Central Contra Costa Sanitary District
f' BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: May 19, 2016
subject: ELIMINATE THE USE OF CAPITAL IMPROVEMENT BUDGET
ALLOCATIONS, AND ADOPT RESOLUTION UPDATING THE CAPITAL
IMPROVEMENT PROGRAM AUTHORIZATION LIMITS
Submitted By. Initiating Dept./Div.:
Edgar J. Lopez, Division Manager Engineering and Technical
Services/Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION: OIL—
J-M. Petit—Director of Engineering and K.Alm Roger S.Bailey
Technical Services Counsel for the District General Manager
ISSUE: Board authorization is requested to (1) eliminate the use o rogram budget
allocations in the District's Capital Improvement Program (CIP) Budget effective July 1,
2016, and (2) amend the table of authorization limits under the CIP Budget to both
reflect the elimination of budget allocations and modify current authorization limits for
the General Manager and Board of Directors related to the CIP Budget commencing
with the Fiscal Year (FY) 2016-17.
BACKGROUND: For over 30 years, the Capital Improvement Budget (CIB) included an
accounting and budgeting procedure titled Capital Improvement Budget Allocation
(CIBA) requests, in which the General Manager was authorized to allocate funds up to
the maximum limit of each CIB program budget, including contingency. As previously
discussed in the FY 2016-17 District budget workshops, staff has proposed revising the
CIP budgeting procedures by eliminating the use of program budget allocations and
replacing them with new procedures that will be more transparent when budgeting for
capital projects.
The major CIP budgeting changes consist of deleting budget allocations based on
Board-authorized program budgets and authorizing the General Manager to allocate up
to 15% of the project budget determined at award of construction. Instead, staff
recommends that all project budgets listed in the fiscal year CIB be authorized with firm
budgets and that the General Manager have the authority limit up to $50,000 to transfer
funds within the program in order to cover the costs for overruns and project changes.
Any project transfer above $50,000 would require Board authorization.
If the deletion of program budget allocations is approved by the Board, the table of
authority limits will need to be updated accordingly. Additionally, if the Board approves
a General Manager authority limit up to $50,000 to transfer funds within the CIP Budget,
Page 1 of 2
POSITION PAPER
Board Meeting Date: May 19, 2016
Subject: ELIMINATE THE USE OF CAPITAL IMPROVEMENT BUDGET
ALLOCATIONS, AND ADOPT RESOLUTION UPDATING THE CAPITAL
IMPROVEMENT PROGRAM AUTHORIZATION LIMITS
that too should be reflected in the table. A strikeout version of the current table of CIP
Authorization Limits is reflected in Attachment 1.
The last update to the CIP Authorization Limits was adopted under Resolution No.
2014-008 on April 10, 2014. It is proposed that that be rescinded upon adoption of the
proposed resolution included as Attachment 2, which sets forth the changes explained
above.
Once approved, staff will incorporate the changes into the CIP Budget and update the
District's engineering and accounting procedures to reflect the changes beginning with
FY 2016-17.
ALTERNATIVES/CONSIDERATIONS: The Board may wish to continue the use of CIP
budget allocations, and may wish to leave current authority limits as is, or revise them.
FINANCIAL IMPACTS: None.
COMMITTEE RECOMMENDATION: The Engineering and Operations Committee
reviewed this subject at its meeting on May 10, 2016, and recommended the changes
reflected in Attachment 1 and Exhibit A to the attached proposed resolution
(Attachment 2).
RECOMMENDED BOARD ACTION:
1. Eliminate the use of program budget allocations among the four Capital
Improvement Programs (CIP) in favor of implementing individual project budgets,
effective July 1, 2016, and
2. Adopt a resolution:
a. Amending the table of authorization limits under the CIP Budget to:
1) Reflect the elimination of CIP budget allocations; and
2) Modify current authorization limits for the General Manager and
Board of Directors related to the CIP Budget commencing with
Fiscal Year (FY) 2016-17; and
b. Rescind Resolution No. 2014-008, effective July 1, 2016.
