2007 CBC were significant changes to
seismic design. In 2009, a seismic evaluation of the treatment plant facilities was
completed and included a recommendation to bring the Pump and Blower Building up to
higher seismic design standards.
The Pump and Blower Seismic Upgrades will update the Pump and Blower Building and
Machine Shop to meet current seismic design standards. The scope of work includes
demolition of existing walls, installation of reinforced concrete shear walls, installation of
buckling restrained braces with associated foundations, and structural steel work.
Complete Project Solutions (CPS), the project structural engineering consultant along
with MWH Global, the electrical -mechanical engineering consultant, and District staff
prepared the plans and specifications for the project.
On March 10 and 16, 2016, the project was advertised for public bid and (0) zero bids
were received on April 27, 2016. District staff proposed to solicit proposals and select a
contractor by an alternate method, by requesting for Guaranteed Maximum Price (GMP)
Page 1 of 5
rL
POSITION PAPER
Board Meeting Date: October 6, 2016
Subject:
AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH MANITO CONSTRUCTION, INC. FOR
THE CONSTRUCTION OF THE PUMP AND BLOWER BUILDING SEISMIC
UPGRADES, DISTRICT PROJECT 7291; AND AUTHORIZE AN
AGREEMENT AMENDMENT WITH COMPLETE PROJECT SOLUTIONS
proposals for construction of the project. District Legal Counsel has reviewed the project
and is confident the District has met the statutory obligations for bidding, and the District
can now enter into a negotiated contract directly with a Contractor.
Staff hired Ewing Construction Services (ECS) to provide engineering services related
to developing the GMP procurement and construction contract documents, in
accordance with Legal Counsel review. A request for statement of qualifications was
sent on May 31, 2016 to several Contractors, some of which were interested parties
from the original planholder's list and others from private or commercial contractors that
specialize in this type of project and who do not normally participate in the public low bid
process. Out of six contractors, four continued into the GMP proposal stage. The
request for proposal was sent on August 5, 2016, and three proposals were received
September 13, 2016 and scored by the District's selection committee. Proposals were
issued by Overaa Construction, Manito Construction, and Roebbelen. Selection was
based on a detailed scoring system that included qualifications and GMP pricing. The
overall weight of the scores consisted of 40% on qualifications and 60% on price. The
successful proposer, which also was the lowest GMP price, is Manito Construction, Inc.
District staff will administer the construction contract and provide construction
management, oversee consultant services, and coordinate activities with Plant
Operations. Staff also recommends retaining CPS to provide services during the
construction phase, including reviewing shop drawings and submittals, responding to
design questions, performing site visits to verify compliance with the design, inspection,
and other related activities. An as -needed construction support services agreement
amendment with a cost ceiling of $345,000 is recommended for CPS. The new cost
ceiling for the CPS agreement, including the original amount, will be $588,400.
CEQA: Staff has concluded that this project is exempt from CEQA under District CEQA
Guidelines Section 15302, because it involves replacement of existing sewer facilities at
substantially the same locations and with the same purpose and level of activity as the
facilities being replaced. Any capacity increases are for non -growth inducing, wet
weather purposes. This project also is exempt under District CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that
the activity in question may have a significant effect on the environment. This certainty
is based on the District's past experience with numerous sewer construction projects of
this nature, the relatively short distances involved, and the District's mitigating
construction specifications. These specifications are standardized general and special
conditions that are made part of the project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with
applicable federal, state, county, district, municipal and local laws, ordinances, orders,
Page 2 of 5
POSITION PAPER
Board Meeting Date: October 6, 2016
Subject:
AWARD A CONSTRUCTION CONTRACT AND AUTHORIZE THE GENERAL
MANAGER TO EXECUTE CONTRACT DOCUMENTS SUBJECT TO
SUBMITTAL REQUIREMENTS WITH MANITO CONSTRUCTION, INC. FOR
THE CONSTRUCTION OF THE PUMP AND BLOWER BUILDING SEISMIC
UPGRADES, DISTRICT PROJECT 7291; AND AUTHORIZE AN
AGREEMENT AMENDMENT WITH COMPLETE PROJECT SOLUTIONS
and regulations. Approval of this project will establish the Board of Directors'
independent finding that this project is exempt from CEQA.
FINANCIAL IMPACTS: The total project cost is anticipated to be $6,782,000, which
includes planning, design, bid price, contingency, and construction management as
shown in Attachment 2. This project is included in the Fiscal Year 2016-17 Capital
Improvement Budget (CIB) with a total estimated project budget of $5,953,000,
therefore, contingency funds are required. There is currently $1.45 million in the CIB
contingency account, and a budget transfer of $829,000 is needed to fund this project.
This will leave $621,000 in the FY 2016-17 contingency account.
ALTERNATIVES/CONSIDERATIONS: Reject all proposals, which is not
recommended.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this project at its meeting on September 22, 2016, and recommended award
of the project.
RECOMMENDED BOARD ACTION: Staff recommends the following:
1. Find that the project is exempt from CEQA,
2. Award a construction contract in the amount of $4,887,800 for the construction of
the Pump and Blower Building Seismic Upgrades, District Project 7291, to Manito
Construction, Inc., the selected proposer,
3. Authorize the General Manager to execute the Contract Documents subject to
SUBMITTAL requirements,
4. Authorize the General Manager to execute an agreement amendment with
Complete Project Solutions to increase the cost ceiling from $243,400 to
$588,400 to provide as -needed construction support services, and
5. Authorize the General Manager to transfer $829,000 from the CIB contingency
account to the Pump and Blower Seismic Upgrades, District Project 7291.
Attached Supporting Documents:
1. Project Location Map
2. Post-Bid/Preconstruction Estimate
Page3of5
K:\Prajects\7291_Pump_Blower_Seisrnic\Autocad\Area Iv1ap.dwg
?βMar -2016
4
PUMP & BLOWER BLDG.
MACHINE SHOP
STAG I N G
AREA
MAIN GATE
(7-17
Central Contra Costa
Sanitary District
AREA MAP
PUMP AND BLOWER BUILDING
SEISMIC UPGRADES
District Project 7291 - Project Location
0
FEET
250
Attachment
1
Page 4 of 5
ATTACHMENT 2
PUMP AND BLOWER BUILDING SEISMIC UPGRADES
DISTRICT PROJECT 7291
POST -BID / PRECONSTRUCTION ESTIMATE
No. Item Description Amounts % Construction
Cost
1. CONSTRUCTION
a. Construction Contract
b. Contingency at 5%
SUBTOTAL - CONSTRUCTION
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Resident Engr.
- Construction Management
- Operations Coordination
$4,887,800
$244,200
$210,000
$280,000
$80,000
$5,132,000 100%
b. Consultants
- CPS (Structural and Inspection) $345,000
- ECS (Contract Admin) $20,000
SUBTOTAL - CONSTRUCTION $935,000 18%
MANAGEMENT
3. PREBID EXPENDITURES
a. Engineering (Design and RFP)
$715,000 14%
SUBTOTAL - PREBID EXPENDITURES $715,000
4. TOTAL ESTIMATED PROJECT COST $6,782,000
5. CIB TOTAL PROJECT BUDGET $5,953,000
6. BUDGET TRANSFER REQUIRED* $829,000
*Budget transfer from the contingency account.
Page5of5