Attached Supportinq Documents:
1. Attachment 1 -strikeout showing changes to the authorization limits.
2. Proposed resolution, including Exhibit A, reflecting proposed new authorization limits.
3. PowerPoint presentation
Page 2 of 2
ATTACHMENT 1
Table 4: Capital Improvement Program Authorization Limits
Action General Manager Board of
Directors
Approve Capital Plan None No limit
Authorize Capital Program budgets None No limit
Transfer funds to individual project budgets Alleeate funds $50,000 or less fetalte ��� No limit Ale-@earl
GGRtmges1' aut#er+zatieR Fequired
Professional Consulting Services $100,000 or less Greater than$100,000
Authorize
Consultant Technical Consulting Services. $100,000 or less Greater than$100,000
Contracts
Professional Eng.Services. $100,000 or less Greater than$100,000
TransferAllesate funds from CIB pregraFA contingency $100,000 or less per Greater than$100,000
accounts to projects not included in the CIB project2
Individual equipment items and equipment contingency in Up to amount specified in Above amount specified in
the Equipment Budget Equipment Budget Equipment Budget
Leroy nduding GORt'RgenG!,'
Individual equipment items not in the Equipment Budget $50,000 or less Greater than$50,000
Authorize supplemental funds to program budgets Not applicable Sewer Construction Fund
and contingency account/sentisgeasyasseunts balance
15%of fiaalprejest
t et4-," a Gmater than 15%of f
prejest et3GFabove
s���;t���stien-seatrast maximum of$1,0
'est
Award construction contracts43 $100,000 or less Greater than$100,000
Authorize Additive $100,000 or less Greater than$100,000
construction
change orders Deductive No limit No Board authorization
required
Subcontractor substitutions All substitutions unless Substitutions protested by
protested by subcontractor subcontractor
Informational
Construction project acceptance All projects announcement to the
Board
Close out project All projects Memo provided to the
Board at end of FY
Limited by the remaining balances of the applicable program and contingency account
2 Limited by the remaining balance of the applicable PregraFn contingency account
a
Final prejeet budget is established at time ef awaFd ef GOR64LIGtiOR GE)RtFaGta
3 Bid protests and rejection of all bids must go to Board regardless of dollar amount
ATTACHMENT 2
RESOLUTION NO. 2016-017
A RESOLUTION OF THE CENTRAL CONTRA COSTA SANITARY DISTRICT
ELIMINATING THE USE OF CAPITAL IMPROVEMENT PROGRAM
BUDGET ALLOCATIONS AND
AMENDING GENERAL MANAGER AUTHORIZATION LIMITS
SET FORTH IN THE CAPITAL IMPROVEMENT PROGRAM BUDGET
WHEREAS, the proper functioning of the Central Contra Costa Sanitary District
("District") requires that the General Manager and his or her staff have adequate
authority to carry out both the routine and reoccurring functions as well as the
emergency functions of the District; and
WHEREAS, on April 10, 2014, the Board adopted Resolution 2014-008 setting forth
General Manager authorities, including authorities contained in the most recent Capital
Improvement Program Budget approved by the Board; and
WHEREAS, staff has recommended eliminating the use of program budget allocations
under the Capital Improvement Program Budget effective July 1, 2016; and
WHEREAS, at its meeting of May 10, 2016, the Engineering & Operations Committee
reviewed and recommended changes to the General Manager and Board authorization
limits contained in the most recent Capital Improvement Program Budget consistent
with elimination of program budget allocations; and
WHEREAS, at its meeting of May 19, 2016, the Board concurred with the Engineering &
Operations Committee's recommended changes to the General Manager and Board
authorization limits contained in the most recent Capital Improvement Program
Authorization Limits, as reflected in Exhibit A.
NOW, THEREFORE, BE IT RESOLVED by the Board of Directors of the Central Contra
Costa Sanitary District ("District") as follows:
1. The use of program budget allocations in the District's Capital Improvement
Program Budget is eliminated effective July 1, 2016;
2. The General Manager and Board authorization limits contained in the Capital
Improvement Program Authorization Limits are amended as shown in Exhibit A,
attached, commencing with Fiscal Year 2016-17; and
3. As of July 1, 2016, existing District Resolution No. 2014-008 shall be rescinded.
PASSED AND ADOPTED this 19th day of May, 2016, by the Board of Directors of the
Central Contra Costa Sanitary District by the following vote:
General Manager Authority
Resolution 2016-0/7
Page 2 of 3
AYES: Members:
NOES: Members:
ABSENT: Members:
Tad J. Pilecki
President of the Board of Directors
Central Contra Costa Sanitary District
County of Contra Costa, State of California
COUNTERSIGNED:
Elaine R. Boehme, CMC
Secretary of the District
Central Contra Costa Sanitary District
County of Contra Costa, State of California
Approved as to form:
Kenton L. Alm, Esq.
Counsel for the District
General Manager Authority
Resolution 2016-0/
Page 3 of 3
EXHIBIT A
Capital Improvement Program Authorization Limits
Action General Manager Board of
Directors
Approve Capital Plan None No limit
Authorize Capital Program budgets None No limit
Transfer funds to individual project budgets $50,000 or less No limit
Professional Consulting Services $100,000 or less Greater than$100,000
Authorize
Consultant Technical Consulting Services. $100,000 or less Greater than$100,000
Contracts
Professional Eng.Services. $100,000 or less Greater than$100,000
Transfer funds from CIB contingency account to projects not $100,000 or less per Greater than$100,000
included in the CIB project2
Individual equipment items and equipment contingency in Up to amount specified in Above amount specified in
the Equipment Budget Equipment Budget Equipment Budget
Individual equipment items not in the Equipment Budget $50,000 or less Greater than$50,000
Authorize supplemental funds to program budgets Not applicable Sewer Construction Fund
and contingency account balance
Award construction contracts3 $100,000 or less Greater than$100,000
Authorize Additive $100,000 or less Greater than$100,000
construction No Board authorization
change orders Deductive No limit required
Subcontractor substitutions All substitutions unless Substitutions protested by
protested by subcontractor subcontractor
Informational
Construction project acceptance All projects announcement to the
Board
Close out project All projects Memo provided to the
Board at end of FY
Limited by the remaining balances of the applicable program and contingency account
2 Limited by the remaining balance of the applicable contingency account
3 Bid protests and rejection of all bids must go to Board regardless of dollar amount
ATTACHMENT 3
PROPOSED AMENDMENT TO AUTHORIZATION LIMITS UNDER
CAPITAL IMPROVEMENTS PROGRAM (CIP) BUDGET
To
MODIFY CURRENT AUTHORIZATION LIMITS
NEW LIMITS EFFECTIVE FISCAL YEAR 2016-17
Presented by
Edgar J . Lopez, PE
Capital Projects Division Manager
May 19, 2016 Board Meeting
EMiSRCJwF :Pln . '
BUDGET FORMAT CHANGES
® Capital Improvement Budget
Elimination of allocations
List of projects with firm individual project
budgets versus placeholders
Formal process for transfer of funds
(Board of Directors' approval)
e_
1 * i .• a, 1 , ..
EXAMPLE OF CIP FORMAT CHANGE
PREVIOUS VERSION FY 2015= 16
ABLE 6: FY 15-16 CIB Recycled Water Program Bud et/Project List
Date: 05/04/15
List of Active Rew Projects Bud et allocated and tracked in Sunc uard Estimated Ex enditures
Priority Project Current Project Allocated to date Prior FY(s) Remaining FY14/15 FY15/16 FY16/17 Future FY Page
Number Phase Spent Budget
7299 C Concord Landscape $3,915,000 $3,697,629 $217,371 $130,000 $87,000 $0 $0 RW-1
e H 7279 P Concord Naval Weapons REW $280,000 $264,855 $15,145 $1,100 $0 $5,000 $0 RW-2
ery H 7300 P Refinery REW $385,000 $283,727 $101,273 $50,000 $4,000 $47,500 $0 RW-3
eryH 7306 D one 1 Recycled Water $145,0001 $35,061 $109,939 $50,000 $0 $0 $0 RW-4
ery H 7306 C one 1 Recycled Water $75,000 $0 $75,0001 $ $29,0001 $46,000 $0 RW-4
Subtotal: $4,800,001 $4,281,2721 $518,72q $231,101 $120,0001 $98,500 $
List of Projects in FY 2015-16 Unallocated A.Carry Over-$288,000
7344 PRec cled Water Planning $250,000 $0 $0 $0 $100,000 $150,000 $0 RW-5
7345 P Filter Plant $200,000 $0 $0 $0 $200,000 $0 $0 RW-6
7344 1 C IFilter Plant 16-17 $200000 $0 $0 $0 $0 $150,0001 $50,000 RW-
7346 1 P ISurge Analysis 16-17 1 $60,000 $0 $0 $0 $0 $65,000 $01 RW-7
B.Estimated Allocations to $450,00 $ $ $o $300,000 $365,00
FY 2015-16 Raw Program:
Program Contingency 10% $30,00 $36,50
Estimated FY Expenditures: S450.000500 00
Total Proposed Authorization „ �
A+B+Contin enc =C $768,000 "'" `
D
i
EXAMPLE OF CIP FORMAT CHANGE
NEW VERSION FY 2016=2017
Project Project Budgeted to Prior Fiscal FY16/17 Future FYs Project Total
Number date Years
7300 Refinery REW $595,000 $355,642 $40,000 $199,358 $595,000
7306 Zone 1 Recycled Water $395,000 $237,005 $37,815 $385,180 $660,000
7344 Recycled Water Planning $100,000 $50,000 $102,185 $347,815 $500,000
7345 Filter Plant $200,000 $200,000 $200,000 $150,000 $550,000
A 7346 Surge Analysis 16-17 $0 $0 $55,000 $45,000 $100,000
7347 Rew Automated Fill Station $115,000 $100,000 $15,000 $0 $115,000
7350 lResidential Fill Station Improv 1 $450,000 $4000001 $50,000 $0 $450,000
Totals: $1,855,000 $1,342,647 $500,000 $1,127,353 $2,970,000
CURRENT AUTHORIZATION LIMITS
Table3: Capital Improvement Program Authorization Limits
ACTION GENERAL BOARD OF
MANAGER DIRECTORS
Approve Capital Plan None No limit
Authorize Capital Program budgets None No limit
Allocate funds o individual project budgets Total program budget No Board
plus contingency' authorization required
Authorize Professional Consulting Services $100,660 or less Greater than$100,000
Consultant Technical Consulting Services. $100,000 or less Greater than$106,000
Contracts Professional Eng.Services. $100,000 or less Greater than$100,DDO
Allocate funds from program contingency accounts o $100,000 or less per Greater than$100,000
projects not included in the CIB projecP
Individual equipment items and equipment contingency in Up o amount Above amount
the Equipment Budget specified in specified in Equipment
Equipment Budget Budget including
including contingency contingency
Individual equipment items not in the Equipment Budget $50,006 or less Greater than$50,000
Authorize supplemental funds to program budgets/ Not applicable Sewer Construction
contingency,accounts Fund balance
Allocate funds or project budget overruns after award of 15%of final project Greater than 15%of
construction contract budget'22 or up to final project budget3 or
maximum of above$1,060.600
$1,000,006 per madmum per project
project whichever is
less
Award construction contract $100,000 or less Greater than$100,000
Authorize Additive $100,001 or less Greater than 100,630
construction
change orders Deductive No limit No Board
authorization required
Subcontractor substitutions All substitutions Substitutions protested
unless protested by by subcontraMr
subcontractor
Construction project acceptance All projects Informational
announcement to the
Board
Close out project All projects Memo provided to the
Board at end of FY
'Limited by the remaining balances of the applicable program budget and contingency account
'Limited by the remaining balance of the applicable program contingency account
3Final project budget is established at time of award of construction contract
4 Bid protests and rejection of all bids must go to Board regardless of dollar amount
PROPOSED MODIFICATIONS
Table Capital Improvement Program Authorization Limits
Action General Manager Board of
Directors
Approve Capital Plant None No6mt
Au horde Capital Program budgets Note No knrt
Transfer funds to indmdual orosd buMMA. ILI.Oo3 ori+`4aam; No Inrtt NaP,we
:k."" _49-W
Professional Consulting Services $100,000 a less Greater than$1 DOM!)
Author
Cu LAW Techneal Consulting Services. $100,000 o les Greater manSID0,000
Contracts
Professional Eng.Services. $100,000o1ess Greater than$100,000
T.•a^sferaieca;e funds from CIE^.-,-.^^^^tirgencf 9100.000or less per Greater than$1 XWO
aoWuflta to projects notelduded n the GIB project,
Indnduel u t nems and n up to amount speared m Above amount spedrstl ot
eq Amen equvpment avttegeaxy Equpnent Budget Equipment Budget
the C-quipmenl Budget _
awag-r�atya.e+ -
Individual egwpment new not m the Equ¢tment Budget S50,D)0 or less Greeter man 550,000
Aut ori supplemefnal turas toprogram budgets No ka0le tion Sewer ConstrucFund
snu:x+ntagene,a.',Jnd__,,...a_„- ...;,;,.,. aPP balance
pydgg s
r-r-
Awardconstrudion contracts- 6100,0000IM GreatermanS100,Osv
Audo¢e Addnw $100,000or ss Grealerdw 5100,000
Wnstructlnn
dmV orders Dedw,tive No limit No Board authontabon
reguned
subcontractor substhu[iors Al substi utons unless Substitutions protested by
protested by subcontractor subcontra^tor
If formations
Construction procto acceptance Al projects anrauncernem to the
Board
Close out Wopa All Pqeds Memo provided tome
Board at end of FY
t Limited by the remaining balances of the applicable program and contingency account
Z Limited by the remaining balance of the applicable praexamcontingency account
budget is
_Bid protests and rejection of all bids must go to Board regardless of dollar amount
'- 1
PROPOSED NEW AUTHORIZATION LIMITS
Capital Improvement Program Authorization Limits
Action General Manager Board of
Directors
Approve Capital Plan Now No limit
Authorize Capital Program budgets None No lmft
Transfer funds to individual project budgets 550,E or less' No limit
Professional Consulting Services $100,000 or less Greater than 9100,D0
Authorize
'Ons Technical Consulting Services. 5100,000 or less Greater than 8100,D00
Contracts
Professional Eng.Services. S100,IXHi or less Greater than$100,=
Transterfunds from ClBmntingency account to projects not $100,OD0 or lass per
�z Greater than$1�0,03D
included in the CIB pro
Individual equipment dems and equipment contingency in Up to amount specified in Above amount specified In
the Equipment Budget Equipment Budget Equipment Budget
Individual equipment items not in the Equipment Budget $50,0100 or less Greater than 550,0W
Authorize supplemental irk to program budgets Not applicable Sewer Construction Furl
and oontgency account balance
Award oonstruction comracts� SIX=or lam Greater than S100,0DO
Authorize Additive SIX=orless Greater than$100,0M
construction
charge orders Deductive No IM No Board aunarrzation
required
Subcontractor substitutions AN substitutions unless Substitutions protested by
protested by subcontractor subcontractor
Informational
Con"Zion project acceptance All projects announcement to the
Board
Close outproject All projects Memo provided to the
Board at end of FY
1 Limited by the remaining balances of the applicable program and contingency account
Z Limited bythe remaining balance of the applicable contingency account
3 Bid protests and rejection of all bids must go to Board regardless of dollar amount '